LEED AP BD+C: Integrative Process

LEED AP BD+C · Work through your exam, one topic at a time.

All guide sections

Integrative Process

What the category rewards

Integrative Process (IP) rewards a team that studies how systems interact before design hardens. In LEED v4 BD+C it is a single-point credit; LEED v4.1 restructures the requirement (and elevates it toward prerequisite status), so confirm which version your exam targets before memorizing point values. The credit has two parts: an early design charrette and discovery-phase analysis of energy- and water-related systems.

Concepts to know

  • Owner's Project Requirements (OPR) - measurable written goals against which every later analysis and commissioning activity is judged.
  • Energy analysis: a simple box or massing model comparing at least two schemes (orientation, envelope, glazing, HVAC strategy) including life-cycle cost.
  • Water analysis: a conceptual site water budget covering potable supply, fixture demand, irrigation demand, and rainwater/greywater reuse opportunities.
  • The analysis must inform the design, not document a decision already made.

Traps

  • IP is not commissioning and is not satisfied by a kickoff meeting or an integrated design charrette alone.
  • Both energy and water analysis are required; doing only one earns nothing.
  • A charrette held after schematic design is complete is usually too late to earn the credit.
  • Submitting a consultant's report with no evidence that a design decision changed is a classic distractor.

Rule of thumb

Ask two questions of every IP scenario: when did it happen (must be pre-design/discovery) and what changed (the analysis must alter a decision). If either answer is missing, treat the credit as failed.