Engineering Drawing and Drafting

  • Standard sheet sizes (ISO A series): A0 = 841 × 1189 mm; each lower number is the previous size halved on the longer side (A1 = 594 × 841, A2 = 420 × 594, A3 = 297 × 420, A4 = 210 × 297 mm).

  • First-angle projection: the object lies between observer and plane, so the view from the front is placed above the top view and the left-side view goes on the right. Third-angle reverses this.

  • Line precedence when lines coincide: visible outline > hidden (dashed) line > centre line > cutting-plane line > dimension/extension line.

  • Dimensioning rules: dimension lines are drawn parallel to the measured edge and never coincide with an outline; extension lines start about 1 mm clear of the object; arrowheads touch the extension line.

  • Scale = drawing length ÷ actual length. Representative fraction (RF) is written as 1:50, 1:100, etc.; a diagonal scale is used when three units (e.g., m, dm, cm) must be read from one scale.

  • An ellipse is drawn by the concentric-circle or rectangle method using the major axis AB and minor axis CD; the foci lie on the major axis at distance sqrt(a² − b²) from the centre.

  • A cycloid is the locus of a point on a circle rolling along a straight line; one full arch has length 2πr and height 2r.

  • Conic sections: eccentricity e = distance from focus ÷ distance from directrix; e < 1 ellipse, e = 1 parabola, e > 1 hyperbola.

  • Section views use uniformly spaced 45° hatching lines (thin, equally spaced); adjacent parts in an assembly are hatched in opposite directions.

Quick reference

Building Materials and Construction

  • Standard brick (Indian modular): 190 × 90 × 90 mm; with 10 mm mortar joints the nominal size is 200 × 100 × 100 mm.

  • Classification of bricks by compressive strength (N/mm²): class 3.5, 5, 7.5, 10, 12.5, 15, 17.5, 20, 25, 30; a first-class brick is well burnt, uniform colour, gives a clear metallic ring, and absorbs not more than about 20% water.

  • Brick earth for good bricks should contain roughly 20–30% alumina, 50–60% silica, and less than 5% lime; excess lime causes bricks to crack and melt.

  • Cement mortar proportion 1:3 to 1:6 by volume for masonry; lime mortar is weaker and used mainly for non-structural work; the mortar should be used within about 30 minutes of mixing.

  • Concrete block masonry uses blocks with a minimum compressive strength of 3.5–5 N/mm² and hollow blocks of 400 × 200 × 200 mm nominal size; hollow blocks reduce dead load and improve thermal insulation.

  • English bond alternates header and stretcher courses and is the strongest brick bond; Flemish bond alternates header and stretcher in each course and gives better appearance.

  • Lintels span openings; a lintel carries the load of masonry above it, while an arch transfers load by compression to its supports.

  • Damp-proof course (DPC) is laid at plinth level, usually 40–50 mm thick, using materials such as bitumen, polythene sheet, or cement concrete with a waterproofing compound.

  • Pile foundation is used where soil bearing capacity is low or the water table is high; end-bearing piles rest on a hard stratum, friction piles transfer load by skin friction.

Quick reference

Surveying and Leveling

  • Principle of surveying: work from the whole to the part - establish a control framework of higher accuracy first, then fill in details.

  • Chain survey: 1 chain = 66 ft = 20.1168 m; 1 link = 0.66 ft = 0.201 m; 1 Gunter's chain has 100 links. Metric chain lengths are 20 m and 30 m.

  • Ranging: direct ranging is used when both ends are intervisible; indirect (reciprocal) ranging is used when the ends are not visible, using two intermediate points aligned by trial.

  • Obstacles to chaining: river (use similar triangles or a parallel line), building (use perpendicular offset and Pythagoras), and hill (step chaining).

  • Levelling: reduced level (RL) of a point = height of instrument (HI) − staff reading. HI = RL of benchmark + backsight reading.

  • Rise and fall method: rise = previous staff reading − next staff reading; fall is the reverse. Arithmetic check: ΣBS − ΣFS = ΣRise − ΣFall = last RL − first RL.

  • Height of instrument (collimation) method check: ΣBS − ΣFS = last RL − first RL, and each RL = HI − intermediate staff reading.

  • The level tube axis must be parallel to the line of collimation; the two-peg test detects the collimation error, and the correction is applied at a distance d as e × (d/D).

  • Theodolite: the horizontal circle reads horizontal angles, the vertical circle reads vertical angles; face-left and face-right readings average out the collimation error.

