NABCEP PVSI flashcards
NABCEP PVSI · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- NEC 690.12 rapid shutdown
- Requires PV conductors outside the array boundary to be reduced to ≤30 V within 30 seconds of shutdown; applies to rooftop and ground-mounted systems per the 2017 and 2020 NEC.
- Cold-temperature Voc correction
- Module Voc at the lowest expected ambient temperature equals Voc(STC) × [1 + (Tmin − 25 °C) × βVoc/100], where βVoc is the Voc temperature coefficient in %/°C.
- NEC 690.8 conductor ampacity
- PV source and output circuit conductors must have ampacity ≥ 1.25 × 1.25 × Isc (125% for continuous current and 125% for irradiance) unless using listed combiner or fuse ratings.
- 120% busbar rule
- NEC 705.12(B)(2) permits the sum of the main breaker and PV breaker ratings to be ≤120% of the busbar rating, or the PV breaker may be placed at the opposite end of the busbar.
- NEC 690.13 disconnecting means
- Requires a lockable, manually operable switch that opens all ungrounded conductors of the PV system; the disconnect must be clearly labeled and accessible to the AHJ.
- NEC 690.47 grounding electrode
- DC grounding electrode conductor sized per NEC 250.166; 690.47(C) permits a common DC/AC grounding electrode for inverters listed to UL 1741 with integrated DC grounding.
- Module nameplate STC ratings
- Standard Test Conditions (1000 W/m², 25 °C cell temperature, AM 1.5) ratings for Pmax, Voc, Isc, Vmp, and Imp; used for string sizing and system design calculations.
- String inverter DC input window
- The MPPT voltage range and maximum DC input voltage of a string inverter; the designed string voltage must remain within this window across all expected temperatures.
- Maximum series fuse rating
- The maximum overcurrent protection device rating permitted in series with a PV module, listed on the module nameplate; exceeding it voids the module listing and creates a fire hazard.
- PV Wire vs USE-2
- PV Wire (UL 4703) is rated for outdoor, exposed, and wet locations; USE-2 is rated for underground service entrance. Both are common for DC PV source circuits.
- Combiner box fuse rating
- The DC fuse or breaker rating per string must be ≥1.25 × Isc and ≤ the module maximum series fuse rating; the busbar must be rated for the total combined current.
- Rapid shutdown device
- A UL 1741-listed initiator and transmitter/receiver that reduces PV conductors outside the array boundary to ≤30 V within 30 seconds of shutdown per NEC 690.12.
- DC arc-flash hazard
- DC arcs do not self-extinguish at low current and can sustain at system voltage; arc-flash energy is calculated from module Isc and string voltage, and labels are required per NEC 110.16.
- GFDI test procedure
- Ground-fault detection and interruption must be tested per the manufacturer's procedure; for grounded systems per NEC 690.5 and ungrounded systems per NEC 690.35.
- Insulation resistance test
- Use a megohmmeter at 500 V or 1000 V DC to measure conductor-to-ground resistance; compare to the manufacturer's minimum (often ≥1 MΩ per module or string) and record values.
- I-V curve trace
- Compare measured Pmax, Voc, Isc, and fill factor to expected values at the measured irradiance and cell temperature; a deviation of 10% or more indicates a fault.
- Thermal imaging inspection
- Scan modules, connections, and combiners under load; a temperature rise greater than 10 °C above neighboring components indicates a high-resistance connection or failing component.
- String current comparison
- Measure each string's operating current with a clamp meter; a deviation greater than 10% from the string average indicates a fault, shading issue, or mismatched module.
- Rapid shutdown test
- Measure voltage at the inverter or combiner within 30 seconds of initiating shutdown; confirm ≤30 V at the array boundary per NEC 690.12 and record the result.
- Title block verification
- Confirm the project address, drawing scale, revision number, and date on the title block; ensure all sheets are the current revision before beginning field work.
- Single-line diagram trace
- Trace the power path from modules through strings, combiner, inverter, AC disconnect, and main panel; verify component ratings and conductor sizes against the equipment schedule.
- String sizing table check
- Compare the design string length and voltage window to the cold- and hot-temperature limits; flag any string outside the inverter MPPT window or exceeding maximum DC voltage.
- Electrical panel schedule
- Confirm the PV breaker size, busbar rating, and available space; verify the 120% rule calculation is documented and the breaker is placed correctly on the busbar.
- Structural drawing review
- Verify roof framing, attachment spacing, and load calculations; confirm the racking layout matches the structural engineer's stamped plans and local snow/wind loads.
- Equipment schedule cross-check
- Compare model numbers, ratings, and quantities on the equipment schedule to the delivered equipment; note any substitutions and verify they are approved by the designer.
- As-built documentation
- Record any field changes such as conductor routing or equipment relocation on the plans and obtain approval before energizing the system.
- Pre-inspection checklist
- Verify permits, approved plans, equipment listings, and manufacturer installation manuals are on site before starting the inspection; missing documents can delay the inspection.
- Conduit support spacing
- NEC 334.30 requires conduit to be supported at intervals not exceeding 10 ft and within 3 ft of boxes; verify supports are secure and properly spaced during inspection.
- Labeling inspection
- Confirm all required labels are present and legible: rapid shutdown, DC/AC disconnects, PV system warning, and arc-flash labels per NEC 690.56 and 110.16.
- Functional testing
- Perform the rapid-shutdown test, verify inverter startup and grid-tie, and confirm monitoring communication; record results with timestamps and test conditions.
- Deficiency report
- List each finding with the applicable code reference, a description, and a required corrective action; classify as critical (safety) or non-critical.
- Final inspection report
- Include the inspection date, inspector name, scope, test results, deficiency list, and sign-off; deliver to the AHJ and system owner.