PKMC Module III: Project Control, Change Management, and Closure

PKMC Module III · Work through your exam, one topic at a time.

All guide sections

Project Control, Change Management, and Closure

What the exam tests

Control, change, and closure test integrated change control, baseline discipline, performance reporting, and end-of-project transition.

Core rules

  • Integrated change control evaluates every change request for impact on scope, schedule, cost, quality, risk, and benefits. The change control board approves, rejects, or defers; approved changes update the relevant baselines and plans.
  • Configuration management controls versions of deliverables and documents so the team works from the approved version.
  • Performance reporting compares actuals with baselines using EVM, milestones, and quality metrics; forecasts should state assumptions.
  • Closure includes customer acceptance, transition to operations, contract closure, final report, archive, lessons learned, and resource release. Lessons learned are captured throughout and consolidated before the team disperses.

Worked example

A stakeholder requests a new report worth 10 days and $20k while CPI is 0.90. The PM documents the request, analyzes schedule and cost impact, and sends it to the CCB. If approved, the baseline and forecast are updated; if rejected, the request and rationale are recorded. Reasoning: the PM does not unilaterally absorb scope or silently change the baseline; the CCB owns the decision.

Traps

  • Accepting small changes informally until scope creep appears.
  • Updating the baseline without approval.
  • Treating a final meeting as closure while acceptance and transition remain open.
  • Waiting until the last day to collect lessons learned.