ITI/NCVT Mason Building Constructor (AITT Theory) study materials
ITI/NCVT Mason Building Constructor (AITT Theory) study resources

ITI/NCVT Mason Building Constructor (AITT Theory) cheat sheet

ITI/NCVT Mason Building Constructor (AITT Theory) · Keep the key ideas within reach.

Quick reference

Trade Safety, Health and Environment

  • Fall protection is required at heights of 1.8 m or more; guardrails consist of a top rail at 1.0 m, a mid rail at 0.5 m and a 150 mm toe board.

  • A scaffold platform must be at least 450 mm wide when used for men and materials, fully planked with no gap greater than 25 mm.

  • Excavations deeper than 1.5 m require shoring, benching or battering; inspection by a competent person is required before each shift.

  • Safe manual lifting limit for one worker is about 20 kg at waist height; heavier loads need two persons or mechanical aid.

  • Ladder inclination is 1 in 4 (about 75 degrees); the ladder must extend 1.0 m above the landing platform.

  • Silica dust from cutting concrete or bricks requires wet cutting or local exhaust ventilation plus a P2/P3 respirator.

  • Portland cement is alkaline (pH about 12-13); eye contact requires immediate flushing with clean water for at least 15 minutes.

  • Electrical tools on site operate at 230 V single phase; use 110 V CTE or RCD-protected supply in wet or confined conditions.

Quick reference

Materials

  • Standard burnt clay brick: 190 x 90 x 90 mm modular or 230 x 110 x 70 mm traditional; water absorption should not exceed 20 percent by mass.

  • Brick compressive strength classes run from 3.5 to 35 N/mm2; a first-class brick gives not less than 10 N/mm2 and has a sharp, ringing sound.

  • Ordinary Portland cement 33/43/53 grade denotes 28-day compressive strength in N/mm2 of a 1:3 mortar cube.

  • Cement should be stored on a dry platform, stacked not more than 8 bags high, and used within 3 months of manufacture.

  • Sand for mortar is fine aggregate passing a 4.75 mm sieve; silt and clay content should not exceed 5 percent for good bond.

  • Aggregate for concrete: fine 4.75 mm and below, coarse 20 mm nominal for normal RCC work, 40 mm for mass concrete.

  • Lime for mortar is slaked quicklime; hydraulic lime sets under water, fat lime requires air and hardens by carbonation.

  • Water for concrete and mortar must be clean and free of oil, acid, alkali and organic matter; potable water is acceptable.

Quick reference

Tools and Equipment for Masonry

  • A trowel blade is typically 250-300 mm long; the brick trowel lays mortar, the pointing trowel (about 150 mm) finishes joints.

  • A 600 mm spirit level reads the bubble between lines for level; a plumb bob or plumb rule transfers verticality over 1.5-2 m.

  • A mason's square checks 90-degree corners; the 3-4-5 method (or multiples) sets out a right angle on the ground.

  • A bolster and club hammer cut bricks and blocks; a cold chisel cuts mortar joints during repair and chasing.

  • A hawk holds mortar while the trowel picks it up; a mortar board is the flat working surface on the scaffold.

  • A jointer or pointing tool forms weather-struck or bucket-handle joints; a raking tool removes mortar for pointing depth.

  • A line and pins stretched between profiles controls courses; line blocks keep the line taut and offset from the face.

  • A concrete mixer drum capacity is quoted in litres of mixed output; a half-bag mixer is about 100-120 litres per batch.

Quick reference

Masonry Bonds

  • Stretcher bond: all bricks laid as stretchers, half-brick overlap, used for half-brick (115 mm) walls and cavity leaves.

  • English bond alternates a header course and a stretcher course; strongest traditional bond, no continuous vertical joint.

  • Flemish bond alternates stretcher and header in every course; more decorative than English bond but weaker in compression.

  • Header bond uses headers only with three-quarter bats at corners; used for curved work and footings of one-brick walls.

  • English garden wall bond has three stretcher courses to one header course; economical for one-brick walls.

  • Quetta bond uses bricks on edge with voids filled by concrete; used for 350 mm and thicker walls in seismic areas.

  • Raking bond (herringbone or diagonal) is used to bond facing to backing and to distribute load in thick walls.

  • Rule for bonding: vertical joints in alternate courses must not align; minimum lap is one-quarter brick (about 57 mm).

