AIC AO: Planning, Scheduling, and Schedule Control

AIC AO · Work through your exam, one topic at a time.

All guide sections

Planning, Scheduling, and Schedule Control

Planning, Scheduling, and Schedule Control tests work breakdown, activity sequencing, critical path method, float, resource management, and delay analysis. Expect network logic and schedule-update questions.

Core rules

  • A work breakdown structure decomposes scope into manageable work packages. Activities have durations, dependencies, and calendars.
  • Dependencies include finish-to-start, start-to-start, finish-to-finish, and start-to-finish. Lag adds time; lead overlaps.
  • The forward pass gives early dates; the backward pass gives late dates. Total float = LS - ES = LF - EF. Critical path has zero total float.
  • Free float is the time an activity can slip without delaying the next activity. Total float is slip without delaying project completion.
  • Resource leveling may change the critical path; crashing adds resources and cost; fast-tracking overlaps phases and increases risk.
  • Schedule control compares planned versus actual, updates logic and durations, and documents delays.

Worked example. Path A-B-C is 3 + 4 + 2 = 9 days. Path A-D-C is 3 + 5 + 2 = 10 days. The critical path is A-D-C at 10 days. Activity B has total float of 1 day. If B slips 2 days, path A-B-C becomes 11 days and the critical path shifts. The scheduler must re-run the network, not just note the slip.

Traps

  • Confusing total float with free float.
  • Ignoring calendar days versus workdays.
  • Forgetting lag or lead in the network.
  • Crashing a noncritical activity and expecting schedule savings.
  • Updating the bar chart without updating logic.