AIC AO: Management Concepts

AIC AO · Work through your exam, one topic at a time.

All guide sections

Management Concepts

Management Concepts tests project delivery, organizational behavior, leadership, contract risk allocation, quality management, and ethics. Questions ask you to choose the management approach that best fits the owner's priorities and the project's constraints.

Core rules

  • Design-bid-build separates design and construction and usually selects by low bid; it gives the owner more design control but takes longer and creates more interfaces.
  • Design-build gives a single point of responsibility and can speed delivery, but the owner gives up some design control.
  • Construction manager at risk (CMAR) provides preconstruction services and a guaranteed maximum price; CM agency acts as the owner's agent and does not hold trade contracts.
  • Lump-sum contracts place quantity risk on the contractor; unit-price contracts pay for measured quantities; cost-plus contracts shift cost risk to the owner.
  • Authority should match responsibility. A project manager coordinates scope, cost, and time; a superintendent directs field operations.
  • Motivation theory: Herzberg separates hygiene factors (pay, conditions) from motivators (achievement, recognition). Maslow's hierarchy is not a rigid checklist.

Worked example. An owner needs a new distribution center quickly, wants one party accountable for design and construction, and is willing to accept fewer design changes. Design-build is the best fit. It compresses schedule through overlap and gives single-point responsibility, but the owner must define performance requirements clearly and control changes through the contract.

Traps

  • Confusing CM agency with CM at risk.
  • Assuming the lowest bid is always the best value.
  • Treating a matrix organization as having no reporting conflict.
  • Applying motivation theory as if one factor always dominates.