Quick reference

Brick and Block Work

  • AAC block density is about 550-650 kg/m3 against 1800-2000 kg/m3 for burnt clay brick, reducing dead load.

  • AAC blocks absorb water readily; use a thin-bed adhesive mortar of 2-3 mm rather than a 10 mm cement mortar joint.

  • A brick wall should be raised not more than 1.0-1.5 m in a day to avoid mortar squeeze-out and loss of plumb.

  • Wetting of bricks before laying is required for dry, porous bricks so mortar water is not absorbed; do not soak.

  • Quoins are the corner bricks; toothing is the stepped end of a wall left for future bonding, one-quarter brick per course.

  • Cavity wall: two leaves of 100 mm separated by a 50-75 mm cavity, tied with wall ties at 450 mm vertical and 900 mm horizontal.

  • Wall ties in a cavity must slope slightly outward and downward so any water drains to the outer leaf.

  • Reinforcement: horizontal ladder or truss mesh in bed joints at 400-600 mm vertical spacing controls shrinkage cracking.

Quick reference

Mortar

  • Mortar grades: M (1:3), S (1:4), N (1:6), O (1:8) cement:sand by volume; higher cement gives higher strength and lower workability.

  • Mortar cube strength at 28 days: 1:3 cement mortar about 10 N/mm2, 1:6 about 5 N/mm2, 1:8 about 3 N/mm2.

  • Lime or plasticiser is added to improve workability and water retention; over-plasticising reduces bond strength.

  • Mortar should be used within 2 hours of mixing in hot weather and within 3 hours in cool weather; never re-temper.

  • Fat mortar is rich in lime and buttery; lean mortar is sandy and harsh; the correct mix is workable but not sticky.

  • Mortar joint thickness for brickwork is 10 mm; for thin-bed blockwork 2-3 mm with adhesive.

  • Water retentivity is the ability of mortar to retain water against suction of the masonry unit; low retention causes poor bond.

  • For repointing, use a mortar weaker than the original masonry so the joint, not the brick, absorbs movement.

Quick reference

Concrete and Plastering

  • Nominal concrete mixes: 1:3:6 (M10), 1:2:4 (M15), 1:1.5:3 (M20); water-cement ratio typically 0.45-0.55 by mass.

  • Concrete cube strength at 28 days is the design criterion; M20 means 20 N/mm2 characteristic cube strength.

  • Slump test measures workability: 25-75 mm for normal RCC, 75-125 mm for pumped or heavily reinforced sections.

  • Compaction by needle vibrator: insert vertically, withdraw slowly, spacing about 1.5 times the radius of action, avoid over-vibration.

  • Curing: keep concrete moist for at least 7 days for OPC, 10-14 days for blended cement or hot weather.

  • Plaster mix: 1:6 cement:sand for internal, 1:4 for external; thickness 12 mm for undercoat, 6 mm for finishing coat.

  • Plaster should be applied in coats, each scratched for key; do not exceed 15 mm total thickness in one coat.

  • Internal plaster is often 1:1:6 cement:lime:sand; lime improves workability and reduces shrinkage cracking.

Quick reference

Drawing, Setting Out and Levelling

  • Scale 1:100 means 1 mm on the drawing equals 100 mm on site; 1:50 doubles the detail size.

  • A site plan shows boundaries, building position, levels and services; a foundation plan shows footings and column positions.

  • Setting out: establish two base lines at right angles using 3-4-5, then offset with profiles and string lines.

  • A dumpy level with a staff measures reduced levels; the height of instrument equals backsight plus known reduced level.

  • Reduced level of a point equals height of instrument minus the foresight reading on that point.

  • A level survey closes with a check: sum of backsights minus sum of foresights equals last RL minus first RL.

  • A theodolite or total station sets out angles and distances; a total station records horizontal distance, vertical angle and coordinates.

  • Grid lines and centre lines are marked with nails or pegs and protected by offset pegs beyond the excavation.

Quick reference

Foundations

  • Minimum depth of foundation is 0.9-1.0 m below natural ground level or below the zone of seasonal moisture change.

  • Safe bearing capacity of good soil is about 150-250 kN/m2; soft clay may be 50 kN/m2 or less.

  • Isolated footing carries a single column; a combined footing carries two columns; a raft spreads load over the whole area.

  • Pile foundations are used when soil bearing is poor or loads are heavy; end-bearing piles reach a hard stratum, friction piles rely on skin friction.

