Core rules

  • Risk management includes planning, identification, qualitative and quantitative analysis, response planning, and monitoring. The risk register records causes, triggers, owners, responses, and residual risk.
  • Threat strategies: avoid, mitigate, transfer, accept, escalate. Opportunity strategies: exploit, enhance, share, accept, escalate.
  • EMV = probability × impact. Use it to compare risk exposure, not to replace judgment.
  • Make-or-buy analysis decides whether to procure. A statement of work defines the procurement scope; a bidder conference ensures common understanding.
  • Fixed-price contracts place cost risk on the seller; cost-reimbursable contracts place more cost risk on the buyer; time and materials suits small, uncertain efforts.

Worked example

A risk has a 20% probability of a −$50,000 impact, so EMV = 0.20 × −50,000 = −$10,000. A mitigation costs $6,000 and reduces probability to 5%, leaving residual EMV = 0.05 × −50,000 = −$2,500. Total exposure becomes −$8,500, an improvement of $1,500. Reasoning: compare the cost of mitigation with the reduction in EMV, not with the full impact alone.

Traps that cost marks

  • Believing transfer eliminates risk; it shifts financial consequence, not ownership of the event.
  • Choosing fixed-price because it sounds safe when scope is undefined.
  • Awarding to the lowest bid without evaluating technical capability.
  • Changing contract scope informally instead of through contract change control.