The Odisha CHSE +2 Plumber General (VOC-ITV) is a higher secondary vocational qualification under the Council of Higher Secondary Education, Odisha, delivered through the Vocational (ITV) stream. It suits students who want a school-leaving credential combined with employable trade skills in plumbing, rather than a purely academic +2 route. The Odisha CHSE +2 Plumber General (VOC-ITV) case studies are 5 cases and about 5,498 words.

1

Trench for a sewer connection on a busy footpath

A two-man team is connecting a 110 mm PVC house drain to the municipal sewer on the footpath of a busy lane in Cuttack. The sewer invert is 1.6 m below ground, so the trench has to be about 1.8 m deep and 0.8 m wide.

830 words, about 4 min
2

First-floor taps starved in a three-storey house

A three-storeyed house in Bhubaneswar has a 1000 litre HDPE tank on a 1.2 m stand on the roof terrace, with the terrace about 9.5 m above ground level. The service connection is an old 20 mm (3/4 inch) galvanised iron pipe, about 18 m long, with a stopcock at the boundary and a 15 mm gate valve near the tank.

1,094 words, about 5 min
3

Sewer smell and gurgling in a new ground-floor toilet

The ground-floor toilet of a two-year-old house in Sambalpur develops a strong sewer smell, worst in the evening, and the floor trap drains away slowly. After each use a ring of water remains in the trap and disappears within about ten minutes.

1,155 words, about 6 min
4

Pinhole leaks in a hotel's CPVC hot water line

A 40-bed hotel in Puri has a 20 mm CPVC hot water line running 22 m from the boiler room to the first-floor bathrooms, carrying water at about 65 degrees Celsius and 3 bar. Six months after commissioning, four pinhole leaks appeared within a 3 m stretch of straight pipe.

1,181 words, about 6 min
5

A running bill that does not match the site measurement

A contractor has been awarded a six-cubicle toilet block for a government high school. The approved specification requires 110 mm PVC SWR pipe of 3 kg/cm2 class for the drain, laid at 1 in 60, with one 110 mm vent stack carried 2 m above the roof and FRP inspection chamber covers.