PKMC Module III key terms
PKMC Module III · Get comfortable with the vocabulary.
- Project Management Life Cycle
- Related: Phase Gate, Project Charter
The sequence of phases a project passes through from start to finish, typically initiating, planning, executing, monitoring and controlling, and closing, with decision gates between phases.
- Phase Gate
- Related: Project Management Life Cycle, Stage Gate Review
A formal review point at the end of a project phase where stakeholders confirm deliverables, approve continued funding, and authorize the next phase or terminate the effort.
- Project Charter
- Related: Project Sponsor, Assumption Log
The document that formally authorizes a project, names the project manager, states high-level objectives and constraints, and gives the manager authority to apply organizational resources.
- Project Sponsor
- Related: Project Charter, Steering Committee
The executive who champions the project, provides funding, resolves escalated issues, and approves major changes, acting as the link between the project and organizational leadership.
- Steering Committee
- Related: Project Sponsor, Change Control Board
A governance group of senior leaders that sets project direction, approves scope and budget changes above thresholds, and removes obstacles the project manager cannot resolve alone.
- Stakeholder Register
- Related: Stakeholder Analysis, Communication Plan
A living document recording each stakeholder's role, contact details, influence, interest, expectations, and engagement approach, used to plan communication and manage relationships.
- Stakeholder Analysis
- Related: Stakeholder Register, Communication Plan
The process of identifying stakeholders and assessing their power, interest, influence, and impact so engagement effort can be prioritized and tailored to each group.
- Requirements Traceability Matrix
- Related: Requirements Gathering, Scope Baseline
A table linking each requirement to its source, related design elements, and test cases, used to confirm that every requirement is delivered and verified.
- Requirements Gathering
- Related: Requirements Traceability Matrix, Scope Statement
The elicitation of stakeholder needs through interviews, workshops, observation, and document review, then converting them into documented, testable requirements.
- Scope Statement
- Related: Scope Baseline, Scope Creep
A narrative description of the project's boundaries: what is included, what is excluded, key deliverables, acceptance criteria, and assumptions and constraints.
- Scope Baseline
- Related: Work Breakdown Structure, Scope Statement
The approved combination of the scope statement, work breakdown structure, and WBS dictionary, used as the reference against which scope changes and completion are measured.
- Work Breakdown Structure (WBS)
- Related: Work Package, Scope Baseline
A hierarchical, deliverable-oriented decomposition of total project scope into manageable work packages that can be estimated, scheduled, and assigned.
- Work Package
- Related: Work Breakdown Structure (WBS), Activity Sequencing
The lowest level of a work breakdown structure, small enough to estimate cost and duration reliably and to assign to a single owner for execution and control.
- Activity Sequencing
- Related: Critical Path, Schedule Baseline
The process of ordering schedule activities and documenting dependencies, such as mandatory, discretionary, and external relationships, to build a logical network.
- Critical Path
- Related: Float, Schedule Baseline
The longest dependent sequence of activities through a schedule network, determining the shortest possible project duration; any delay on it delays the project finish.
- Float (Slack)
- Related: Critical Path, Schedule Baseline
The amount of time an activity can be delayed without delaying the project finish (total float) or its successor (free float).
- Schedule Baseline
- Related: Critical Path, Earned Value Management
The approved version of the project schedule, including start and finish dates and milestones, against which actual progress is compared to measure schedule performance.
- Analogous Estimating
- Related: Parametric Estimating, Bottom-Up Estimating
A top-down cost or duration estimate based on historical data from similar past projects, adjusted for known differences; fast but less accurate than detailed methods.
- Parametric Estimating
- Related: Analogous Estimating, Bottom-Up Estimating
An estimating technique that multiplies a measurable unit rate from historical data, such as cost per square meter, by the quantity required for the current project.
- Bottom-Up Estimating
- Related: Work Package, Contingency Reserve
An estimating approach that builds total project cost or duration by aggregating detailed estimates prepared for each individual work package or activity.
- Contingency Reserve
- Related: Management Reserve, Risk Register
Budget set aside for identified risks that have been analyzed and accepted, held by the project manager and released as those risks occur or are retired.
- Management Reserve
- Related: Contingency Reserve, Cost Baseline
Budget held outside the cost baseline for unplanned scope changes or unknown risks, controlled by senior management and requiring formal approval before use.
- Cost Baseline
- Related: Earned Value Management, Management Reserve
The approved time-phased project budget, excluding management reserve, against which actual expenditures and earned value performance are tracked and reported.
- Earned Value Management (EVM)
- Related: Schedule Performance Index, Cost Performance Index
A performance measurement method comparing planned value, earned value, and actual cost to quantify cost and schedule variance and forecast likely final outcomes.
- Schedule Performance Index (SPI)
- Related: Cost Performance Index, Earned Value Management (EVM)
Earned value divided by planned value; a ratio below one indicates the project is behind schedule relative to the baseline at the measurement date.
