ITI/NCVT Mason Building Constructor (AITT Theory): Estimation, Measurement and Costing

ITI/NCVT Mason Building Constructor (AITT Theory) · Work through your exam, one topic at a time.

All guide sections

Estimation, Measurement and Costing

Estimation, Measurement and Costing tests quantity take-off, measurement units, deduction rules, rate analysis and preparation of a simple bill of quantities. Expect brickwork in m3, plaster in m2, concrete in m3, reinforcement in kg and finishes in m2.

Core rules

  • Measure brickwork and concrete in cubic metres, plaster and tiling in square metres, steel in kilograms, and linear items in running metres.
  • Deduct openings according to the measurement rule; a common convention is no deduction for small openings below the specified threshold, but always state the rule used.
  • Add wastage and shrinkage allowances separately; do not hide them inside the measured net quantity.
  • Rate analysis separates material, labour, plant, overheads and profit.
  • Keep measurements in a standard format so another person can check them.

Worked example

A wall is 4 m long × 3 m high with a door 1 m × 2.1 m. Gross area = 12 m2; door area = 2.1 m2; net plaster area = 9.9 m2. At Rs 250/m2, plaster cost = 9.9 × 250 = Rs 2,475. Add 10% overhead and profit = Rs 2,722.50. For brickwork, the same wall at 230 mm thick has net volume 9.9 × 0.23 = 2.277 m3; do not price it as 12 × 0.23 because the opening is excluded under the stated rule.

Traps that cost marks

Mixing units, forgetting wastage, deducting openings twice, or omitting labour from a rate are common. A low material rate can still give a high final cost if wastage and overheads are ignored.

Key points

  • Brickwork and concrete: m3; plaster and tiling: m2; steel: kg.