  • Contour interval depends on scale and terrain: for a scale of 1:1000 on flat ground use about 0.25–0.5 m; on steep ground use 1–2 m.

Quick reference

Mechanics of Materials and Structural Analysis

  • Stress σ = P/A; strain ε = ΔL/L; Young's modulus E = σ/ε (Hooke's law valid within the proportional limit).

  • Poisson's ratio μ = lateral strain ÷ longitudinal strain; for steel μ ≈ 0.3, for concrete ≈ 0.2.

  • Thermal stress in a fully restrained bar: σ = α E ΔT. Free expansion = α L ΔT.

  • Bending equation: M/I = σ/y = E/R; section modulus Z = I/ymax, so σ = M/Z.

  • For a rectangular section b × d: I = bd³/12, Z = bd²/6. For a circular section of diameter d: I = πd⁴/64, Z = πd³/32.

  • Shear stress τ = VQ/(Ib); for a rectangular section the maximum shear stress is 1.5 × average (3V/2bd), occurring at the neutral axis.

  • Torsion of a circular shaft: τ/r = T/J = Gθ/L; polar moment J = πd⁴/32 for a solid shaft.

  • Euler buckling load for a pin-ended column: Pcr = π²EI/L²; effective lengths: both ends pinned L, fixed–fixed 0.5L, fixed–pinned 0.7L, fixed–free 2L.

  • Simply supported beam with a central point load W and span L: maximum BM = WL/4 at midspan, maximum deflection = WL³/48EI.

  • Cantilever with a point load W at the free end: maximum BM = WL at the fixed end, maximum deflection = WL³/3EI.

  • A truss is analysed by the method of joints (two unknowns per joint) or the method of sections (cut through three members, take moments about the intersection point).

Quick reference

Concrete Technology and RCC Design

  • Concrete grades: M20 means characteristic cube strength of 20 N/mm² at 28 days; the mix is denoted by nominal proportions such as 1:1.5:3 for M20 (cement : fine aggregate : coarse aggregate).

  • Water–cement ratio governs strength and durability; the workability requirement is expressed by slump (mm) or compacting factor. Typical slump for RCC work is 50–100 mm.

  • Cement types: OPC 33, 43 and 53 grade refer to 28-day compressive strength in N/mm²; PPC contains fly ash or slag and gives better durability and lower heat of hydration.

  • Initial setting time of OPC must be not less than 30 minutes; final setting time not more than 600 minutes.

  • Curing: concrete should be kept moist for at least 7 days for OPC and 10–14 days for blended cements; curing improves strength gain and reduces shrinkage cracking.

  • Nominal cover to reinforcement (IS 456): 20 mm for mild exposure, 30 mm for moderate, 45 mm for severe, 50 mm for very severe, 75 mm for extreme exposure.

  • Limit state of collapse in flexure: Mu = 0.87 fy Ast d (1 − fy Ast / (fck b d)); the limiting value of xu/d is 0.53 for Fe415 and 0.48 for Fe500.

  • Minimum tension reinforcement in a beam: Ast/bd = 0.85/fy; maximum tension reinforcement = 4% of bD.

  • Shear design: nominal shear stress τv = Vu/(bd); the shear strength of concrete τc depends on the percentage of tension steel; the maximum shear stress τc,max is 3.1 N/mm² for M20 and 3.5 N/mm² for M25.

  • Development length Ld = φ σs/(4 τbd); for deformed bars in tension, τbd is taken as 1.6 times the plain-bar value, and the value is increased by 25% for compression.

Quick reference

Applied Mechanics and Strength of Materials

  • Resultant of two forces P and Q at angle θ: R = sqrt(P² + Q² + 2PQ cos θ); the direction is given by tan α = Q sin θ / (P + Q cos θ).

  • Lami's theorem applies to three coplanar concurrent forces in equilibrium: P/sin α = Q/sin β = R/sin γ, where each angle is opposite the corresponding force.

  • Equilibrium of a coplanar force system: ΣFx = 0, ΣFy = 0, ΣM = 0. A body is in static equilibrium when these three conditions hold.

  • Moment of a force about a point = F × perpendicular distance; the principle of moments states that for equilibrium the sum of clockwise moments equals the sum of anticlockwise moments.

  • Friction: limiting friction F = μN, where μ is the coefficient of friction and N the normal reaction. The angle of friction φ satisfies tan φ = μ.

  • Centroid of a triangle lies at one-third of the height from the base; the centroid of a semicircle of radius r is at 4r/3π from the diameter.