- Cost Performance Index (CPI)
- Related: Schedule Performance Index (SPI), Estimate at Completion
Earned value divided by actual cost; a ratio below one means work is costing more than budgeted, while a value above one indicates cost efficiency.
- Estimate at Completion (EAC)
- Related: Cost Performance Index (CPI), Earned Value Management (EVM)
A forecast of total project cost based on current performance, commonly calculated as budget at completion divided by the cost performance index.
- Quality Assurance
- Related: Quality Control, Quality Management Plan
The process-oriented activities that audit processes and standards to confirm the team is building quality in, rather than inspecting defects out after delivery.
- Quality Control
- Related: Quality Assurance, Acceptance Criteria
The product-oriented activity of inspecting and testing deliverables against acceptance criteria and quality standards, recording defects and verifying corrective actions.
- Acceptance Criteria
- Related: Quality Control, Requirements Traceability Matrix
The specific, testable conditions a deliverable must satisfy for the customer or sponsor to formally accept it as complete and conforming.
- Risk Register
- Related: Risk Response Strategy, Contingency Reserve
A log of identified risks with their probability, impact, score, owner, response strategy, and status, reviewed regularly throughout the project.
- Risk Response Strategy
- Related: Risk Register, Issue Log
A chosen approach for handling a risk, such as avoid, mitigate, transfer, accept for threats, or exploit, enhance, share, accept for opportunities.
- Issue Log
- Related: Risk Register, Escalation Path
A record of problems that have already occurred and are affecting the project, tracking owner, impact, escalation, and resolution status until closed.
- Procurement Plan
- Related: Statement of Work, Fixed-Price Contract
The document describing what will be purchased, the contract types and selection methods to be used, and the schedule for soliciting and awarding vendor work.
- Statement of Work (SOW)
- Related: Procurement Plan, Service Level Agreement
A document defining the work a vendor must perform, including deliverables, standards, schedule, and acceptance terms, forming the basis for bids and contracts.
- Fixed-Price Contract
- Related: Time and Materials Contract, Statement of Work (SOW)
An agreement where the seller commits to a defined scope for a set price, placing cost-overrun risk mainly on the seller and requiring clear, stable requirements.
- Time and Materials Contract
- Related: Fixed-Price Contract, Procurement Plan
An agreement paying the seller for actual labor hours at agreed rates plus materials, useful when scope is uncertain but requiring caps and close monitoring.
- Service Level Agreement (SLA)
- Related: Statement of Work (SOW), Vendor Performance Review
A contract annex specifying measurable service targets such as uptime or response time, with remedies or credits when the vendor misses those targets.
- Vendor Performance Review
- Related: Service Level Agreement (SLA), Procurement Plan
A structured evaluation of a seller's delivery against quality, schedule, cost, and contract terms, feeding decisions on corrective action or future awards.
- Communication Plan
- Related: Stakeholder Register, Escalation Path
A document defining who receives what information, in which format, how often, and through which channel, plus who is responsible for each communication.
- Escalation Path
- Related: Issue Log, Steering Committee
The agreed chain of contacts and timeframes for raising an issue above the project manager when it exceeds their authority or threatens project objectives.
- RACI Matrix
- Related: Communication Plan, Team Development
A responsibility chart labeling each stakeholder or role as Responsible, Accountable, Consulted, or Informed for specific tasks, clarifying ownership and decision rights.
- Team Development
- Related: RACI Matrix, Conflict Resolution
Activities that build capability and cohesion, such as training, co-location, and team-building, moving a group through forming, storming, norming, and performing stages.
- Conflict Resolution
- Related: Team Development, Escalation Path
The use of techniques such as collaborating, compromising, or smoothing to address disagreements constructively and preserve working relationships within the team.
- Change Control Board
- Related: Change Request, Integrated Change Control
A group authorized to review change requests, assess impacts on scope, schedule, cost, and risk, and approve, defer, or reject each request formally.
- Change Request
- Related: Change Control Board, Integrated Change Control
A formal proposal to modify scope, schedule, cost, or quality, documented with rationale and impact analysis before being routed to the change control process.
- Integrated Change Control
- Related: Change Request, Change Control Board
The process of reviewing all change requests, assessing their combined effects across baselines, and updating plans and documents only after approval.
- Scope Creep
- Related: Scope Baseline, Change Request
Uncontrolled expansion of project scope through small, unapproved additions that erode schedule and budget without corresponding adjustments to baselines.
- Lessons Learned
- Related: Project Closure, Phase Gate
Documented insights about what worked and what did not, captured during and after the project and stored for reuse by future teams.
- Project Closure
- Related: Lessons Learned, Acceptance Criteria
The final process of confirming deliverables are accepted, releasing resources, closing contracts, archiving records, and obtaining formal sign-off from the sponsor.