RBSE SS Voc Plumbing study materials
RBSE SS Voc Plumbing study resources

RBSE SS Voc Plumbing: Estimating and Costing

RBSE SS Voc Plumbing · Work through your exam, one topic at a time.

All guide sections

Estimating and Costing

What this domain tests

Estimating and Costing tests quantity take-off, bill of quantities, rate build-up and tender totals. You must measure pipe, fittings, fixtures and labour in the correct units, then add wastage, overheads and taxes.

Core rules

  • Measure pipe in running metres, fittings in numbers, fixtures in numbers, and excavation/backfill in cubic metres.
  • Take off from drawings and schedules; record location and size so quantities can be checked.
  • Add wastage for cuts and damage: often 5–10% for pipe, but use the project allowance.
  • A rate build-up includes material, labour, tools/plant, overheads and profit; tax is added as required.
  • Separate lead, lift and height allowances if the work is above normal reach.
  • A BOQ is a priced schedule; a tender total is the sum of measured items plus provisional sums and taxes.

Worked example

25 m of 25 mm CPVC pipe at ₹180/m costs ₹4,500. Add 5% wastage: 25 × 0.05 = 1.25 m, or ₹225, giving ₹4,725. Add 18% GST: ₹4,725 × 0.18 = ₹850.50, total ₹5,575.50. The reasoning is material cost first, then wastage on quantity, then tax on the extended amount; labour and fittings are separate items.

Traps

Mixing metres and numbers, forgetting fittings and supports, applying GST before wastage, ignoring height/lead, and pricing a provisional sum as a measured item are common mistakes.