FCI AGM Phase I: Professional Knowledge: Procurement, Distribution and Supply Chain Management

FCI AGM Phase I · Work through your exam, one topic at a time.

All guide sections

Professional Knowledge: Procurement, Distribution and Supply Chain Management

Procurement, Distribution and Supply Chain Management tests purchasing methods, public procurement discipline, buffer-stock operations, PDS logistics, inventory control and distribution performance.

Core rules

  • Procurement cycle: need identification, specification, sourcing, tender or quotation, evaluation, award, contract, receipt and payment.
  • Public procurement must follow transparency, competition and value for money; lowest price is not always lowest total cost.
  • FCI operations involve MSP-based procurement, buffer stock norms, warehouse receipt, quality checks and PDS movement.
  • Inventory: EOQ balances ordering and holding costs. Reorder point = demand during lead time + safety stock.
  • Distribution: plan mode, route, loadability and cold-chain or dry-storage requirements; monitor lead time, fill rate and stock-outs.

Worked example

Daily demand is 200 bags. Lead time is 5 days. Safety stock is 300 bags. Find the reorder point.

Demand during lead time = 200 × 5 = 1000 bags. Reorder point = 1000 + 300 = 1300 bags. Order when stock reaches 1300 bags. Using only 1000 ignores demand variability and delays during replenishment; using safety stock alone ignores normal lead-time consumption.

Traps

  • Confusing EOQ, which minimizes total ordering and holding cost, with the reorder point.
  • Selecting the lowest bid without landed cost, quality and delivery reliability.
  • Forgetting that safety stock responds to variability and service level, not average demand alone.
  • Treating procurement as a one-time purchase rather than a contract and supplier-performance cycle.