  • Parallel-axis theorem: I = IG + A d², where IG is the moment of inertia about the centroidal axis and d is the distance between axes.

  • Work done = force × distance moved in the direction of the force; power = work ÷ time; kinetic energy = ½mv²; potential energy = mgh.

  • Strain energy stored in an axially loaded bar = ½ P ΔL = P²L/(2AE); the resilience modulus is σ²/(2E).

  • A body is in equilibrium under the action of a general coplanar force system when ΣFx = 0, ΣFy = 0, and ΣM about any point = 0.

Quick reference

Estimating, Costing and Quantity Surveying

  • Approximate estimate methods: plinth area rate method (cost = plinth area × rate per m²), cubical content method (volume × rate per m³), and unit rate method (per bed, per km, etc.).

  • Centre-line method: total length of the centre line of walls is computed once and multiplied by the width and depth of each item; it is efficient for walls of the same thickness.

  • Long wall–short wall method: long walls are measured out-to-out (centre length + one breadth) and short walls in-to-in (centre length − one breadth) for each cross wall.

  • Earthwork by the trapezoidal rule: V = h[(A1 + An)/2 + A2 + A3 + … + An−1]; prismoidal rule: V = h/3[(A1 + An) + 4(sum of even areas) + 2(sum of odd areas)].

  • Deduction for openings in masonry: deduct the full volume of the opening including the frame; for plaster, deduct openings exceeding 0.5 m² in area.

  • Contingency allowance in a detailed estimate is typically 3–5% of the estimated cost; work-charged establishment and centage charges are added separately.

  • Rate analysis: the rate per unit includes materials, labour, plant, contractor's profit (usually 10%), and overheads; the lead and lift of materials affect the rate.

  • Bar bending schedule: cutting length of a straight bar = clear span + 2 × end cover + 2 × hook length; for a 90° bend the deduction is 2d per bend, and for a 135° hook it is 3d per hook (d = bar diameter).

  • Standard hooks: a semicircular hook adds 9d to the length; a 45° bend adds 1d, a 90° bend adds 2d, and a 135° bend adds 3d.

  • Valuation: depreciation by the straight-line method = (cost − salvage value) ÷ useful life; the sinking fund method uses annual instalments that accumulate at compound interest.

Quick reference

Water Supply, Sanitation and Environmental Engineering

  • Per capita water demand in Indian towns: about 135 litres per head per day (lpcd) for domestic use; total demand including industrial and public use is usually taken as 150–200 lpcd.

  • Design period: 30 years for water supply schemes, 15–20 years for treatment units; peak factor for demand is usually 1.5–2.0 times the average.

  • Water treatment sequence: screening → aeration → coagulation–flocculation (alum) → sedimentation → filtration (rapid sand filter) → disinfection (chlorination).

  • Rapid sand filter: rate of filtration 100–150 litres/m²/min; slow sand filter: 100–200 litres/m²/day. Slow sand filters remove bacteria better but need more land.

  • Chlorine demand = chlorine dose − residual chlorine. A free residual chlorine of 0.2 mg/L after 30 minutes contact is the usual requirement.

  • Sewage flow: about 80% of water supplied appears as sewage; the peak factor for sewage is 2–3. BOD is measured at 20°C over 5 days (BOD5).

  • Standard BOD5 of domestic sewage is about 200–300 mg/L and suspended solids about 200–300 mg/L; the COD/BOD ratio indicates biodegradability.

  • Septic tank: detention period 12–36 hours; sludge is removed every 1–3 years; effluent is disposed of through a soak pit or drain field.

  • Self-cleansing velocity in a sewer is about 0.6–0.75 m/s; the maximum velocity to avoid erosion is about 3 m/s.

  • A water seal of 25–50 mm in a trap prevents foul gases from entering a building; the minimum diameter of a house drain is 100 mm.

Quick reference

Roads, Bridges and Transportation Engineering

  • Road classification (Indian): National Highways, State Highways, Major District Roads, Other District Roads, and Village Roads.

  • Design speed and camber: for a bituminous surface in heavy rainfall, camber is 1 in 50; in light rainfall, 1 in 60. For earth roads the camber is 1 in 25.

  • Superelevation e = V²/(127R) (V in km/h, R in m); the maximum superelevation is 7% for plain terrain and 10% for hilly terrain without snow.

  • Stopping sight distance SSD = 0.278 V t + V²/(254 f), where t is the reaction time (about 2.5 s) and f the coefficient of longitudinal friction (about 0.35–0.4).

  • CBR method of flexible pavement design: the total thickness depends on the soaked CBR of the subgrade; the required thickness decreases as CBR increases.

