Fixed-Price Supplier and a Known Risk

Project Manager Examination · Put your knowledge to work in context.

All case studies

Fixed-Price Supplier and a Known Risk

MetroWater has awarded a $1.2 million fixed-price contract for a 10-month customer billing implementation. The supplier was the lowest bidder and its statement of work assumes clean legacy data. During discovery, the team finds that 20% of customer records have duplicate or missing addresses; the supplier claims $180,000 extra for cleansing. Separately, a municipal permit required for the data-center migration may be delayed: the risk register estimates a 25% probability and a $400,000 impact if the migration slips two months. For $60,000, a consultant can expedite the permit with high confidence. The supplier is already three weeks late. The contract includes a change clause, a 10% cap on liquidated damages at $5,000 per day, and no data-quality warranty from the buyer. The project manager holds a $120,000 management reserve and a $90,000 contingency reserve.

1. Calculate the expected monetary value of the permit risk and recommend a response. Which reserve should fund it, and what assumptions would you test?

Read the worked answer

EMV of the permit risk = 0.25 × $400,000 = $100,000. The expediter costs $60,000 with high confidence, so the expected net benefit of expediting is about $40,000 compared with doing nothing, before considering schedule and reputational effects. On pure EMV, expedite. But check the assumptions: is the $400,000 impact the full business case, including delay penalties and lost revenue? Is the 25% probability still valid after discovery? If expediting does not eliminate the risk, compare $60,000 against the residual EMV. Also consider response strategy: this is mitigation-reducing probability-rather than avoidance or transfer; a permit delay may be insurable or contractually shared, but that is unlikely. Fund the expediter from the contingency reserve because it addresses an identified risk, not from management reserve. Document the decision, update the risk register, and assign an owner to track the permit.

2. How should the project manager handle the supplier's $180,000 claim for data cleansing? Distinguish between a change and a failure.

Read the worked answer

First read the contract, not the claim. The statement of work assumes clean legacy data; the buyer gave no data-quality warranty; discovery found 20% defective records. That supports the supplier's position that cleansing is outside the fixed price-unless the SOW also made the supplier responsible for data validation or the buyer disclosed the sample data. Treat it as a change, not a failure: request a detailed breakdown of the $180,000, compare it with independent estimates, and negotiate scope (for example, buyer cleanses and supplier validates, or cleanse only records needed for migration). Do not simply pay or refuse. Issue a formal change order if the work is authorized, with schedule and cost impact, and update the contract's scope baseline. Also separate this from the three-week delay: determine whether the delay is supplier-caused, buyer-caused by data, or shared. Documenting the causal link protects both the claim analysis and any liquidated-damages decision.

3. Should the project manager invoke liquidated damages for the three-week delay? Explain how the reserves should and should not be used.

Read the worked answer

Liquidated damages are a contractual remedy, not a management tool. Before invoking them, establish the cause of the three-week delay. If it is supplier-caused and the contract notice provisions were followed, the buyer is entitled to $5,000 per day up to 10% of contract value, or $120,000, but withholding payment can damage the relationship and delay further. If the delay is caused by buyer data or the permit, liquidated damages may not apply. The project manager should send a contractual notice, document daily, and separate the delay analysis from the commercial negotiation. Reserves: the $90,000 contingency is for identified risks such as the permit; the $120,000 management reserve is for unidentified risks and should not be used to pay a known scope change. If the $180,000 claim is valid, it needs a change order and potentially additional funding, not a reserve raid. Escalate the commercial decision to the procurement or contract owner.