LARE Section 4 flashcards
LARE Section 4 · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Contour interval
- The vertical distance in elevation between two adjacent contour lines on a topographic map. A smaller interval reveals finer terrain detail and is used for flatter sites.
- Percent slope formula
- Slope percent equals rise divided by run, multiplied by 100. A 1-foot rise over 20 feet of run is a 5 percent slope, the maximum typical accessible running slope.
- Cut and fill balance
- A grading condition in which excavated soil volume equals the volume needed for fill, minimizing hauling costs. Unbalanced sites require importing or exporting earthwork.
- 100-year floodplain
- Land inundated by a flood having a 1 percent chance of occurring in any given year. The 500-year floodplain corresponds to a 0.2 percent annual probability.
- Rational method
- Peak runoff formula Q = CiA, where C is the runoff coefficient by surface type, i is rainfall intensity, and A is drainage area. Used to size storm drainage.
- Standard of care
- The degree of skill and care ordinarily exercised by competent landscape architects under similar circumstances. It defines the benchmark for professional negligence claims.
- Graphic scale
- A drawn bar scale that remains accurate if a drawing is photographically enlarged or reduced, unlike a stated ratio such as 1 inch equals 20 feet.
- Bearing versus azimuth
- Bearing is an angle from north or south toward east or west, written with a quadrant letter. Azimuth is a clockwise angle from north ranging 0 to 360 degrees.
- Metes and bounds
- A legal description of land that follows boundary courses and distances from a point of beginning, often referencing monuments, and returns to close the traverse.
- Benchmark
- A fixed point of known elevation used as a reference for survey work. A temporary benchmark is established for a project and tied to a permanent datum.
- USGS quadrangle map
- A topographic map typically at 1:24,000 scale showing contours, planimetric features, and land cover. Used for early site inventory and regional context analysis.
- Specifications precedence
- Contract language that establishes which document governs when drawings and specifications conflict. Specifications commonly control over drawings unless the contract states otherwise.
- Soils report contents
- A geotechnical report giving bearing capacity, seasonal high water table, permeability, and shrink-swell potential. These values inform footing, paving, and drainage design.
- Tree protection zone
- The area around a tree where disturbance is restricted to protect roots. It is often set at the dripline or a radius based on trunk diameter per local code.
- Plan detail scale
- Detail drawings depict small areas at large scale, such as 1 inch equals 1 foot, while site plans use small scales, such as 1 inch equals 50 feet.
- Concrete 28-day strength
- Concrete mix design is specified by compressive strength reached at 28 days. Landscape flatwork typically uses 3,000 to 4,000 psi, often air entrained for freeze-thaw resistance.
- Asphalt pavement section
- A layered assembly of compacted subgrade, aggregate base, and hot-mix asphalt surface. Base compaction is verified as a percentage of maximum dry density.
- Permeable paver system
- Unit pavers with open-graded aggregate joints and base that store and infiltrate stormwater. The reservoir layer is sized for the design storm and soil infiltration rate.
- AIA A201 General Conditions
- Standard contract general conditions defining the architect's administration role, including site visits and issuing interpretations, but not supervising or controlling construction means and methods.
- Change order
- A written modification to the contract, signed by owner and contractor, adjusting scope, price, or time. A construction change directive orders work before price agreement.
- Request for information
- A formal written question from the contractor seeking clarification of contract documents. The designer's response may result in a clarification or a change order.
- Shop drawing review
- The designer's check of contractor submittals for conformance with the design concept and contract documents, not for approval of the contractor's means and methods.
- Substantial completion
- The stage when work is sufficiently complete for its intended use. It triggers warranties, retainage release, and the start of the correction period for punch list items.
- Critical path
- The longest-duration sequence of dependent activities through a project network. Any delay on the critical path delays project completion because it has zero total float.
- Total float
- The time an activity can be delayed without delaying project completion. It equals late finish minus early finish, or late start minus early start.
- Unit cost estimating
- An estimating method multiplying a cost per unit, such as per square foot of paving, by the quantity. Accuracy improves with more detailed quantity takeoffs.
- Instructions to bidders
- A contract document describing bidding procedures, submission requirements, and evaluation criteria. It is distinct from the general and supplementary conditions.
- Retainage
- A percentage of each progress payment withheld by the owner until completion. It protects the owner against incomplete or defective work and lien exposure.
- Mechanics lien
- A statutory claim against a property by contractors or suppliers for unpaid work or materials. Lien waivers release these rights when payment is received.
- Gantt bar chart
- A scheduling graphic showing activities as bars along a time axis. It communicates duration well but shows dependencies and float less clearly than a network diagram.
- Punch list
- A record of incomplete or defective items identified at substantial completion. Items must be corrected before final payment and release of retainage.
- Performance bond
- A surety instrument guaranteeing the contractor will complete the work per the contract. Payment bonds separately protect subcontractors and suppliers from nonpayment.