Junior Engineer flashcards
Junior Engineer · Build recall with a focused review session.
34 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Hooke's Law
- Within the elastic range, stress is proportional to strain: σ = E·ε. The constant E is Young's modulus, a material property measured in the same units as stress, such as MPa or ksi.
- Section Modulus
- S = I/c, where I is the moment of inertia about the neutral axis and c is the distance to the extreme fiber. Bending stress is then σ = M/S, so a larger S lowers stress.
- Poisson's Ratio
- The negative ratio of lateral strain to axial strain under uniaxial loading, ν = −ε_lateral/ε_axial. Typical values are about 0.3 for steel and 0.15–0.2 for concrete.
- Thermal Stress
- When thermal movement is fully restrained, stress equals E·α·ΔT, where α is the coefficient of thermal expansion and ΔT the temperature change. Free movement produces no stress.
- Parallel Axis Theorem
- The moment of inertia about any axis equals that about the parallel centroidal axis plus area times the square of the distance between axes: I = I_c + A·d².
- Neutral Axis
- The line through a bending cross-section where longitudinal strain and bending stress are zero. It passes through the centroid for elastic bending of a homogeneous section.
- Resultant Vector
- For perpendicular components, magnitude R = √(Fx² + Fy²) and direction θ = arctan(Fy/Fx). For non-perpendicular vectors, resolve into components, sum, then recombine.
- Moment of a Force
- The rotational effect about a point: M = F·d, where d is the perpendicular distance from the point to the line of action. Units are force times length, such as kN·m.
- Continuity Equation
- For steady incompressible flow, Q = A·v is constant along a pipe, so A₁v₁ = A₂v₂. Reducing the cross-sectional area increases velocity proportionally.
- Centroid of a Triangle
- The centroid lies one-third of the height above the base, measured along the median from the base, and at the average of the vertex coordinates.
- Drawing Scale Ratio
- A scale of 1:n means one drawing unit represents n real units. A 25 mm dimension on a 1:100 plan equals 2,500 mm, or 2.5 m, on site.
- Rebar Mass per Meter
- For a round steel bar of diameter d in millimeters, mass ≈ d²/162 kg/m. A 16 mm bar gives about 1.58 kg/m; a 20 mm bar about 2.47 kg/m.
- Bill of Quantities
- A measured schedule listing work items with descriptions, units, and quantities, used for pricing and progress payment. It is distinct from the schedule of values.
- Cutting-Plane Line
- A heavy chain line on a drawing marking where a section is taken, with arrows showing the viewing direction and letters matching the section drawing title.
- Order of Precedence
- The contract clause ranking documents when they conflict. Specifications commonly govern quality over drawings, and larger-scale details govern over smaller-scale plans.
- Average End Area Method
- Earthwork volume between two sections: V = L·(A₁ + A₂)/2, where L is the spacing and A₁, A₂ are cross-section areas. The prismoidal formula adds a mid-section term.
- Formwork Stripping Strength
- Soffit formwork for slabs and beams is removed only after concrete reaches a specified strength, commonly about 70% of f'c, confirmed by field-cured cylinders.
- Crane Load Chart
- A manufacturer table giving capacity at each combination of radius and boom length. Capacity falls as radius increases, and rigging and attachment weights must be deducted.
- Wellpoint Dewatering
- A line of small-diameter suction points installed around an excavation lowers the water table by roughly 4–6 m per stage, suitable for granular soils.
- Height of Instrument
- HI = known elevation + backsight. A new point's elevation is HI minus the foresight reading on that point. The run checks when ΣBS − ΣFS equals the elevation change.
- Closed Traverse Angle Check
- For a closed polygon with n sides, the sum of interior angles must equal (n − 2) × 180°. Any misclosure is distributed among the angles before coordinates are computed.
- Latitude and Departure
- Latitude = distance × cos(bearing) and departure = distance × sin(bearing). A closed traverse requires the sum of latitudes and the sum of departures each to equal zero.
- Slope Correction
- A measured slope distance is longer than the horizontal distance. The correction is C = −h²/(2L), where h is the elevation difference and L the slope distance.
- Hierarchy of Controls
- Effectiveness order from highest to lowest: elimination, substitution, engineering controls, administrative controls, then personal protective equipment. PPE is the last line of defense.
- Excavation Protective System
- Excavations 1.5 m or deeper require sloping, benching, shoring, or shielding unless entirely in stable rock. A competent person inspects daily and after rain.
- Recordable Incident Rate
- Incident rate = (recordable incidents × 200,000) / hours worked. The 200,000 constant represents 100 full-time workers at 40 hours for 50 weeks.
- Total Float
- The time an activity can be delayed without delaying project completion: LS − ES or LF − EF. Activities on the critical path have zero total float.
- Critical Path
- The longest-duration chain of dependent activities through the network. It sets the project duration, and any delay on it delays completion unless compressed.
- Cost Performance Index
- CPI = EV/AC, earned value divided by actual cost. A value below 1.0 indicates the work cost more than budgeted; above 1.0 indicates cost savings.
- Estimate at Completion
- EAC = BAC/CPI when current cost performance continues. If remaining work proceeds at the budgeted rate, EAC = AC + (BAC − EV).
- Liquidated Damages
- A contract-specified sum per day of delay that is a genuine pre-estimate of the owner's loss. Courts may reject it if it is an unenforceable penalty.
- Substantial Completion
- The stage when the work is sufficiently complete for its intended use. It typically starts the warranty period and allows partial release of retainage.
- Concrete Slump Test
- A workability test per ASTM C143: concrete is placed in a standard cone in three layers, the cone is lifted, and the drop of the sample is measured.
- Standard vs Modified Proctor
- Both find maximum dry density and optimum moisture content. Modified Proctor uses greater compaction energy, giving higher maximum dry density at lower optimum moisture content.