BSEH Secondary NSQF Construction study materials
BSEH Secondary NSQF Construction study resources

BSEH Secondary NSQF Construction study plan

BSEH Secondary NSQF Construction · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Masonry and Concreting Works & Construction Materials and Their Properties

  • Distinguish the five main grades of ordinary Portland-type cement by their typical use cases and list two field clues for each

  • Explain how water-cement ratio, curing duration and aggregate grading each change the strength and workability of a concrete mix

  • Sequence the steps of brick masonry in English bond and state the purpose of each step from soaking to pointing

  • Name four defects in fresh or hardened concrete (segregation, bleeding, honeycombing, shrinkage cracking) and give one corrective action per defect

  • Compute the cement, sand and coarse aggregate quantities for a nominal 1:2:4 mix of a stated volume using dry-volume factor 1.54

Your checkpoint

A one-page concrete and masonry cheat sheet with mix ratios, curing times, brick bonds and defect-fix pairs, plus two fully worked quantity calculations

Week 2

Masonry and Concreting Works & Building Drawing, Measurement and Estimation

  • Describe the formwork, reinforcement and placing sequence for a reinforced concrete slab and a column, including stripping times

  • Interpret a simple plan and section drawing well enough to read wall thickness, door and window sizes, and floor levels

  • Measure lengths and areas from a scaled plan and convert them to cubic quantities for excavation and concrete

  • Explain the purpose and typical spacing of main and distribution reinforcement in a one-way slab

  • Prepare a short bar-bending schedule for a rectangular slab given bar diameter, spacing and cover

Your checkpoint

A hand-sketched plan of a single-room structure with a measurement sheet and a bar-bending schedule for its slab

Week 3

Construction Materials and Their Properties & Carpentry, Joinery and Woodwork

  • Compare the properties and typical uses of bricks, concrete blocks, stone, timber, plywood, glass and steel sections

  • Classify common timber types by hardness and durability, and state where each is appropriate in a building

  • Identify the main woodworking joints (mortise and tenon, dovetail, half-lap, housing) and describe the load or use each suits

  • Explain seasoning of timber, its moisture-content target and how it prevents warping and shrinkage

  • List the standard sizes and grades of plywood and describe the glue lines and face grades that affect use

Your checkpoint

A two-column comparison table of ten construction materials with properties, typical uses and one limitation each, plus a labelled sketch of four wood joints

Week 4

Hand Tools, Power Tools and Equipment & Construction Safety, Health and Environment

  • Match twenty hand and power tools to their correct use and state one misuse per family of tools

  • Describe safe handling and inspection routines for a circular saw, an angle grinder and a drilling machine

  • Explain the hierarchy of hazard control and apply it to three construction hazards such as falls, silica dust and electrical contact

  • State the correct use of personal protective equipment for cutting, mixing, welding and working at height

  • Outline first-aid and emergency response steps for a fall, an electric shock and a chemical splash

Your checkpoint

A tool safety card for five power tools with pre-use checks, PPE required and two common misuse examples, plus a hazard-control table for three site hazards

Week 5

Construction Safety, Health and Environment & Finishing Works (Plastering, Painting, Flooring, Tiling)

  • Describe safe storage, handling and disposal of cement, paints, solvents and adhesives, including ventilation and fire precautions

  • Sequence a plastering operation from surface preparation to curing and state the mix and thickness for undercoat and finish coats

  • Explain the causes of common plaster defects such as crazing, blistering and efflorescence, with one remedy each

  • Describe surface preparation and coat sequence for painting on plaster, wood and metal surfaces

  • Outline tile and flooring laying steps, including bedding, joint width, levelling and grouting

Your checkpoint

A finishing works checklist covering plaster, paint and tiling, with defect-cause-remedy entries and a waste disposal note for each material

Week 6

Plumbing, Sanitary and Water Supply Works & Electrical Wiring and Fittings in Buildings

  • Trace a cold water supply layout from source to fixture and explain the role of storage tank, pump, valve and air gap

  • Describe the layout and gradient requirements of a soil and waste drainage system, including traps and vent pipes

  • Identify common sanitary fittings and state the flow or connection requirement of each

  • Explain the basic wiring of a lighting circuit and a socket circuit, including live, neutral and earth conductors and their colour conventions

  • State the purpose of earthing, miniature circuit breakers and residual current devices, and describe one test for each

Your checkpoint

A hand-drawn single-line diagram of the water supply and drainage of a two-room unit plus a labelled lighting and socket circuit diagram with protective devices marked

Week 7

Building Drawing, Measurement and Estimation & Carpentry, Joinery and Woodwork

  • Prepare a rate analysis for one cubic metre of brick masonry and one square metre of plastering using material and labour components

  • Build a simple bill of quantities for a small building from a measured sheet with units and quantities clearly stated

  • Explain the difference between a detailed estimate, an approximate estimate and a revised estimate

  • Describe the sequence of carpentry work for a door frame and shutter, from marking to fixing and finishing

  • List the checks for a finished door or window installation covering squareness, clearance, hinges and locking

Your checkpoint

A complete mini estimate for one room including quantities, rate analysis for two items and a total cost summary

Week 8

Employability Skills and Entrepreneurship & Construction Safety, Health and Environment & Masonry and Concreting Works

  • Draft a short business idea for a small construction service, stating customer, cost, price and one risk

  • Explain the importance of communication, teamwork and time management on a construction site with one example each

  • Revise the weakest two domains using timed practice sets and record the accuracy of each attempt

  • Recite the key safety, mix-design and measurement facts from weeks one to seven without notes

  • Build a final one-page summary sheet linking safety, materials and measurement decisions across a project

Your checkpoint

A one-page business idea sheet plus a full-length timed mock test with a scored error log identifying two weak areas and a revision action for each

Milestones

Week 2: Can compute concrete quantities for a given volume from a nominal mix and read dimensions off a scaled plan without error in five out of five practice items

Week 4: Scores at least 70 percent on a 30-question set drawn from domains 1, 2, 3 and 5, and can name the control measure for three site hazards unaided

Week 6: Draws the water supply, drainage and basic electrical circuits of a small unit from memory with correct symbols and protective devices labelled

Week 7: Produces a bill of quantities and rate analysis with arithmetic checked twice and no unit mismatch between measurement sheet and estimate

Week 8: Completes a full-length timed mock at or above the target pass mark, with an error log covering every wrong answer and a dated revision plan