AIC AO study materials
AIC AO study resources

AIC AO study plan

AIC AO · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Materials, Methods, and Project Modeling and Design & Planning, Scheduling, and Schedule Control

  • Map the AIA A201 and A101 general conditions clauses to the project delivery sequence, annotating which contract article governs design, bidding, construction, and closeout.

  • Build a one-page comparison of design-bid-build, design-build, and CM at-risk showing where cost certainty, schedule risk, and owner control shift between delivery methods.

  • Draft a work breakdown structure for a hypothetical 40,000 sq ft commercial building down to level-three activities, then code each activity to a CSI MasterFormat division.

  • Sequence the WBS into a precedence diagram and identify the critical path by hand, documenting total float for at least five non-critical chains.

Your checkpoint

A 10-15 page study packet containing the contract-clause map, delivery-method comparison table, and a hand-calculated CPM network with critical path and float values labeled.

Week 2

Materials, Methods, and Project Modeling and Design & Planning, Scheduling, and Schedule Control

  • Compute schedule durations from production rates for concrete formwork, structural steel erection, and drywall hanging, showing crew-size assumptions and productivity factors.

  • Explain how to compress a schedule through crashing and fast-tracking, and calculate the cost slope for three crash options to justify the least-cost acceleration.

  • Describe the submittal, RFI, and change-order workflows and state which schedule activities each one typically gates.

  • Interpret a baseline-versus-actual schedule update and calculate schedule variance in days and earned schedule metrics.

Your checkpoint

A schedule-analysis worksheet with three crash cost-slope calculations, one worked earned-schedule example, and a written recommendation on which acceleration option to pursue.

Week 3

Bidding and Estimating & Budgeting, Costs, and Cost Control

  • Assemble a quantity takeoff for concrete, masonry, and rough carpentry from a written scope description, showing measurement rules and waste factors for each line.

  • Build a unit-price estimate by applying labor, material, and equipment rates to the takeoff, then add crew-based labor burden and sales tax by line item.

  • Structure a bid into direct costs, indirect costs, overhead, contingency, and profit, and explain how each layer is typically applied.

  • Compare lump-sum, unit-price, cost-plus-fee, and GMP contract types on risk allocation and how each shapes the estimate.

Your checkpoint

A complete bid package for a sample scope: takeoff sheets, priced estimate with burden and markup, and a one-page bid-summary letter with stated qualifications and exclusions.

Week 4

Budgeting, Costs, and Cost Control & Management Concepts

  • Convert an estimate into a project budget broken down by cost code, and establish a schedule of values that matches the billing structure.

  • Calculate earned value metrics (CPI, SPI, EAC, VAC) from a provided cost-and-schedule dataset and interpret what each result signals to management.

  • Describe how a general contractor tracks committed versus incurred versus forecast costs and explain the role of a cost report in monthly project review.

  • Explain how to manage retainage, lien waivers, and pay applications so that cash flow stays positive through the project.

Your checkpoint

A monthly cost report for the sample project containing budget-versus-actual by cost code, earned value calculations, forecast-to-complete, and a written variance narrative.

Week 5

Engineering Concepts & Construction Safety

  • Explain structural load paths and how gravity and lateral systems transfer to foundations, and identify which engineering discipline owns each decision on a typical project.

  • Describe the roles of mechanical, electrical, and plumbing systems in coordination and explain why clash detection matters before installation.

  • Build a site-specific safety plan outline covering the OSHA Focus Four hazards with the abatement measure for each.

  • Explain the competent-person concept, the hierarchy of controls, and how a pre-task safety meeting and job hazard analysis fit into daily operations.

Your checkpoint

A 6-10 page site-specific safety plan outline with the Focus Four hazard table and a completed job hazard analysis for one high-risk activity such as steel erection or trenching.

Week 6

Communication Skills & Project Administration

  • Draft a meeting agenda, minutes, and action-item log for a weekly owner-architect-contractor meeting, and practice running a 30-minute mock meeting with a colleague or recording.

  • Write three types of project correspondence: an RFI, a notice of a differing site condition, and a formal delay notice, each citing the governing contract clause.

  • Explain the document control lifecycle for submittals, shop drawings, and as-builts, and describe how document retention supports claims defense.

  • Describe how project closeout is administered, including punch list, substantial completion, final payment, and warranty turnover.

Your checkpoint

A communication portfolio containing one agenda, one set of minutes with action log, three drafted letters (RFI, differing site condition notice, delay notice), and a closeout checklist.

Week 7

Management Concepts & Communication Skills

  • Compare leadership styles and explain when directive versus participative approaches suit a construction team, using a scenario to justify the choice.

  • Describe how to build and motivate a project team, including delegation, accountability, and conflict resolution between field and office staff.

  • Explain the roles and responsibilities of owner, architect/engineer, contractor, and subcontractors, and identify where authority and liability overlap.

  • Practice answering scenario-based questions on ethics, negotiation, and team conflict by writing out structured responses using a situation-action-result format.

Your checkpoint

A written response bank of 10 scenario questions on leadership, team dynamics, and ethics, each answered in structured paragraph form with a stated decision and rationale.

Week 8

Materials, Methods, and Project Modeling and Design & Bidding and Estimating & Budgeting, Costs, and Cost Control & Planning, Scheduling, and Schedule Control & Construction Safety & Project Administration & Communication Skills & Engineering Concepts & Management Concepts

  • Consolidate all domain notes into a single indexed reference sheet capped at 20 pages, organized by exam domain with cross-references.

  • Complete two full-length timed practice sets under exam conditions and score each by domain to identify remaining weak areas.

  • Re-drill the two lowest-scoring domains with targeted review and rewrite the affected reference-sheet sections.

  • Rehearse the highest-yield calculations (CPM float, earned value, crash cost slope, unit-price markup) from memory until each is completed accurately within three minutes.

Your checkpoint

A final 20-page indexed reference sheet, two scored practice-set results with a domain-by-domain gap analysis, and a one-page exam-day strategy sheet covering pacing and question triage.

Milestones

Week 2: Can build a CPM network by hand and correctly identify the critical path and total float on a fresh 15-activity problem in under 20 minutes.

Week 4: Can produce a priced estimate and a monthly cost report with correct earned value metrics, and explain each variance in writing without notes.

Week 6: Can draft an RFI, delay notice, and meeting minutes that each cite the correct contract clause, and score at least 70% on a mixed 40-question practice set across domains 1, 5, 6, and 9.

Week 8: Scores at or above 75% on two full-length timed practice sets, with no single domain below 60%, and completes all four core calculations accurately within three minutes each.