- Takt time
- Available production time divided by customer demand rate, expressed as time per unit. It sets the pace the process must meet; cycle time above takt time means demand cannot be satisfied.
- Little's Law
- Throughput time equals work in process divided by throughput rate. At a fixed completion rate, cutting WIP by half halves the time a unit spends in the system.
- Value-added ratio
- Value-added processing time divided by total lead time. It expresses how much of the elapsed time a customer would pay for; most streams score in the low single digits.
- Rolled throughput yield
- The product of first-pass yields at every step in a process. Because yields multiply, it reveals hidden rework that a simple average yield figure conceals.
- Push versus pull
- Push releases work according to a forecast and schedule. Pull releases work only when a downstream customer or process consumes it, capping inventory and shortening lead time.
- Overproduction waste
- Producing more, earlier, or faster than the next process or customer needs. It is considered the worst waste because it creates excess inventory and hides defects and imbalance.
- Days of supply
- On-hand inventory quantity divided by average daily demand. It converts stock counts into time, which is the measure that matters when comparing queues to lead time.
- Seven wastes
- Overproduction, waiting, transportation, overprocessing, inventory, motion, and defects. Many organizations add unused human talent as an eighth waste.
- Cost of poor quality
- Appraisal costs plus internal failure costs plus external failure costs. Prevention spending reduces the total, while inspection alone shifts cost without removing the defect source.
- Spaghetti diagram
- A drawing of the actual path people, material, or documents take through a layout. Distance and number of crossings are measured to target layout and flow improvements.
- Current and future state maps
- The current-state map documents existing material and information flow; the future-state map designs the improved flow. An action plan with owners and dates bridges them.
- Process box on a map
- A rectangle representing one process step, annotated with cycle time, changeover time, uptime, batch size, and available time. Inventory triangles between boxes record queue quantities.
- Effective capacity
- Available time multiplied by uptime, divided by cycle time. Comparing each step's effective capacity with demand identifies the real bottleneck rather than the slowest nominal cycle.
- PDCA cycle
- Plan establishes a target condition and method, Do runs the experiment, Check compares results with the target, Act standardizes or adjusts. No target condition means no improvement cycle.
- 5S workplace organization
- Sort, set in order, shine, standardize, sustain. Sustain is the step most often lost; it requires scheduled audits, visible scores, and named owners for each area.
- Standard work
- A documented specification of takt time, work sequence, and standard in-process stock for a process. It provides the baseline against which any change is measured and evaluated.
- SMED
- Single-minute exchange of die. Setup steps are separated into internal, performed while the machine is stopped, and external, performed while it runs; internal work is converted then reduced.
- Kanban rules
- Downstream withdraws what it needs, upstream produces only what is withdrawn, nothing moves without a kanban, and the number of kanban cards caps total work in process.
- Jidoka
- Stopping the process immediately when an abnormality occurs so defective work is not passed downstream. Andon signals request help, and root cause analysis follows the stop.
- Poka-yoke
- Error prevention built into the process using contact, fixed-value, or motion-step methods. Prevention at the source is preferred over detection and over relying on operator training.
- A3 problem solving
- A one-page structure covering background, current condition with data, target condition, root cause, countermeasures, implementation plan, and follow-up. The format forces concise, evidence-based thinking.
- Five whys
- Repeatedly asking why a problem occurred until the systemic cause is reached, then countermeasuring that cause. Each answer should be verified against evidence at the process, not assumed.
- Kaizen event
- A focused improvement workshop, typically five days, that scopes and baselines the process, analyzes it, implements and trials changes, then standardizes results and reports them.
- Hoshin kanri
- Policy deployment that translates annual objectives into measurable targets at each organizational level, using catchball dialogue to negotiate and align targets up and down the chain.
- Leader standard work
- A defined daily and weekly routine for leaders, including gemba walks, tiered meetings, and escalation checks, that sustains improvement after a project team disbands.
- Tiered daily management
- Short stand-up meetings at successive organizational levels with a fixed agenda, visible metrics, and a defined escalation path and time limit for unresolved issues.
- Value stream manager
- A role accountable for end-to-end flow and lead time across a product family. It intentionally crosses functional boundaries, so its authority must be defined explicitly.
- Gemba
- The actual place where work is performed. Observing the real process there is treated as the primary source of truth; reports and dashboards are secondary evidence.
- Respect for people
- Engaging the people who do the work in designing standards, and leaders asking questions rather than imposing countermeasures. It is a mechanism for improvement, not a courtesy.
- Local efficiency metric trap
- Measuring each department on utilization or efficiency encourages building inventory and overproduction. Flow and lead-time measures align local behavior with end-to-end performance.
- Pilot then replicate
- Deploy Lean first in a constrained area, prove results with data, standardize the new method, then spread it to other areas with local adaptation rather than literal copying.
- 70-20-10 learning
- A common Lean capability model: most learning happens on the job in a real improvement, some through coaching, and a minority through classroom instruction.