Iran Nezam Electrical Supervision Exam study materials
Iran Nezam Electrical Supervision Exam study resources

Iran Nezam Electrical Supervision Exam cheat sheet

Iran Nezam Electrical Supervision Exam · Keep the key ideas within reach.

Quick reference

Electrical Building Systems Design

  • Lighting design uses the lumen method: N = (E × A) / (Φ × CU × LLF), where E is target illuminance in lux, A is area in m², Φ is lumens per luminaire, CU is coefficient of utilization, and LLF is light loss factor.

  • Illuminance targets (IES/EN 12464-1 practice): offices 500 lux, corridors 100 lux, classrooms 300–500 lux, industrial fine work 750–1000 lux, parking 75 lux.

  • Receptacle layout rule: no point on a wall may be more than 1.8 m (6 ft) from a general-purpose receptacle along the floor line in dwelling habitable rooms; kitchen countertop receptacles at intervals not exceeding 1.2 m (4 ft).

  • Small-appliance branch circuits in dwellings: minimum two 20 A circuits for kitchen/dining countertops; laundry a separate 20 A circuit; bathroom receptacles on dedicated 20 A circuits protected by RCD/GFCI.

  • Continuous loads are taken at 125 % of nameplate for branch-circuit and feeder sizing; the panel busbar and main breaker must exceed the connected demand after factors.

  • Voltage-drop design targets: ≤3 % on a branch circuit and ≤5 % total from service to load (feeder plus branch); motor starting drop commonly limited to 15 % at the motor terminals.

  • Box fill and device spacing: a lighting outlet or receptacle outlet must be provided in every habitable room, bathroom, hallway, stairway, garage, and outdoor entrance; switch height typically 1.1–1.2 m above finished floor.

Quick reference

Wiring Methods, Conductors, and Raceways

  • Conductor ampacity tables are corrected by ambient temperature factor and adjusted by conduit fill (bundling) factor; both multipliers apply to the table value before comparing with the breaker.

  • Standard conduit fill limits (Chapter 9 style): 1 conductor 53 %, 2 conductors 31 %, over 2 conductors 40 % of interior cross-sectional area.

  • Minimum conductor sizes: 1.5 mm² for lighting circuits, 2.5 mm² for general receptacle circuits, 4 mm² for kitchen/laundry and water-heater circuits (IEC 60364 / Iranian practice); 16 mm² copper minimum for service entrance in many local rules.

  • Bending radius for insulated conductors: not less than 8× the overall cable diameter for cables ≤ 25 mm, and 10–12× for larger; for conduit, typically 6× the trade diameter.

  • Colors: phase L1 brown, L2 black, L3 grey, neutral blue, protective earth green-yellow; PEN conductor green-yellow with blue marking at terminations.

  • Conduit support intervals: rigid metal/PVC conduit every 3 m and within 1 m of boxes; cable tray every 1.5–3 m; flexible conduit max 1 m unsupported at the equipment end.

  • Derating for more than three current-carrying conductors in a raceway: 80 % at 4–6, 70 % at 7–9, 50 % at 10–20 conductors (IEC 60364-5-52 Table B.52.17 style).

Quick reference

Protection, Grounding, and Bonding

  • Breaker selection rule: I_breaker ≥ I_design and I_breaker ≤ I_z (corrected cable ampacity); I2 (tripping current) ≤ 1.45 × I_z for overload protection.

  • Earth-fault loop impedance must satisfy Zs ≤ U0 / Ia, where U0 is nominal line-to-earth voltage (230 V) and Ia is the current that trips the device within the required disconnection time (0.4 s for 230 V final circuits ≤ 32 A).

  • RCD types: Type AC for sinusoidal AC residual currents, Type A for pulsating DC (electronics, inverters), Type B for smooth DC (EV chargers, PV inverters, some VFDs).

  • Earthing system designations: TN-S (separate PE throughout), TN-C-S (PEN split at origin), TT (local earth electrode, RCD required), IT (isolated or high-impedance earthed source).

  • Main equipotential bonding conductor cross-section: ≥ half the largest protective conductor, minimum 6 mm² copper (10 mm² where the supply is larger); supplementary bonding minimum 2.5 mm² (4 mm² if mechanically unprotected).

  • Earth electrode resistance target: typically ≤ 10 Ω for a single electrode in TT systems; ≤ 5 Ω where specified for sensitive installations; measured by fall-of-potential or clamp method.

  • Surge protective devices: Type 1 at the service entrance where a lightning protection system exists, Type 2 at distribution boards, coordinated by energy (IEC 61643-11).

Quick reference

Codes and Standards

  • The Iranian national building code (مقررات ملی ساختمان) is issued by the Ministry of Roads and Urban Development; Part 13 covers electrical installations and references IEC 60364 as the technical basis.

  • Part 13 mandates licensed-engineer design and supervision for electrical systems of buildings above the small-installation threshold, with drawings and calculations submitted for approval.

  • The Iranian electrical installations standard (مبحث ۱۳ and the استانداردهای وزارت نیرو / توانیر distribution regulations) governs service connection, metering, and consumer interface requirements.

  • IEC 60364 series is the reference for protection, earthing, conductor sizing, and verification; IEC 62305 for lightning protection; IEC 60079 for hazardous-area equipment.

