NASCLA Contractor study materials
NASCLA Contractor study resources

NASCLA Contractor key terms

NASCLA Contractor · Get comfortable with the vocabulary.

Critical Path Method (CPM)

A scheduling technique that identifies the longest sequence of dependent activities in a project, thereby determining the minimum project duration and showing which activities cannot be delayed without delaying completion.

Related: Total Float, Schedule of Values
Total Float

The amount of time an activity can be delayed from its early start without delaying the project completion date; activities lying on the critical path have zero float.

Related: Critical Path Method (CPM)
Schedule of Values

An itemized breakdown of the contract sum allocated to individual work items, used to evaluate progress and calculate the amount of each monthly progress payment.

Related: Earned Value Management, Retainage
Earned Value Management

A cost-control method that compares the budgeted cost of work performed with actual costs and planned value to measure schedule and cost performance on a project.

Related: Schedule of Values, Critical Path Method (CPM)
Change Order

A written amendment to the construction contract that modifies scope, price, or schedule, and becomes binding once signed by the owner and accepted by the contractor.

Related: Request for Information (RFI), Substantial Completion
Request for Information (RFI)

A formal written question from the contractor to the design professional asking for clarification of the contract documents; the response becomes part of the project record.

Related: Submittal, Change Order
Submittal

Shop drawings, product data, samples, or similar documents the contractor provides to the designer for review and approval before fabricating or installing the related work.

Related: Request for Information (RFI), Mock-Up
Retainage

A percentage of each progress payment withheld by the owner until completion or specified milestones, giving the owner leverage to ensure final completion and correction of defects.

Related: Schedule of Values, Substantial Completion
Substantial Completion

The stage at which the work is sufficiently complete in accordance with the contract documents that the owner can occupy or use it for its intended purpose.

Related: Punch List, Retainage
Liquidated Damages

A pre-agreed amount charged to the contractor for each day of delay past the contract completion date, treated as an estimate of owner loss rather than a penalty.

Related: Substantial Completion, Change Order
As-Built Drawings

Marked-up drawings the contractor maintains during construction and delivers at closeout, showing actual dimensions, locations, and deviations from the original design documents.

Related: Daily Field Report, Submittal
Bid Bond

A bond guaranteeing that a bidder will enter into the contract and furnish required performance and payment bonds if awarded the work; forfeited if the bidder defaults.

Related: Performance Bond, Payment Bond
Performance Bond

A surety bond protecting the owner if the contractor fails to perform the contract, allowing the surety to complete the work or pay for its completion.

Related: Payment Bond, Surety
Payment Bond

A surety bond guaranteeing payment to subcontractors, laborers, and suppliers for work and materials furnished on the project, shielding the owner from mechanics liens.

Related: Lien, Performance Bond
Contingency

A reserve included in an estimate or budget to cover unforeseen costs, minor scope changes, or price escalation; it is not a markup or profit item.

Related: Guaranteed Maximum Price (GMP), Change Order
Guaranteed Maximum Price (GMP)

A contract arrangement that caps the amount the owner will pay; savings may be shared, and the contractor absorbs overruns not caused by owner-directed changes.

Related: Contingency, Construction Manager at Risk (CMAR)
Lump Sum Contract

An agreement in which the contractor performs a defined scope for a single fixed price, bearing the risk of quantity and cost variations within that scope.

Related: Unit Price Contract, Scope of Work
Unit Price Contract

An agreement that pays the contractor a fixed price for each unit of work actually performed, with the total contract value set by measured quantities.

Related: Lump Sum Contract, Change Order
Work Breakdown Structure

A hierarchical division of the project into manageable work packages used for estimating, scheduling, cost control, and assigning responsibility to specific parties.

Related: Schedule of Values, Critical Path Method (CPM)
Design-Build

A delivery method in which a single entity contracts with the owner for both design and construction, concentrating responsibility and often shortening the overall schedule.

Related: Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP)
Construction Manager at Risk (CMAR)

A delivery method in which a construction manager is engaged early for a fee to advise on design and cost, then holds a contract to build within a guaranteed maximum price.

Related: Guaranteed Maximum Price (GMP), Design-Build
Scope of Work

A written statement defining the work, materials, and deliverables included in a contract, and by implication the items that are excluded.

Related: Lump Sum Contract, Change Order
Job Safety Analysis

A procedure that breaks a task into steps, identifies hazards at each step, and defines controls before work starts, often documented as a pre-task briefing.

Related: Competent Person, Personal Protective Equipment (PPE)
Competent Person

An individual designated by the employer who can identify existing and predictable hazards in the surroundings and has authority to take prompt corrective action.

Related: Job Safety Analysis, Excavation Protective System
Personal Protective Equipment (PPE)

Items such as hard hats, safety glasses, gloves, and fall harnesses worn by workers to reduce exposure to hazards when other controls cannot fully eliminate them.

Related: Job Safety Analysis, Fall Protection
Hazard Communication Standard

The OSHA rule requiring chemical hazard evaluation, container labeling, safety data sheets, and worker training so employees understand the chemicals they handle.

Related: Personal Protective Equipment (PPE), Job Safety Analysis
Excavation Protective System

A method such as sloping, benching, shoring, or shielding used to protect workers in trenches from cave-ins, generally required for excavations five feet deep or more.

Related: Competent Person, Job Safety Analysis
Fall Protection

Systems and practices such as guardrails, safety nets, and personal fall arrest equipment used to protect workers from falls at elevations of six feet or more in construction.

Related: Personal Protective Equipment (PPE), Competent Person
Punch List

A list of incomplete or defective items identified near project completion that the contractor must correct before final acceptance and release of final payment.

Related: Substantial Completion, Quality Control Plan
Mock-Up

A full-size physical sample of a building component or assembly built on site to establish a quality standard and obtain approval before full-scale installation.

Related: Submittal, Quality Control Plan
Quality Control Plan

A project-specific document describing inspection procedures, testing requirements, acceptance criteria, and the parties responsible for verifying that work meets the specifications.

Related: Punch List, Mock-Up
Certificate of Occupancy

An official document issued by the local building authority confirming that a completed structure complies with applicable codes and is approved for its intended use.

Related: Occupancy Classification, Substantial Completion
Occupancy Classification

The category assigned to a building based on its intended use, such as business, mercantile, or residential, which drives allowable height, area, and fire protection requirements.

Related: Certificate of Occupancy, Fire-Resistance Rating
Fire-Resistance Rating

The period, usually stated in hours, that a building assembly resists a standardized fire exposure, used to satisfy code requirements for separations and structural protection.

Related: Occupancy Classification, Egress
Egress

The continuous path for leaving a building, comprising exit access, the exit itself, and exit discharge, sized and arranged so occupants can evacuate safely in an emergency.

Related: Occupancy Classification, Fire-Resistance Rating
Building Information Modeling (BIM)

A digital three-dimensional model of a building containing coordinated geometry and data used for design coordination, clash detection, quantity takeoff, and construction planning.

Related: Work Breakdown Structure, Submittal
Daily Field Report

A record kept by site supervision documenting weather, workforce, equipment, deliveries, visitors, and notable events each day, supporting progress tracking and later claims.

Related: As-Built Drawings, Request for Information (RFI)
Lien

A legal claim against real property filed by a party who furnished labor or materials and was not paid, potentially allowing the property to be sold to satisfy the debt.

Related: Payment Bond, Retainage
Surety

A company that issues bonds guaranteeing a contractor's performance or payment obligations, after evaluating the contractor's financial strength, experience, and capacity to complete work.

Related: Performance Bond, Bid Bond