NASCLA Contractor flashcards
NASCLA Contractor · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Notice to Proceed
- The owner's written directive that starts the contract clock. Contract time is measured from this date, so owner-caused delays before it are usually not compensable.
- Constructability Review
- A preconstruction examination of drawings and specifications for conflicts, missing details, and infeasible sequencing that would otherwise produce field delays and change orders.
- Value Engineering
- A formal, owner-approved proposal to reduce cost by changing materials, methods, or systems without reducing the required function, quality, or performance of the project.
- Bid Bond
- A surety guarantee, usually 5 to 10 percent of the bid, that is forfeited if the low bidder fails to sign the contract and furnish the required bonds.
- Performance Bond
- A surety bond typically equal to 100 percent of the contract price that protects the owner if the contractor defaults and cannot complete the work.
- Addendum
- A written modification to the bidding documents issued before bid opening. Bidders must acknowledge each addendum in the proposal or the bid may be rejected.
- Labor Burden
- The cost above base wages for FICA, workers' compensation, unemployment insurance, and fringe benefits, commonly 25 to 40 percent of the base wage rate.
- Request for Information
- A formal written question from the contractor seeking clarification of the contract documents. The answer enters the project record and may trigger a change order.
- Construction Change Directive
- A written owner-architect order directing changed work before price and time are agreed; it is later converted into a change order with an agreed cost.
- Substantial Completion
- The stage when work is sufficiently complete for the owner's intended use. It starts warranty periods, releases most retainage, and shifts insurance and utility responsibility.
- Conditional Lien Waiver
- A waiver that becomes effective only after the stated payment actually clears the bank, protecting the payer from later lien claims for that amount.
- Critical Path
- The longest sequence of dependent activities through the schedule network. It has zero total float and determines the shortest possible project duration.
- Total Float
- The time an activity can slip without delaying project completion, calculated as late start minus early start or late finish minus early finish.
- Schedule Performance Index
- SPI equals earned value divided by planned value. A value below 1.0 means the project is behind schedule; above 1.0 means it is ahead.
- Time Impact Analysis
- A delay analysis method that inserts a fragment representing the changed work into the current accepted schedule to measure its effect on the completion date.
- Competent Person
- An individual able to identify existing and predictable hazards and authorized to take prompt corrective action; required for excavation, scaffold, and fall protection inspections.
- Excavation Protective System
- Required in trenches 5 feet deep or more. Sloping, shoring, or shielding must suit the soil type, with a ladder within 25 feet of lateral travel.
- Slump Test
- An ASTM C143 field test of concrete consistency in which a standard cone is filled, lifted, and the drop measured in inches to indicate workability.
- OSHA Focus Four Hazards
- Falls, struck-by, caught-in or between, and electrical hazards. They cause most construction fatalities and are the primary targets of OSHA construction inspections.
- Fall Protection Threshold
- OSHA requires fall protection at 6 feet in construction, 10 feet on scaffolds, and 15 feet in steel erection, using guardrails, nets, or personal arrest systems.
- Permit-Required Confined Space
- A space with limited entry, not meant for continuous occupancy, containing a hazardous atmosphere, engulfment, or entrapment hazard. Entry requires a permit and attendant.
- Recordable Injury
- Under 29 CFR 1904, a work-related death, days away, restricted work, medical treatment beyond first aid, or loss of consciousness that must be logged.
- Three-Phase Quality Control
- The USACE system using a preparatory meeting, an initial inspection of the first work, and recurring follow-up inspections for each definable feature of work.
- Hold Point
- A designated step in an inspection and test plan where the work cannot continue until the inspector or owner gives written approval.
- Occupant Load Calculation
- Floor area divided by the code occupant load factor, such as 150 gross for business or 15 net for unconcentrated assembly; it drives exits and egress width.
- Type I Construction
- The most fire-resistive IBC construction type, built of noncombustible structural members with 2 to 3 hour fire resistance and typical for high-rise buildings.
- Water-Cement Ratio
- The weight of water divided by the weight of cementitious material. Lower ratios increase strength and durability; structural concrete commonly runs 0.40 to 0.50.
- Type S Mortar
- A high-bond masonry mortar with a minimum 1800 psi compressive strength, used for structural walls, below-grade masonry, and where flexural strength is needed.
- A992 Steel
- The standard grade for structural W-shapes in the United States, with a minimum yield strength of 50 ksi plus improved weldability and toughness.
- Builder's Risk Insurance
- Property coverage on the structure during construction for fire, wind, theft, and vandalism; it typically excludes contractor tools, equipment, and employee vehicles.
- Mechanic's Lien
- A statutory claim recorded against real property by one who furnished labor or materials without payment; strict deadlines and preliminary notices apply.
- Underbilling
- A work-in-progress condition where costs and estimated earnings exceed billings to date; it is an asset representing cash not yet collected from the owner.