Iran Nezam Architecture Supervision Exam · Keep the key ideas within reach.

Quick reference

Architectural Design and Planning

  • Setback (tarak-e eshteghal) is measured from the property line to the outermost building projection; balconies count when projecting beyond the permitted line.

  • Floor Area Ratio (FAR / zel-e sakhteman) = total above-grade gross floor area ÷ plot area; local zoning tables fix the maximum FAR per zone.

  • Building coverage ratio (dar sad-e ezafe) = footprint area ÷ plot area, capped separately from FAR, so a tall tower and a wide low block on the same plot differ.

  • Occupancy load per use drives egress width: assembly areas require more exit width per person than office or residential use; check the current national building code tables.

  • Solar orientation rule of thumb for Iranian plateaus: long axis east–west, main glazing south, with 30–60 cm overhangs cutting summer noon gain while admitting winter sun.

  • Accessibility ramp: maximum running slope 1:12, landing at every 9 m of run and at each direction change, handrails both sides, minimum clear width 1.20 m.

  • Stair geometry: riser 17–18 cm and tread 28–30 cm for public buildings; 2R + T should fall between 60 and 64 cm for comfortable ascent.

  • Daylight rule: window glazing area of roughly 1/8 to 1/10 of floor area is the code minimum for habitable rooms; deeper rooms need supplementary lighting.

Quick reference

Building Construction and Structural Systems

  • Dead load is self-weight from material density × volume; live load comes from code occupancy tables, and seismic load is derived from the base shear formula V = C·W.

  • Seismic base shear: V = C·W, where C is the seismic coefficient from the design spectrum and W is the total effective seismic weight including a fraction of live load.

  • Concrete cover minimums: 25 mm for slabs, 30–40 mm for beams and columns in moderate exposure; increase for foundations cast against soil (typically 50–75 mm).

  • Concrete mix: characteristic cylinder strength f'c governs design; the water/cement ratio controls durability and strength - lower w/c means higher strength and lower permeability.

  • Steel connection hierarchy: in moment frames, connections must develop the plastic moment of the beam so hinges form in beams, not in welds or columns.

  • Bracing vs. moment frame: braced frames give high stiffness and low drift but concentrate force at connections; moment frames are ductile but drift more under wind.

  • Slab systems: one-way slabs span mainly in one direction (L/B ≥ 2); two-way slabs carry load in both directions and are common in Iranian residential construction.

  • Foundation choice follows soil bearing capacity: shallow spread footings for adequate bearing strata; piles or mat foundations where soft soil or high water table exists.

Quick reference

Materials and Building Components

  • Cement types: Type I general purpose, Type II moderate sulfate resistance, Type III high early strength, Type IV low heat of hydration, Type V high sulfate resistance.

  • Aggregate grading affects workability and strength; well-graded aggregate reduces voids and cement demand, and the maximum aggregate size is limited by member thickness and rebar spacing.

  • Concrete curing: keep moist for at least 7 days (normal cement) or 3 days for high-early-strength; curing loss cuts strength and raises shrinkage cracking.

  • Brick (ajr) quality: fired clay brick should ring when struck, show no efflorescence, and have absorption low enough to prevent freeze–thaw damage in cold zones.

  • Gypsum and lime plasters are the traditional Iranian interior finish; gypsum sets fast and is not for exterior use, while lime tolerates moisture and improves workability.

  • Thermal insulation: mineral wool and EPS are rated by thermal conductivity λ (W/m·K); lower λ means better insulation, and thickness is set by the climate zone requirement.

  • Waterproofing membranes: bituminous sheet for roofs and foundations, cementitious coating for wet areas; all laps must be shingled so water flows over the lap, not into it.

  • Rebar grade naming: in the common Iranian designation, the number after the prefix indicates nominal yield strength in kgf/mm² (e.g., AIII / 400-grade bars).

Quick reference

Building Services (Mechanical and Electrical)

  • Heating load = transmission losses (U·A·ΔT summed over the envelope) + infiltration/ventilation load; cooling load adds solar gain through glazing and internal gains.

  • U-value is the reciprocal of total thermal resistance: U = 1/(R_si + ΣR_layer + R_se); lower U means better envelope performance.

  • Elevator planning: one elevator per roughly 3,000–4,000 m² of office floor area as a starting check; verify with a traffic analysis for tall buildings.

  • Electrical load estimation uses demand factors: total connected load × demand factor gives design demand; diversity factors lower the service size for mixed occupancies.

  • Earthing/grounding: the earth electrode resistance must be low enough for protective device operation; TN and TT systems differ in where neutral is bonded and how faults clear.

  • Fire alarm zoning: each floor is normally its own detection zone, and audible/visual alarms must be audible above ambient noise throughout the occupied space.

  • HVAC duct sizing: equal-friction method keeps pressure drop per unit length constant; velocity method limits noise in occupied branches.

  • Plumbing venting: every trap needs a vent; a vent stack prevents siphonage of trap seals, and fixture units size the drain and vent pipes.

Quick reference

Construction Supervision and Site Management

  • Supervision cycle: inspect, record, compare to approved drawings and specifications, issue instruction or non-conformance report, then verify corrective action and close out.

