NASCLA Contractor study plan
NASCLA Contractor · Give each week a clear focus.
8 weeks · About 7 hours per week
Building Codes, Standards and Plan Reading
Read a full residential and a full light-commercial plan set from cover sheet to detail sheets and label every major view on a one-page index you create
Decode 30 common architectural, structural, and MEP symbols and abbreviations into a personal flashcard deck
Locate and cite 15 specific code sections covering egress, stairs, guards, and fire separation using the adopted code edition's index
Perform a linear measurement takeoff of walls, openings, and finishes from two plan sheets and reconcile the totals against the dimension strings
Your checkpoint
A one-page plan-reading index plus a 30-card symbol deck and a 15-citation code log, all scored at 80% or better on a self-quiz
Building Codes, Standards and Plan Reading & Bidding, Estimating and Contract Negotiation
Cross-check 10 plan details against code minimums for headroom, handrail height, riser/tread, and window egress and note each pass or fail
Build a complete material takeoff for one small project scope, including waste factors and unit conversions
Assemble a bid package that separates labor, material, equipment, subcontractor, overhead, and profit lines for that same scope
Identify and write out five common estimating errors and the check you would use to catch each one
Your checkpoint
A complete bid sheet for one practice scope with a written assumptions-and-exclusions page
Project Scheduling and Cost Control
Build a 40-activity critical path schedule for a small commercial build, including logic ties and a realistic weather allowance
Calculate float for every activity and mark the critical path on the printed network
Convert the schedule into a 12-period cost-loaded cash flow curve
Compute earned value for a worked example and interpret CPI and SPI in one written paragraph
Draft a two-week look-ahead schedule from the master schedule, including crew and material needs
Your checkpoint
A cost-loaded CPM schedule with a marked critical path, an S-curve, and a one-paragraph variance analysis
Project Planning and Pre-Construction & Contract Administration and Project Documentation
Sequence the pre-construction phase from site investigation through notice to proceed and list the approval or permit required at each step
Draft a submittal register covering 20 items with responsible party, required date, and review turnaround
Write a mock RFI and a mock change order that each contain every element needed for a defensible record
Identify the documentation required at a project meeting and produce a one-page minutes template
Map the contractual notice deadlines for delay, differing site conditions, and change directives into a single reference table
Your checkpoint
A pre-construction checklist package containing the permit sequence, a 20-item submittal register, and a notice-deadline table
Site Supervision and Field Operations & Quality Assurance and Quality Control
Write a daily site log template and complete three sample entries that capture crew counts, weather, deliveries, and delays
Draft a site logistics and staging plan for a constrained urban lot, showing access, laydown, and dumpster placement
Build a three-phase inspection and test plan naming the hold points and the acceptance criteria for each
Diagnose five common concrete, framing, and waterproofing defects and write the corrective action for each
Prepare a punch list of 15 realistic line items from a described walkthrough and rank them by severity
Your checkpoint
A field operations binder containing three completed daily logs, a site logistics sketch, and a hold-point inspection plan
Safety, Health and Environmental Compliance
Build a job hazard analysis for five high-risk tasks, listing hazards, controls in hierarchy order, and the responsible person for each control
Identify the required written safety programs, training, and recordkeeping for a 12-employee crew and note the retention period for each record
Select fall protection, excavation protective systems, and scaffold access controls for three described scenarios and state the trigger threshold that applies
Outline the steps for handling a silica, lead, or asbestos exposure concern, including who must be notified and within what timeframe
Write a site-specific emergency action plan covering evacuation, medical response, and severe weather
Your checkpoint
A site-specific safety plan with five completed JHAs and an emergency action plan section
Business Management, Law, Accounting and Risk & Materials, Methods and Construction Technology
Compare the rights and remedies of the main contract delivery methods and document the risk shift in each
Calculate retainage, progress payment, and a lien deadline scenario for three worked examples using the stated contract terms
Read a sample balance sheet and income statement and compute current ratio, gross margin, and working capital
Build a risk register with 12 identified risks, each scored for likelihood and impact with a mitigation owner
Match 15 materials or assemblies to their correct installation method and the standard or test that governs acceptance
Your checkpoint
A business-and-risk packet containing three solved payment/lien problems and a scored 12-line risk register
Project Planning and Pre-Construction & Bidding, Estimating and Contract Negotiation & Contract Administration and Project Documentation & Project Scheduling and Cost Control & Site Supervision and Field Operations & Safety, Health and Environmental Compliance & Quality Assurance and Quality Control & Building Codes, Standards and Plan Reading & Materials, Methods and Construction Technology & Business Management, Law, Accounting and Risk
Complete three full-length timed practice exams and log every missed item by domain
Re-study only the two lowest-scoring domains until the retest score clears 85%
Recite from memory the key numeric thresholds for egress, fall protection, excavation, and retainage
Review every flashcard, code citation, and reference table created in weeks 1 through 7 in two passes
Your checkpoint
A scored practice exam log across three attempts showing improvement, plus a one-page personal cheat sheet of numeric thresholds
Milestones
Week 2: Score 80% or higher on a 25-question self-made quiz drawn from your week 1 and week 2 deliverables
Week 4: Complete the first full-length timed practice exam and record a baseline score with a per-domain breakdown
Week 6: Complete the second full-length timed practice exam and score at least 5 percentage points above baseline
Week 8: Score 85% or higher on the final full-length practice exam with no single domain below 75%