32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Change
The addition, modification or removal of anything that could have a direct or indirect effect on services; the scope includes documentation, processes, roles, suppliers and data as well as technology.
Change enablement purpose
To maximize the number of successful service and product changes by ensuring that risks are properly assessed, authorizing changes to proceed, and managing the change schedule.
Change schedule
A calendar of planned changes and their dates, used to plan work, avoid collisions between changes, communicate planned changes to users, and assign resources.
Unauthorized change
A change implemented without the authorization its change model requires; it is a significant source of risk and is tracked as a control metric.
Change enablement components
The practice rests on three elements: change models, change authority, and the change schedule, also called the change calendar.
Change enablement scope
Any component that could affect services: hardware, software, cloud services, documentation, processes, roles, suppliers and data, across all service value chain activities.
Standard change
A pre-authorized, low-risk, well-understood and repeatable change performed under a documented procedure, needing no new authorization decision each time it is used.
Normal change
A change assessed and authorized through a change model; the assessed risk level sets the depth of assessment and which change authority decides.
Emergency change
A change that must be implemented as soon as possible, for example to restore service after a major incident or apply a security fix, using a pre-defined emergency authority.
Change model
A repeatable, predefined approach for a type or category of change, specifying triggers, steps, roles, timescales, authorization points and escalation paths.
Risk-based categorization
Placing each change into a risk tier based on assessed impact, complexity, novelty and dependencies; the tier determines the required authority and assessment depth.
Change risk factors
Impact on users and services, complexity, number of affected configuration items, novelty, regulatory or security exposure, timing, and dependencies on other changes.
Change authority
The person or group accountable for authorizing a change; it may be a named role, a team, or a change advisory board constituted for a defined scope.
Change advisory board
A formally constituted group that assesses and authorizes changes within a defined scope; ITIL 4 does not require every change to be reviewed by one.
Delegated change authority
Authorization responsibility passed to another role or team, such as an emergency authority or regional manager; the delegation must be documented and bounded.
Change assessment inputs
Risk and impact analysis, expected benefit, urgency, test evidence, capacity and resource needs, dependencies, compliance obligations and rollback capability.
Approval decision options
The change authority may authorize, authorize with conditions, defer, reject, or request further information; the decision and conditions are recorded in the change record.
Separation of duties in change
For high-risk changes the person authorizing should differ from the person implementing, so accountability and technical execution are not held by one individual.
Change registration
Recording the change with description, scope, justification, requestor, affected configuration items, applicable change model, risk assessment and planned dates.
Change scheduling
Entering the change in the change calendar after checking collisions with other changes, change freeze periods, business cycles and resource availability.
Change authorization step
The change authority reviews the assessment and records a decision; only authorized changes progress to build, test and deployment.
Change closure
Verifying the intended outcome was achieved, updating the configuration management database and documentation, closing the record, and capturing lessons learned.
Post-implementation review
A review after a significant, failed, emergency or unauthorized change that verifies outcomes, explains deviations and records corrective and improvement actions.
Change and incident interface
Emergency changes restore service after major incidents, while incidents caused by changes feed back into change assessment and continual improvement.
Change and release interface
Change enablement authorizes the change; release and deployment management build, test and deploy it; the practices are distinct but tightly coordinated.
Change and configuration interface
Change records are linked to configuration items, and the configuration management database is updated as part of change closure.
Standard change via service request
Standard changes are typically triggered through the service request management practice, using a pre-authorized model without a new authorization decision.
Change enablement in value chain
The practice primarily supports design and transition and obtain/build, and contributes to plan, engage, deliver and support, and improve activities.
Change success rate
The proportion of changes implemented without causing an incident, outage or unplanned rollback; a core measure of change enablement effectiveness.
Percentage of unauthorized changes
The share of changes made without the required authorization; a high value indicates the change model is too heavy or poorly communicated.
Change lead time
The elapsed time from change registration to implementation; long authorization waits reveal bottlenecks in the change value stream.
Organizational change management for changes
Addressing stakeholder engagement, communication, training and readiness so people adopt a change; it complements technical risk and authorization controls.