  • Concrete for footings is usually M15-M20 with 40-50 mm cover against earth; reinforcement cover in footings at least 50 mm.

  • Damp-proof course (DPC) is laid at plinth level, minimum 150 mm above ground, continuous and lapped 100 mm at joints.

  • Anti-termite treatment is applied to the soil, along the wall line and at junctions before and after laying the floor.

  • Under-reamed piles are used in expansive black cotton soil to resist uplift and swelling pressure.

Quick reference

Walls and Structural Elements

  • Load-bearing wall thickness: half-brick (115 mm) for partition, one-brick (230 mm) for main walls, 1.5-brick (345 mm) for heavy loads.

  • Slenderness ratio of a wall is effective height or length divided by thickness; limit is about 27 for unreinforced masonry.

  • A column carries axial compression; a beam carries bending and shear; a lintel spans an opening and carries the wall above.

  • A pier is a thickened section of wall projecting on one or both faces, used to stiffen a long or high wall.

  • A buttress is an external pier built against a wall to resist lateral thrust, often with a battered face.

  • Reinforced concrete columns in masonry require a minimum of 4 bars of 12 mm diameter and ties at 150-200 mm spacing.

  • A plinth is the portion of wall between ground and floor level; a sill is the lower member of a window opening.

  • Expansion joints in long walls are provided at 20-30 m intervals to accommodate thermal movement.

Quick reference

Arches, Lintels, Stairs and Roofing

  • Arch terms: span is the clear opening, rise is the height from springing line to crown, intrados is the inner curve, extrados the outer.

  • Semicircular arch rise equals half the span; segmental arch rise is less than half the span; flat arch has a slight rise.

  • A relieving arch transfers load around an opening; a lintel is a horizontal beam over an opening.

  • Lintel bearing is typically 100-150 mm on each side of the opening; a lintel carries the wall above it, not the roof load unless designed.

  • Stair terms: rise is the vertical height of one step, tread the horizontal going; 2R + T is about 600-640 mm for comfortable climbing.

  • Common stair proportions: rise 150-190 mm, tread 250-300 mm, width of stair 900-1200 mm, headroom at least 2100 mm.

  • Roof pitch for country tiles is 30-40 degrees; for plain tiles 40-45 degrees; corrugated sheet minimum pitch about 10 degrees.

  • Roof terms: ridge is the top line, eaves the lower edge, verge the gable edge, hip the sloping edge, valley the internal intersection.

Quick reference

Flooring, Tiling and Finishing

  • Floor finishes: cement concrete 1:2:4 base with 1:2 cement mortar topping of 20-25 mm, or IPS 40 mm thick.

  • Tile adhesive coverage is checked by lifting a tile; minimum 80 percent coverage in dry areas and 95 percent in wet areas.

  • Ceramic tile joint width is 2-3 mm with grout; expansion joints every 6-8 m and at the perimeter.

  • Vitrified tiles have water absorption below 0.5 percent; ceramic tiles 3-10 percent; use the correct adhesive for each.

  • Skirting height is typically 100-150 mm; dado height in bathrooms 1200-1500 mm above floor.

  • Marble and granite are laid on a 20-30 mm cement mortar bed with slurry backing; joints are filled with matching grout.

  • A level floor is checked with a 3 m straight edge; allowable deviation is about 3 mm in 3 m.

  • Wood flooring requires a moisture content of 8-12 percent and a ventilated void or underlay beneath it.

Quick reference

Estimation, Measurement and Costing

  • Brickwork is measured in cubic metres; volume equals length times height times thickness, with deductions for openings over 0.1 m2.

  • Plaster is measured in square metres; deduct openings over 0.5 m2 and add for reveals and jambs.

  • Concrete is measured in cubic metres; formwork in square metres of contact area; reinforcement in kilograms or tonnes.

  • Standard brick count: 500 bricks per cubic metre of brickwork (with 10 mm joints, 190x90x90 mm brick).

  • Mortar for brickwork: about 0.30 m3 of wet mortar per cubic metre of brickwork; add 33 percent for dry volume.

  • Dry volume of mortar equals wet volume times 1.30-1.33 to allow for bulking and voids.

  • Rate analysis: cost per unit equals material cost plus labour cost plus plant plus overheads and profit (usually 10-15 percent).

  • Contingency in a preliminary estimate is 5-10 percent; a detailed estimate is prepared from drawings and a bill of quantities.

