NABCEP PVIS study plan
NABCEP PVIS · Give each week a clear focus.
8 weeks · About 7 hours per week
PV Installation Professional (PVIP) - domain structure not enumerated in source
Map the PVIP task list into your own checklist of site assessment, sizing, permitting, installation, commissioning, and O&M subtopics
Explain how irradiance, air mass, and tilt/orientation interact to set array energy yield
Compute a simple string sizing check (Voc temperature-corrected at record low, Vmp window at high cell temperature) for a sample 10 kW array
Identify the NEC Articles and sections most cited on the exam (690, 705, 250, 310, 480) and note what each governs
Your checkpoint
A one-page formula sheet plus 10 worked string-sizing and voltage-drop problems with answers checked against manufacturer datasheets
PV Installation Professional (PVIP) - domain structure not enumerated in source
Perform a full site survey exercise: shade analysis, roof condition, structural attachment points, interconnection location, and pathway routing
Size a residential grid-tied system from an annual kWh target including derate factors and soiling
Select conductors, OCPD, and disconnects for the DC and AC sides using continuous-load and 125% rules
Draft a single-line diagram for a string inverter system with rapid shutdown
Your checkpoint
A complete design package for one fictional residence: load analysis, array layout sketch, single-line diagram, and bill of materials
PV Installation Professional (PVIP) - domain structure not enumerated in source
Interpret NEC 690 requirements for rapid shutdown, PV source/output circuits, and labeling
Apply NEC 705 interconnection rules for supply-side and load-side connections and calculate busbar loading
Explain grounding and bonding requirements for PV systems including equipment grounding conductors and array bonding
Describe structural and weatherproofing considerations for roof and ground mounts
Your checkpoint
A 20-question self-written code quiz with cited NEC sections and a written explanation for every answer
PV Installation Professional (PVIP) - domain structure not enumerated in source
Sequence a commissioning procedure: visual inspection, insulation resistance, polarity, open-circuit and operating current checks, and performance verification
Diagnose common faults (ground fault, arc fault, underperforming string, inverter derating) and state the test that isolates each
Explain storage integration basics: ESS sizing, inverter modes, and NEC 706 concepts
Practice safe work practices for DC arc hazard and energized work
Your checkpoint
A commissioning checklist and a troubleshooting decision tree covering at least eight fault scenarios
PV Installation Professional (PVIP) - domain structure not enumerated in source
Work through the permitting and interconnection workflow including utility application data and inspection readiness
Compare string, microinverter, and hybrid inverter architectures on cost, shading tolerance, and code implications
Calculate voltage drop and verify conductor ampacity derating for temperature and conduit fill
Review O&M practices including monitoring alarms, IV curve tracing, and cleaning schedules
Your checkpoint
A comparison matrix of three system architectures scored against five project constraints, with a recommendation memo
PV Installation Professional (PVIP) - domain structure not enumerated in source
Answer timed practice sets under exam conditions and log every missed question by root cause
Re-derive from memory the formulas for string voltage limits, voltage drop, energy yield, and conductor sizing
Review battery and energy storage safety requirements including ventilation, clearances, and disconnection
Explain the roles and limits of the PV Installation Professional in project scope and job safety analysis
Your checkpoint
A timed 60-question practice exam with a scored error log grouped by root cause
PV Installation Professional (PVIP) - domain structure not enumerated in source
Close every gap identified in the week 6 error log by reworking the underlying concept
Rehearse code lookups quickly using the index and article structure for unfamiliar questions
Complete two hands-on exercises, such as a torque and terminations drill and a megger test on a mock array
Explain inspection red flags that commonly fail a final inspection
Your checkpoint
A closed-gap report showing each weak area, the corrective action taken, and a re-test score of at least 85%
PV Installation Professional (PVIP) - domain structure not enumerated in source
Take two full-length timed practice exams and review every answer, right or wrong
Summarize your formula sheet and code map onto one page for final review
Confirm exam-day logistics, allowed references, and identification requirements
Rest and taper: limit study to light review in the final 48 hours
Your checkpoint
A final one-page reference sheet and a practice exam score of at least 85% on both attempts
Milestones
Week 2: Can complete a full residential design package with correct string sizing and a coherent single-line diagram without references
Week 4: Scores at least 80% on the self-written code quiz and can cite the governing NEC section for each answer
Week 6: Scores at least 75% on the first timed 60-question practice exam with an error log covering every miss
Week 8: Scores at least 85% on two full-length timed practice exams and has a one-page reference sheet ready