WBCHSE HS Vocational Construction: Estimation, Costing and Quantity Surveying

WBCHSE HS Vocational Construction · Work through your exam, one topic at a time.

All guide sections

Estimation, Costing and Quantity Surveying

What this domain tests

You must measure quantities from drawings, apply the long wall–short wall or centre line method, deduct openings, use correct units, and build a bill of quantities with rates.

Core rules and concepts

  • Units: earthwork and concrete in m³, brickwork in m³, plaster and painting in m², steel in kg, doors and windows in numbers, water supply and sanitary lines in running metres.
  • Long wall–short wall method: long wall length = centre-to-centre length + half width at each end (i.e. + one full width); short wall length = centre-to-centre length − half width at each end.
  • Deductions: openings above 0.1 m² are deducted from masonry and plaster; no deduction for small holes.
  • Costing: quantity × rate = amount; add contingencies, work-charged establishment and centage; abstract gives the total; rates come from the schedule of rates plus non-schedule items.

Worked example

Room 4 m × 3 m internal, 230 mm walls, height 3 m, one door 1.0 × 2.1 m. Centre line long = 4 + 0.23 = 4.23 m; long wall = 4.23 + 0.23 = 4.46 m. Centre line short = 3 + 0.23 = 3.23 m; short wall = 3.23 − 0.23 = 3.00 m. Long walls: 2 × 4.46 × 0.23 × 3 = 6.155 m³. Short walls: 2 × 3.00 × 0.23 × 3 = 4.140 m³. Total 10.295 m³. Less door 0.483 m³ → 9.812 m³. At ₹6,500/m³ the brickwork costs about ₹63,780.

Traps that cost marks

Using the inside length as the long wall; forgetting door and window deductions; mixing m² and m³ units; deducting small holes that need no deduction; quoting a rate without the schedule reference.