Quick reference

Maintenance, Repair and Waterproofing

  • Efflorescence is a white salt deposit; brush off dry, do not wash, and identify the water source causing it.

  • Cracks wider than 0.3 mm in masonry are grouted with cement slurry or epoxy; hairline cracks are raked and filled.

  • Repointing: rake out the joint to 15-20 mm depth, clean, wet and fill with fresh mortar in layers.

  • Waterproofing of a roof: brickbat coba, cement-based coating or membrane; a minimum slope of 1:100 to 1:80 to drains.

  • A waterproofing membrane must be turned up at parapets and walls by at least 150 mm.

  • Dampness in walls is treated by a DPC, a damp-proof membrane, or by injecting a silicone or cementitious damp course.

  • Grouting of cracks uses a low-viscosity epoxy or cement grout injected under pressure through ports.

  • Spalling of concrete is repaired by removing loose concrete, treating reinforcement for rust, and patching with polymer-modified mortar.

Quick reference

Employability Skills and Workplace Practice

  • A method statement describes the safe sequence of work; a risk assessment records hazards, likelihood and control measures.

  • A permit to work is required for hot work, confined spaces and work at height above 1.8 m.

  • A tool-box talk is a short briefing before work begins covering the task, hazards and controls.

  • Personal protective equipment: helmet, safety boots, gloves, eye protection, high-visibility vest, and hearing protection in noisy areas.

  • A bar chart shows activities against time; the critical path is the longest sequence of dependent activities.

  • Measurement sheets and daily progress reports record work done, labour, materials and plant used on site.

  • Under the Factories Act and Building and Other Construction Workers Act, the contractor must provide safety, welfare and first-aid facilities.

  • Communication on site uses standard terms: 'line', 'level', 'plumb', 'strike', 'tooth', and hand signals for crane operation.

Quick reference

Trade Safety, Health and Environment (continued)

  • Housekeeping: remove waste daily, keep walkways clear of 1.0 m minimum width, and stack materials at a stable height.

  • First aid: for a fracture, immobilise the limb and do not attempt to realign it; for burns, cool with water for 10-20 minutes.

  • Noise above 85 dB(A) over an 8-hour day requires hearing protection and a noise assessment.

  • Scaffold inspection is required before first use, at intervals not exceeding 7 days, and after alteration or bad weather.

Quick reference

Materials (continued)

  • Steel reinforcement grades: Fe415 and Fe500 denote yield strength in N/mm2; a 12 mm bar weighs 0.888 kg per metre.

  • Timber for shuttering should be seasoned to a moisture content of 12-15 percent to limit shrinkage and warping.

  • Glass is graded by thickness: 4-6 mm for ordinary glazing, 6-8 mm for larger panes; toughened glass is used in doors.

  • Bitumen grades 30/40, 60/70 and 80/100 denote penetration in tenths of a millimetre; 60/70 is common for waterproofing.

Quick reference

Tools and Equipment for Masonry (continued)

  • A concrete vibrator needle diameter 25-50 mm suits normal sections; a larger needle is used for mass concrete.

  • A plate compactor is used for compacting granular fill in layers of 150-200 mm.

  • A wall chaser or grinder with a diamond blade cuts chasing for conduits; depth should not exceed one-third of wall thickness.

  • A wheelbarrow holds about 0.05 m3 (50 litres); a head pan about 0.015 m3; use them for batching by volume.

Quick reference

Masonry Bonds (continued)

  • A queen closer is half a brick cut lengthwise; a king closer is a brick cut so one end is half width.

  • A bevelled closer is used at corners in Flemish bond to keep the face pattern correct.

  • A bat is a piece of brick cut across its width; a three-quarter bat is used at quoins and openings.

  • In a one-and-a-half-brick wall, the two leaves are bonded with headers or wall ties; English bond gives the strongest bond.

Quick reference

Brick and Block Work (continued)

  • Brick masonry in mud mortar is used in low-cost construction; cement mortar 1:6 is common for load-bearing walls.

  • A concrete block of 400x200x200 mm weighs about 18-20 kg; AAC block of the same size weighs about 8-10 kg.

  • Lintels over openings in brick walls bear 100-150 mm each side; a concrete lintel is often 100-150 mm deep.

  • A 'tooth' left for future work is one-quarter brick deep per course; a 'rack' is a straight vertical joint left for later bonding.

Quick reference

Mortar (continued)

  • Mortar for plastering is often 1:4 to 1:6 cement:sand; for masonry 1:6 is common for load-bearing walls.