  • Flexible pavement layers from bottom to top: subgrade, sub-base, base course, and wearing course. Rigid pavement is a cement concrete slab that distributes load by beam action.

  • Bitumen grades: VG-10, VG-20, VG-30 and VG-40; the penetration test, ductility test, and softening point test characterise bitumen.

  • Bridges: the span is the distance between supports; the waterway is the area of the opening; the afflux is the rise in water level upstream caused by the bridge.

  • Traffic volume is expressed as PCU (passenger car units); a car = 1 PCU, a truck or bus = 3 PCU, a motorcycle = 0.5 PCU, a cycle = 0.5 PCU.

  • Culvert: a cross-drainage structure with a span up to about 6 m; a minor bridge has a span of 6–60 m, and a major bridge has a total length above 60 m.

Quick reference

Construction Management

  • PERT uses three time estimates: optimistic (to), most likely (tm), and pessimistic (tp). Expected time te = (to + 4tm + tp)/6; variance = ((tp − to)/6)².

  • CPM is activity-oriented and deterministic; the critical path is the longest path through the network and has zero total float.

  • Total float = LS − ES = LF − EF; free float = ES of successor − EF of current activity; the critical path has zero total float.

  • Earliest start (ES) is the maximum EF of predecessors; latest finish (LF) is the minimum LS of successors.

  • A network diagram must have a single start node and a single end node; dummy activities are used to maintain logic without consuming time or resources.

  • S-curve shows cumulative progress or cost against time; the cost slope = (crash cost − normal cost) ÷ (normal time − crash time) and is used for time–cost trade-off.

  • Labour output: a mason can lay about 1 m³ of brickwork per day with one helper; a carpenter can fix about 8–10 m² of shuttering per day.

  • Safety: a hard hat, safety shoes, and a safety belt are mandatory for work at height above 1.8 m; scaffolding must be inspected before use.

  • Work measurement: the unit of measurement for brickwork is m³, for plastering m², for painting m², and for reinforcement kg or tonne.

Quick reference

Safety and Professional Practice

  • Personal protective equipment (PPE): helmet, safety shoes, high-visibility vest, gloves, and ear and eye protection are required on site.

  • Excavation safety: provide shoring or benching for trenches deeper than 1.5 m; keep the excavated soil at least 1 m away from the edge.

  • Scaffolding: the working platform should be at least 600 mm wide and fitted with a toe board and guard rail; the maximum height of a working platform is 2 m below the next lift.

  • Ladder safety: the ladder should be set at about 75° to the horizontal (1 in 4 rule) and extend at least 1 m above the landing.

  • Electrical safety on site: use 110 V or 230 V with an earth-leakage circuit breaker; temporary wiring must be protected and isolated after work.

  • First aid: for electric shock, switch off the supply first, then give artificial respiration if breathing stops; report all accidents in the accident register.

  • Professional ethics: an engineer must not accept a commission from a supplier, must sign only work actually inspected, and must disclose conflicts of interest.

  • The contract documents (drawings, specifications, bill of quantities, conditions of contract) govern the work; the bill of quantities is measured and valued at the contract rates.

  • Occupational health: silica dust from cutting concrete causes silicosis; wet cutting and dust masks reduce exposure.

Quick reference

Computer-Aided Drafting and Basic Software Applications

  • CAD coordinate entry: absolute (x,y), relative (@x,y), and polar (@distance<angle). Ortho mode constrains drawing to horizontal and vertical directions.

  • Common AutoCAD commands: LINE, CIRCLE, ARC, RECTANGLE, POLYGON, OFFSET, TRIM, EXTEND, FILLET, CHAMFER, ARRAY, MIRROR, SCALE, ROTATE.

  • Layers control line type, colour, and line weight; the current layer is the one on which new objects are created. Objects cannot be edited on a locked layer.

  • Object snapping (OSNAP) snaps to endpoints, midpoints, centres, intersections, and perpendicular points; it improves accuracy compared with free-hand picking.

  • A block is a named group of objects inserted as a single entity; an attribute can attach text data (e.g., a door number) to a block.

  • Paper space and model space: draw full-size in model space and set the plot scale in the layout (paper space) viewport, e.g., 1:100.

  • Dimension styles control arrow size, text height, and precision; the dimension scale factor (DIMSCALE) must match the plot scale.

  • A DXF or DWG file is the standard exchange format for CAD drawings; a PDF is used for sharing and printing but is not editable as vector geometry in CAD.