ITIL 4 Change Enablement study materials
ITIL 4 Change Enablement study resources

ITIL 4 Change Enablement key terms

ITIL 4 Change Enablement · Get comfortable with the vocabulary.

Change enablement

The practice that maximizes the number of successful service and product changes by ensuring risks are properly assessed, changes are authorized to proceed, and a change schedule is managed.

Related: Change, Change model, Change authority
Change

The addition, modification, or removal of anything that could have a direct or indirect effect on services, products, or the organization's ability to deliver value.

Related: Change model, Change enablement
Change policy

A documented set of rules describing how changes are categorized, assessed, authorized, and recorded in an organization, including who may approve each type of change.

Related: Change model, Change authority, Standard change
Change type

A category assigned to a change, commonly standard, normal, or emergency, that determines which model, assessment depth, and authority apply to it.

Related: Standard change, Normal change, Emergency change
Change model

A repeatable, defined approach for handling one type of change, describing the steps, roles, timescales, and criteria to apply from request through to closure.

Related: Change type, Risk-based categorization, Change authority
Standard change

A low-risk, well-understood, and repeatable change that is pre-authorized by the change policy and follows a documented procedure, so no individual approval is needed each time.

Related: Change type, Change policy
Normal change

A change that is not pre-authorized and must be scheduled, assessed, and authorized through a defined process whose rigour matches the level of risk.

Related: Change type, Change advisory board
Emergency change

A change that must be implemented as soon as possible, for example to restore service after a major incident or close a security vulnerability, and which uses an expedited assessment and authorization path.

Related: Emergency change advisory board, Incident management
Risk-based categorization

The activity of assigning each change to a change type and change model according to its assessed likelihood and impact, so that effort and authority match the risk.

Related: Risk assessment, Change type, Change model
Change impact

The effect a change may have on services, users, components, and other changes, used together with likelihood to judge risk and decide how much control is needed.

Related: Risk assessment, Change collision, Service configuration management
Change authority

The person or group accountable for deciding whether a particular change may proceed, with the level of authority set by the change policy and the change's risk.

Related: Change advisory board, Delegated authority, Change authorization
Change advisory board (CAB)

A group, often including technical and business representatives, that assesses higher-risk normal changes and recommends or makes the authorization decision within its delegated authority.

Related: Change authority, Normal change, Change assessment
Emergency change advisory board (ECAB)

A small, empowered group that can meet at short notice to assess and authorize emergency changes, so urgent work is not delayed by the full advisory board's schedule.

Related: Emergency change, Change authority
Risk assessment

The evaluation of a change's likelihood of failure and potential impact, together with its expected benefits, so that decision-makers can judge whether the risk is acceptable.

Related: Change impact, Risk-based categorization, Change assessment
Delegated authority

Authority to authorize changes that has been formally passed from a higher level, such as a CAB, to a named individual or team, with agreed limits on scope and risk.

Related: Change authority, Change authorization
Request for change

The formal record raising a proposed change, capturing what is to change, why, the desired outcome, and the initial details needed for assessment and scheduling.

Related: Change register, Change assessment
Change register

A log holding every change record with its details, status, assessment, authorizations, and outcome, giving a single view of changes in progress and completed.

Related: Request for change, Change schedule, Change closure
Change schedule

A calendar showing planned changes, their timing, and the components and services affected, used to plan work, communicate with users, and avoid clashes.

Related: Change collision, Change freeze, Change enablement
Change assessment

The review of a change's risk, impact, expected benefit, resource needs, and readiness, producing the information authorizers need and any conditions for implementation.

Related: Risk assessment, Change authorization, Change advisory board
Change authorization

The formal decision, taken by the appropriate change authority, that a change may proceed; it may be given with conditions and is recorded against the change record.

Related: Change authority, Change assessment, Delegated authority
Change implementation

Carrying out the approved change according to plan, including build, test, and deployment steps, with the agreed back-out plan available if the change does not succeed.

Related: Back-out plan, Deployment management, Change closure
Change closure

The final stage of the change lifecycle, confirming the change was implemented and its outcome recorded, updating logs, and capturing lessons for future changes.

Related: Post-implementation review, Change register
Back-out plan

A documented procedure describing how to restore the previous state if a change does not succeed, including the steps, timeframe, and who decides to invoke it.

Related: Change implementation, Emergency change
Change collision

A situation where two or more changes affect the same components or services at overlapping times, creating risk of conflict, disruption, or failed implementation.

Related: Change schedule, Change impact
Change freeze

A defined period, such as a peak trading time, during which normal changes are restricted or prohibited so that stability of critical services is protected.

Related: Change schedule, Normal change
Post-implementation review

A check after a change is live that confirms the expected outcome was achieved, identifies unintended effects, and records lessons to improve future changes.

Related: Change closure, Continual improvement
Service value chain

The six connected activities of plan, improve, engage, design and transition, obtain and build, and deliver and support, through which the organization turns demand into value.

Related: Value stream, Change enablement
Value stream

A sequence of activities, practices, and resources that together create value for a stakeholder in response to a specific demand, such as delivering a change.

Related: Service value chain, Change model
Release management

The practice of making new and changed services and features available for use, working with change enablement to confirm what is authorized to go live.

Related: Deployment management, Change authorization
Deployment management

The practice of moving new or changed hardware, software, documentation, or data to live environments, typically executed under an authorized change.

Related: Release management, Change implementation
Service configuration management

The practice of ensuring accurate, reliable information about configuration items and their relationships is available, which supports impact and risk assessment of changes.

Related: Change impact, Change assessment
Incident management

The practice of minimizing the negative impact of incidents by restoring normal service as quickly as possible, sometimes requiring emergency changes to achieve this.

Related: Emergency change, Change enablement
Organizational change management

The management of the people side of change, covering stakeholder engagement, communication, training, and support so that changes are adopted and sustained.

Related: Stakeholder engagement, Change enablement
Change success rate

The proportion of changes that are implemented without causing an incident, requiring a back-out, or failing to deliver their intended outcome.

Related: Continual improvement, Post-implementation review
Continual improvement

The recurring activity of identifying and acting on opportunities to improve products, services, and practices, applied to change enablement through metrics, reviews, and lessons learned.

Related: Change success rate, Post-implementation review
Stakeholder engagement

Identifying the people and groups affected by or interested in a change, and communicating with and involving them appropriately so the change is understood and accepted.

Related: Organizational change management, Change