TEST ARCHED flashcards
TEST ARCHED · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Project vs program
- A project is a temporary endeavor producing a unique result; a program is a group of related projects managed together to obtain benefits not available from managing them individually.
- Project charter
- A document issued by the sponsor that formally authorizes the project, names the project manager, and grants authority to apply organizational resources to project activities.
- Triple constraint
- The interdependent balance of scope, time, and cost, with quality at the center; changing one constraint typically forces adjustment to at least one other.
- PMO types
- Supportive PMOs provide templates and best practices; controlling PMOs enforce compliance with frameworks; directive PMOs directly manage and take responsibility for projects.
- Scope baseline
- The approved combination of the project scope statement, work breakdown structure, and WBS dictionary, used as the reference for measuring scope performance and controlling changes.
- Work breakdown structure
- A deliverable-oriented hierarchical decomposition of total project scope; its lowest level, the work package, can be estimated, scheduled, and assigned to one owner.
- Validate vs control scope
- Validate Scope is formal acceptance of completed deliverables by the customer; Control Scope monitors scope status and manages changes to the scope baseline.
- Requirements traceability matrix
- A grid linking each requirement to its source, design elements, build components, and test cases, confirming that every requirement is covered and every deliverable justified.
- Scope creep
- Uncontrolled expansion of project scope through undocumented additions, often without corresponding adjustments to time, cost, or resources.
- Coupling and cohesion
- Coupling is the degree of dependency between modules, which should be low; cohesion is the relatedness of work within a module, which should be high.
- CAP theorem
- A distributed data system cannot simultaneously guarantee consistency, availability, and partition tolerance; under a network partition it must sacrifice consistency or availability.
- Availability formula
- Availability equals mean time between failures divided by the sum of mean time between failures and mean time to repair; reducing repair time raises availability.
- Design trade-off analysis
- A weighted evaluation of design alternatives against criteria such as cost, risk, performance, and maintainability, documenting the selected option and rejected alternatives with rationale.
- Critical path
- The longest duration path through the project network, which determines the shortest possible project duration; activities on it have zero total float.
- Cost performance index
- CPI equals earned value divided by actual cost; a value below one indicates the project is spending more than the work performed is worth.
- Schedule performance index
- SPI equals earned value divided by planned value; a value below one indicates work is progressing slower than the baseline plan.
- Estimate at completion
- EAC is the forecast total cost at completion; when current variances are expected to continue, EAC equals budget at completion divided by CPI.
- Crashing vs fast tracking
- Crashing shortens duration by adding resources and cost; fast tracking overlaps sequential activities, shortening duration but increasing risk and rework potential.
- Total float
- The amount of time an activity can be delayed without delaying the project finish date; calculated as late start minus early start or late finish minus early finish.
- Quality assurance vs control
- Quality assurance focuses on processes to prevent defects; quality control inspects deliverables to detect defects and verify they meet specified quality standards.
- Cost of quality
- The total cost of conformance (prevention and appraisal) plus cost of non-conformance (internal and external failures), used to justify quality investment.
- Control chart rule
- A process is out of control when a data point falls outside control limits or seven consecutive points fall on one side of the mean, indicating special-cause variation.
- Definition of Done
- A shared checklist of criteria an increment must satisfy to be considered complete; work not meeting it is not accepted as finished.
- Risk vs issue
- A risk is an uncertain event that may affect the project if it occurs; an issue is a risk that has occurred and now requires active management.
- Threat response strategies
- Avoid eliminates the threat, transfer shifts impact to a third party, mitigate reduces probability or impact, accept acknowledges it, and escalate moves it beyond project authority.
- Change control board
- A group with authority to review, approve, reject, or defer change requests, evaluating impacts on scope, schedule, cost, quality, and risk before deciding.
- Residual and secondary risk
- Residual risk remains after responses are applied; secondary risk is a new risk created by implementing a risk response.
- Communication channels formula
- The number of communication channels equals n times n minus one, divided by two, where n is the number of stakeholders; channels grow quadratically as stakeholders are added.
- Power-interest grid
- A stakeholder classification plotting influence against interest; high power and high interest stakeholders are managed closely, while low power and low interest are monitored.
- RACI matrix
- A responsibility assignment grid where each task has one Accountable owner, plus Responsible doers, Consulted contributors, and Informed recipients of updates.
- Phase gate
- A governance review at the end of a phase that checks deliverables against exit criteria before authorizing funding and work for the next phase.
- Escalation threshold
- A predefined numeric or criteria-based trigger, such as a variance exceeding ten percent, that requires raising an issue to a higher governance authority.