Pipe wrench sizing
A pipe wrench is sized by the pipe diameter it grips, not its overall length; a 350 mm wrench suits about 50 mm pipe. Pull the handle toward you for a firm bite.
Basin wrench purpose
A long, spring-loaded wrench with a pivoting jaw that reaches behind a lavatory bowl to loosen trap nuts and supply couplings where a standard wrench cannot fit.
Reaming after cutting
Removing the internal burr left by a tube cutter or hacksaw. A burr narrows the bore, increases turbulence, and promotes corrosion, so ream every cut before jointing.
Die stock threading
A hand tool holding a die that cuts external threads on steel pipe. Oil the die and reverse a quarter turn after each full turn to break chips and avoid torn threads.
uPVC versus CPVC
uPVC is rigid unplasticised PVC for soil, waste, and vent lines. CPVC is chlorinated PVC that also handles hot water up to roughly 80 to 90 degrees Celsius.
PPR fusion jointing
Polypropylene random pipe is joined by heating both pipe and fitting and pushing them together. The fused joint is stronger than the pipe wall and suits hot and cold supply.
Solvent cement hazards
PVC solvent cement is flammable and releases volatile organic compounds. Use it only with ventilation, away from flame, and wear gloves and eye protection.
Confined space entry test
Before entering a manhole or sump, test oxygen (19.5 to 23.5 percent), flammable gas, hydrogen sulphide, and carbon monoxide. Keep an attendant outside with a harness and tripod.
Direct versus indirect supply
Direct supply feeds fixtures from mains pressure. Indirect supply fills a storage tank from the mains, then gravity or a booster pump feeds the fixtures.
Water hammer arrestor
A device that absorbs the pressure surge when a valve closes suddenly. It is an air chamber or mechanical shock absorber installed close to the fixture.
Backflow prevention
Protection against reverse flow that could contaminate potable water. An air gap, reduced-pressure zone assembly, or double check valve is fitted at the cross-connection.
Supply pipe velocity limit
Water velocity in supply pipes is kept below about 1.5 to 2.0 metres per second. Higher velocity causes noise, erosion, and water hammer.
Fixture unit values
A fixture unit rates the load a fixture places on the drainage system. Typical values are 4 to 6 for a WC, 1 for a basin, and 2 for a sink or bath.
Floor trap water seal
A floor trap, often called a nahani trap, has a 50 mm water seal and a 50 to 75 mm outlet. It drains floor washing water and blocks sewer gas.
Running flush cistern cause
A cistern that keeps running usually has a worn float valve washer, a mis-set float arm, or a leaking flush valve seat, letting water pass continuously.
WC trapway seal
The water closet trapway must retain a water seal of at least 50 mm. This seal stops sewer gas entering the room while allowing waste to pass.
Two-pipe drainage system
Soil from water closets and waste from sinks and basins discharge into separate stacks. A one-pipe system combines them into a single stack with venting.
Stack vent function
The soil vent pipe continues full bore above the roof. It relieves pressure in the stack and discharges sewer gas above the building, protecting trap seals.
Drain gradient rule
Horizontal drains are laid at about 1 in 60 to 1 in 100 for 100 mm pipe. Too flat allows solids to settle; too steep leaves liquids behind.
Inspection chamber placement
An inspection chamber or manhole is provided at changes of direction, at junctions, and at intervals of 45 to 90 metres along a straight drain run.
Isometric riser diagram
A three-dimensional single-line drawing of pipework showing sizes, gradients, and fittings. It is the main working drawing for supply and drainage layouts.
Invert level meaning
The invert level is the height of the inside bottom of a pipe above a stated datum. Successive invert levels drop by the pipe gradient along the run.
Drawing line conventions
Solid thick lines show visible pipe, dashed lines show concealed or under-slab pipe, and centre lines mark pipe axes or symmetry. Symbols indicate valves, drains, and vents.
Quantity take-off wastage
When measuring pipe and fittings from drawings, add wastage allowances, commonly 5 to 10 percent on pipe and 2 to 5 percent on fittings, to cover offcuts and breakage.
Rate analysis components
A unit rate is built from material cost, labour cost, plant and tools, overheads, and contractor profit. It converts measured quantities into a priced bill.
Bill of quantities content
A BOQ lists each item with description, unit (metre, number, kilogram), quantity, rate, and amount. Measured quantities must agree with the drawings.
Solvent joint leak repair
A leaking solvent-welded joint cannot be tightened. Cut out the fitting and remake the connection using a coupling and new solvent cement.
Water meter leak test
Shut every fixture and watch the water meter. A moving dial indicates a hidden leak, often a running cistern, a dripping tap, or a buried supply line.
Dye test for leaks
Add dye to a cistern or trap and observe downstream. Dye appearing where it should not locates a broken seal or a cross-connection between systems.
Trap arm vent limit
The trap arm, the pipe between trap and vent, is limited in length, commonly 1.5 to 2.4 metres depending on size. A longer arm risks self-siphonage.
Vent terminal height
A vent pipe must terminate at least 150 mm above the roof surface and at least 3 metres from an operable window or fresh air intake.
Legionella temperature control
Store hot water at 60 degrees Celsius or above and distribute it at 50 degrees Celsius or above. Lukewarm water and dead legs allow Legionella to multiply.