  • Concrete placement checks: formwork alignment and cleanliness, rebar size/count/spacing/cover, approved mix design, slump test, sampling of test cubes, and vibration during pour.

  • Critical-path method: the critical path is the longest duration path through the network; its float is zero, so any delay there delays the project completion date.

  • Total float = LS − ES = LF − EF; float is the schedule buffer available before a task pushes the completion date.

  • Earned value: CPI = EV/AC and SPI = EV/PV; CPI below 1 means cost overrun, SPI below 1 means schedule slippage.

  • Daily site report captures weather, labor and plant on site, work performed, deliveries, tests taken, and any instruction received - it is the primary contemporaneous record.

  • Snag/punch list closeout: list defects by location, assign responsible party and deadline, and re-inspect before releasing retention or final payment.

  • Hold-point inspection: work must stop at a defined stage (e.g., before covering rebar) until the supervisor signs off; covering before inspection forfeits verification.

Quick reference

Building Regulations, Codes, and Standards

  • The national building code (Maqarrat-e Melli-e Sakhteman) is issued in parts; Part 3 covers fire protection, Part 6 loads, Part 9 concrete, and later parts cover energy and maintenance.

  • Fire compartmentation limits spread: rated walls and floors with protected openings divide a building into compartments sized by occupancy and height.

  • Means of egress: two remote exits are required above a threshold occupancy and travel distance; exit stairs must be enclosed where the building exceeds the low-rise limit.

  • Occupant load factors convert floor area to persons per use; exit width, door swing, and stair capacity are then sized from that load.

  • Seismic design provisions classify sites by soil type and set the design base acceleration; irregularities in plan or height trigger stricter analysis and detailing.

  • Energy code (Part 19) sets envelope U-values and glazing limits by climate zone; compliance is checked by prescriptive tables or whole-building calculation.

  • Permit sequence: approved architectural and structural drawings, then construction permit, then staged inspections, then occupancy certificate before use.

  • Change control: any deviation from approved drawings requires the designer's sealed revision and, where it affects structure or egress, re-approval by the authority.

Quick reference

Contracts, Legal Responsibilities, and Professional Ethics

  • Standard contract types: lump-sum (fixed price for defined scope), unit-price (paid per measured quantity), and cost-plus (actual cost plus fee) - risk allocation differs sharply.

  • Retention is a percentage withheld from each payment until defects liability ends; it protects the client but must be released per the contract terms, not indefinitely.

  • Variation order: scope changes must be instructed in writing, priced by the contract rates or a new agreed rate, and reflected in both time and money before execution.

  • Delay damages (liquidated damages) are a pre-agreed sum per day of late completion; they must be a genuine estimate, not a penalty, to be enforceable.

  • Force majeure excuses performance only when the event is outside control, unforeseeable, and unavoidable; notice deadlines in the contract still apply.

  • Professional liability: the designer's seal carries responsibility for code compliance; supervision does not transfer design liability to the supervisor.

  • Conflict of interest: a supervisor must not certify work by a firm in which they hold a financial interest; disclose and recuse.

  • Dispute ladder: engineer's decision, then amicable settlement or mediation, then arbitration or court as named in the contract's dispute clause.

Quick reference

Safety, Health, and Environmental Requirements

  • Fall protection is required at edges and openings; guardrails at open edges of floors and roofs, and covers over floor openings fixed so they cannot be displaced.

  • Scaffolding: stable base, plumb standards, ties to the structure, complete working platforms, and guardrails with toe boards on every open side.

  • Excavation safety: slope or shore trenches deeper than about 1.2 m, keep spoil back from the edge, and inspect after rain or any ground movement.

  • Electrical site safety: residual-current protection on temporary supplies, no damaged leads, lockout/tagout before work on energized circuits, and grounding of metal plant.

  • Hazard communication: keep safety data sheets for chemicals on site, label containers, and provide PPE matched to the exposure (dust, solvent, noise).

  • Noise and dust control: wet down demolition debris, schedule noisy work within permitted hours, and monitor workers' exposure against occupational limits.

  • Waste management: segregate construction and demolition waste, and dispose only at licensed sites; asbestos-containing material needs a specialist survey before disturbance.

  • Incident reporting: record near-misses as well as injuries; root-cause analysis of near-misses prevents the events that would have caused harm.

Quick reference

Quantity Surveying, Cost Estimation, and Documentation

  • Measurement convention: quantities are net dimensions from drawings, with deductions for openings above a stated size, and the method of measurement must be stated in the bill.

  • Concrete volume = length × width × depth per member, summed by grade; formwork area is measured separately as the contact area of concrete with formwork.

  • Rebar weight: W = (d²/162) kg per metre for bar diameter d in mm; total = unit weight × cut length × number of bars, plus laps and washers.

  • Masonry wall area = length × height − openings; report thickness separately because a 10 cm and a 20 cm wall have different unit rates.

  • Plaster and paint area follow the finished surface, including reveals where specified; ceilings are measured separately from walls.

  • Unit rate build-up: labor, material, plant, overhead, and profit are summed per unit; the estimate is only as good as the productivity assumptions behind it.

  • Cost index escalation adjusts historical rates to current prices; apply the index to the base date of the estimate, not to the payment date.

  • As-built documentation: record drawings, test certificates, warranties, and operation manuals form the handover package; missing documents block final acceptance.