Odisha CHSE +2 Plumber General (VOC-ITV): Pipe Joining, Fabrication and Installation

Odisha CHSE +2 Plumber General (VOC-ITV) · Work through your exam, one topic at a time.

All guide sections

Pipe Joining, Fabrication and Installation

Scope

This domain tests threaded, solvent-welded, compression, flanged, welded and push-fit joints, plus cutting, bending, support and pressure testing. The exam focuses on joint preparation and cure times.

Core rules

  • Cut square, deburr and clean the pipe end before joining.
  • Threaded joints: use the correct die, apply PTFE tape 3–4 turns in the thread direction or an approved sealant, and do not over-tighten.
  • Solvent-welded UPVC: clean, apply primer, apply cement evenly, push fully, quarter-turn and hold; allow the specified cure before testing.
  • Flanged joints: use a matching gasket, align the flanges and tighten bolts in a star pattern.
  • Support pipes at specified spacing; allow expansion and contraction.
  • Pressure-test the completed section before concealment.

Worked example

Join two 50 mm UPVC pipes. Cut square, chamfer and clean the ends; mark insertion depth; apply primer to both surfaces; apply cement while wet; push fully and quarter-turn; hold about 30 seconds; wipe excess; allow the recommended cure before filling. Reason: primer softens the surface, cement fuses it, and the quarter-turn spreads cement without trapping air.

Traps

Skipping primer; too much cement; testing immediately; misaligned flanges; over-tightening plastic threads; no support.