  • Fire-related requirements reference the national fire code (مقررات ملی ساختمان مبحث ۳) and NFPA 72/101 principles for detection, alarm, and egress lighting.

  • Standards hierarchy: mandatory national code and utility regulations first, then referenced IEC/EN standards, then manufacturer instructions; conflicts resolve in favor of the mandatory national document.

  • Verification on completion requires insulation resistance, continuity of protective conductors, earth-electrode resistance, RCD trip test, polarity, and loop-impedance measurement, documented in a test report.

Quick reference

Low-Voltage Distribution and Load Calculations

  • Panel schedule demand: connected load is the sum of nameplate VA; demand load applies demand factors by occupancy (e.g., 100 % for the first 10 kVA of dwelling general load, 40 % thereafter).

  • Lighting load estimate: 15–25 VA/m² for offices, 10–20 VA/m² for residential, 30–50 VA/m² for retail; use actual luminaire schedule when available.

  • Three-phase power: P = √3 × U × I × cos φ; per-phase current I = P / (√3 × U × cos φ). Balance single-phase loads across phases to within 10–15 %.

  • Voltage drop (three-phase): ΔU = √3 × I × L × (R cos φ + X sin φ); single-phase: ΔU = 2 × I × L × (R cos φ + X sin φ), with R in Ω/m at operating temperature.

  • Copper resistivity at 20 °C is 0.0175 Ω·mm²/m; use 0.0225 Ω·mm²/m at 70 °C conductor temperature for voltage-drop calculations.

  • Diversity factor reduces the sum of individual maximum demands to the maximum demand of the installation; demand factor applies to a single load group's connected load.

  • Transformer sizing: kVA = total demand kW / (power factor × loading limit, typically 0.8); allow 20–25 % spare capacity for future growth.

Quick reference

Electrical Safety, Fire Protection, and Hazardous Locations

  • Hazardous-area zone classification: Zone 0/1/2 for gases and vapors (continuous, likely, unlikely), Zone 20/21/22 for dust; equipment must be certified for the zone and gas/dust group.

  • Protection concepts: Ex d flameproof, Ex e increased safety, Ex i intrinsic safety (ia/ib), Ex p pressurization, Ex n non-sparking; temperature class T1–T6 limits surface temperature (T6 = 85 °C max).

  • Fire alarm system categories: addressable vs conventional; detector spacing typically 7.5 m (heat), 10.5 m for smoke on flat ceilings with 0.5 m clearance from walls.

  • Emergency lighting: escape-route illuminance ≥ 1 lux along the centerline, ≥ 5 lux in open areas, 50 % of required illuminance within 5 s and full output within 60 s, 90-minute duration minimum.

  • Firestop every penetration of a fire-rated wall or floor with a listed system rated to the same fire resistance; cable trays crossing fire compartments require internal and external sealing.

  • RCD protection is mandatory for socket outlets ≤ 32 A, bathroom circuits, outdoor circuits, and construction-site circuits; 30 mA is the standard personnel-protection sensitivity.

  • Arc-flash and shock risk assessment: establish approach boundaries, lockout/tagout, and verify absence of voltage before work; PPE level follows incident-energy calculation.

Quick reference

Special Installations

  • Emergency lighting circuits must be supplied from a source that survives normal supply failure (central battery, self-contained luminaires, or generator), and be independent of normal lighting control.

  • Fire alarm cabling uses fire-resistant cable (e.g., PH30/PH120 or FPLR/FPLP equivalents) in dedicated conduit, separated from power circuits by at least 300 mm or a barrier.

  • Elevator (lift) supply: dedicated feeder to the machine room, isolator within sight of the controller, car lighting on a separate circuit, and a two-way communication/alarm supply.

  • IT and communication cabling: separate pathways from power, minimum 300 mm separation or a grounded metallic divider; bend radius ≥ 4× cable diameter for copper data cable.

  • Renewable-energy interfaces: PV inverter output requires a dedicated breaker with the inverter's maximum output current × 1.25, a DC isolator at the array, and Type A or B RCD depending on inverter topology.

  • Generator/ATS installations require a transfer switch that prevents parallel connection with the utility, neutral switching where separately derived, and load prioritization for life-safety loads.

  • Electric vehicle charging: Mode 3 with a dedicated RCD (Type A + DC detection or Type B), a pilot-control line, and load management where the service capacity is limited.

Quick reference

Professional Practice, Supervision, and Legal Responsibilities

  • The licensed engineer (مهندس ناظر) is responsible for conformity of the executed work with the approved drawings, the national building code, and the issued permit; supervision reports are filed at defined construction stages.

  • The supervision report (گزارش ناظر) must be submitted at foundation, structure, and completion stages; withholding a report halts the occupancy certificate.

  • Design liability: the designer warrants fitness for purpose of the design; the supervisor warrants conformity of execution; neither may approve a deviation without an official revision.

  • Contract documents hierarchy: agreement, conditions of contract, specifications, drawings, bill of quantities; the more stringent document prevails for safety and code compliance.

  • The engineer must declare conflicts of interest and may not supervise work executed by a firm in which they hold a financial interest.

  • Records to retain: approved drawings, calculations, test reports, material certificates, as-built documents, and correspondence; retention typically spans the project life plus the statutory limitation period.

  • Non-compliance or negligence can trigger disciplinary action by the construction engineering organization (سازمان نظام مهندسی ساختمان), insurance liability, and civil damages.