- Solar window shading fraction
- The share of annual sun-path hours blocked by obstructions, read from a Solar Pathfinder or SunEye. Above roughly 20% annual shade, arrays are usually uneconomic without module-level electronics.
- Peak sun hours (PSH)
- The daily solar energy received expressed as hours at 1000 W/m² irradiance. Annual kWh equals array kW times PSH times 365 times the system derate factor.
- Azimuth convention
- Compass direction the array faces, measured in degrees from true north. South is 180°, east 90°, west 270°. Roofs within 30° of south are generally strong production orientations.
- Roof pitch conversion
- Pitch in degrees equals arctangent of rise divided by run. A 4:12 pitch is about 18.4° and 6:12 is about 26.6°, which affects row spacing and self-shading.
- Usable array area
- Total roof area minus required setbacks for fire access, ridges, edges, vents, chimneys, and skylights. It sets the maximum module count and system size.
- System derate factor
- A multiplier, typically 0.75 to 0.85, applied to nameplate output to account for soiling, temperature, mismatch, wiring, inverter, and availability losses in production estimates.
- 120% busbar rule
- NEC 705.12(B) permits the sum of the main breaker and the backfed PV breaker to reach 120% of the panel busbar rating when the PV breaker sits opposite the utility feed.
- Maximum string voltage
- Module open-circuit voltage at STC times the number of modules times the cold-temperature correction factor. It must not exceed the inverter maximum DC input voltage.
- Minimum string length
- The fewest modules whose Vmp at the highest expected cell temperature stays above the inverter MPPT minimum operating voltage and start voltage.
- Voc temperature coefficient
- The percentage change in open-circuit voltage per degree Celsius, typically about minus 0.25 to 0.35 percent. It drives cold-weather maximum voltage calculations for string sizing.
- Pmax temperature coefficient
- The percentage change in maximum power per degree Celsius above 25 °C, typically minus 0.30 to 0.45 percent. Hotter modules produce less power at the same irradiance.
- Rapid shutdown requirement
- NEC 690.12 limits conductors within the array boundary to 80 volts within 30 seconds of shutdown. Module-level electronics or listed shutdown devices satisfy the requirement.
- DC conductor ampacity rule
- PV source and output conductors must be sized at 125% of short-circuit current for continuous duty. Voltage drop should stay near 2% on the DC home run.
- UL 2703 listing
- The standard for racking and mounting systems that provides listed bonding and grounding paths between modules and rails, simplifying equipment grounding conductor installation.
- Microinverter vs string inverter
- Microinverters provide per-module MPPT and monitoring with no high-voltage DC on the roof. String inverters cost less per watt but are sensitive to shading and string mismatch.
- Simple payback
- Net installed cost after incentives divided by first-year utility savings. It ignores rate escalation, degradation, and inverter replacement, so it should accompany a 25-year cash flow.
- Levelized cost of energy
- Present value of all lifecycle costs divided by present value of lifetime kWh produced. Comparing LCOE to the customer's blended utility rate shows economic value.
- Residential clean energy credit
- A 30% federal credit on qualified residential solar installed cost, claimed on IRS Form 5695. Battery storage also qualifies when installed with the system.
- Commercial ITC basis
- The investment tax credit applies to eligible installed cost but excludes portions funded by non-taxable grants or rebates. The depreciable basis is reduced by half the credit.
- MACRS depreciation
- A five-year accelerated depreciation schedule for commercial solar, often paired with bonus depreciation. It lowers taxable income and improves commercial project returns.
- Net metering vs net billing
- Net metering credits exports at the retail rate. Net billing credits exports at a lower avoided-cost or export rate, reducing the value of overproduction.
- Incentive stacking order
- Apply grants and rebates first to reduce cost basis, then the federal tax credit, then state credits or SREC income. Confirm each program's rules against double-dipping.
- P50 versus P90 estimate
- P50 is the median expected annual production. P90 is the value exceeded with 90% confidence, used for conservative financial projections and production guarantees.
- Permit package contents
- Typically a site plan, single-line diagram, structural letter, module and inverter datasheets, and UL listings. Incomplete submittals are the most common cause of delay.
- Interconnection application
- A separate utility filing from the building permit that requests permission to parallel with the grid. Approval and any upgrade costs must be disclosed before contract signing.
- Contract essentials
- Scope, price and payment schedule, change-order process, timeline, warranty terms, cancellation rights, and clear assignment of who claims which incentive.
- Warranty stack
- Module product and power warranties, inverter warranty, rack warranty, workmanship warranty, and any production guarantee. Each has a different term and claimant process.
- Supply-side connection
- A PV interconnection made ahead of the main breaker on the service conductors. It avoids the busbar 120% limit but requires utility approval and a service disconnect.
- Arc-fault protection
- NEC 690.11 requires DC arc-fault circuit protection on PV circuits operating at 80 volts or more, detecting and interrupting series arcs on the array wiring.
- PV system labeling
- Placards at the DC disconnect, point of interconnection, rapid shutdown equipment, and service stating system voltage and current, required for inspector and firefighter safety.
- Performance ratio (PR)
- Actual energy yield divided by the theoretical yield at nameplate rating for the received irradiance. Well-designed systems typically run 0.75 to 0.85.
- IV curve tracing
- A field test that sweeps module or string voltage and current to reveal ground faults, failed bypass diodes, mismatch, and connector degradation without dismounting modules.