  • Adding 10-15 percent lime by volume of cement improves workability and reduces cracking.

  • Water-cement ratio for mortar is about 0.5-0.6 by mass; too much water causes shrinkage and weak bond.

  • Mortar should be mixed on a clean, impervious surface or in a mechanical mixer for at least 2 minutes after all materials are added.

Quick reference

Concrete and Plastering (continued)

  • Concrete cover: 40 mm for slabs, 40 mm for beams, 50 mm for columns, 50-75 mm for footings in contact with earth.

  • Formwork is struck when concrete has gained sufficient strength: sides of beams after 24 hours, soffits of slabs after 7-14 days.

  • Plaster should be cured for at least 7 days; rapid drying causes shrinkage cracks and dusting.

  • A scratch coat (key coat) is 6-9 mm thick and scored to provide a mechanical key for the finishing coat.

Quick reference

Drawing, Setting Out and Levelling (continued)

  • A benchmark is a fixed reference of known reduced level; a temporary benchmark is established on site for the work.

  • Contour lines join points of equal level; the closer the lines, the steeper the slope.

  • A section drawing shows a vertical cut through the building; an elevation shows the external face.

  • A bar bending schedule lists bar mark, diameter, shape, length and number of bars for reinforcement.

Quick reference

Foundations (continued)

  • A trench fill foundation fills the excavation with concrete to a designed width and depth, saving formwork and labour.

  • A stepped footing spreads load from a wall in steps of 100-150 mm each side; the base width is designed from bearing capacity.

  • A grillage foundation uses steel beams in layers to spread heavy loads on weak soil.

  • Dewatering by pumping may be needed where the water table is above the foundation level; the excavation must be kept dry.

Quick reference

Walls and Structural Elements (continued)

  • A lintel over an opening carries the wall above; the wall above an arch is carried by the arch, so the lintel is not loaded.

  • A column base distributes the column load to the footing; a slab on grade rests on the ground and is not a structural slab.

  • A retaining wall resists lateral earth pressure; the stem, base slab and shear key are its main parts.

  • A parapet wall is at least 1.0 m high on a roof for safety; it must have a coping to shed water.

Quick reference

Arches, Lintels, Stairs and Roofing (continued)

  • A relieving arch has a rise of about one-eighth to one-quarter of its span and carries the wall above an opening.

  • A flat arch has a slight rise and is built of bricks on edge with a 10-15 mm camber.

  • A dog-legged stair has two flights with a half-space landing; a quarter-turn stair uses winders.

  • A trussed roof uses rafters, tie beam, principal rafter and struts; the pitch and span determine member sizes.

Quick reference

Flooring, Tiling and Finishing (continued)

  • A screed is a thin layer of mortar over a structural floor to provide a level surface for the finish.

  • A floor drain must be set at least 10 mm below the surrounding tile surface to drain water.

  • Terrazzo is a mix of marble chips and cement, ground and polished; it is laid 20-25 mm thick.

  • Paint on plaster requires the plaster to be dry (moisture below 12-15 percent) and the surface sealed with a primer.

Quick reference

Estimation, Measurement and Costing (continued)

  • A bill of quantities lists items with description, unit and quantity; the contractor prices each item.

  • A preliminary estimate uses a plinth area rate; a detailed estimate is built up item by item from drawings.

  • Contingency and work-charged establishment are added to the estimated cost; centage charges cover overheads and profit.

  • A rate analysis for brickwork includes bricks, mortar, labour, scaffolding and curing, with a mason's output of about 1 m3 per day.

Quick reference

Maintenance, Repair and Waterproofing (continued)

  • A damp-proof course must be continuous around the building and lapped 100 mm at joints and 150 mm at corners.

  • A waterproofing membrane on a roof is protected by a screed or tiles to prevent damage from traffic.

  • Cracks in plaster are raked out to a V shape, primed and filled with a polymer-modified mortar.

  • A leaking pipe or drain is located by a water test or dye test before repair; repair the cause, not just the stain.

Quick reference

Employability Skills and Workplace Practice (continued)

  • A material requisition is raised before work starts; it lists the quantity, specification and required date.

  • A daily labour return records the number of workers by trade and the hours worked.

  • A quality check on brickwork includes plumb, level, line, joint thickness and bond pattern, recorded on a checklist.

  • A handover document lists completed work, defects and outstanding items, signed by the contractor and the client.