NCCCO Rigger Level II study plan
NCCCO Rigger Level II · Give each week a clear focus.
8 weeks · About 7 hours per week
Site and Lift Planning
Calculate the weight of ten different loads from dimensions, material density tables, and manufacturer data, showing every step of the arithmetic
Survey a written site scenario and list at least fifteen hazards, ranking each by severity and stating a control for each
Compute required ground bearing pressure for five crane setups and match each to an outrigger pad or matting solution
Draft a complete written lift plan for a single-crane pick using a standard plan template, including rigging sketch and critical lift determination
Your checkpoint
A finished lift plan packet for one structural pick (load weight calc, hazard log, ground pressure calc, rigging sketch) submitted for self-review against a written checklist
Site and Lift Planning & Rigging Selection and Configuration
Read and interpret load charts for at least three crane configurations, locating capacity at a given radius, boom length, and quadrant
Calculate net allowable capacity for eight practice picks by deducting all applicable loads and attachments from gross capacity
Determine the load's center of gravity for five asymmetric loads and identify the resulting rigging point
Select sling type, size, and number of legs for five loads, checking each against rated capacity at the planned angle
Your checkpoint
A load chart worksheet of eight fully worked capacity calculations with a written statement of the governing limit for each
Rigging Selection and Configuration
Compute sling leg tension for ten two-, three-, and four-leg bridle configurations at angles from 30 to 60 degrees
Match hitches (vertical, choker, basket) to load types and apply the correct capacity reduction for each
Select below-the-hook hardware (shackles, hooks, master links, swivels, spreader beams) for six rigging assemblies and justify each choice
Identify and correct three rigging configurations that would induce load tipping, crushing, or edge damage
Your checkpoint
A rigging selection sheet for six assemblies showing sling tension math, hardware ratings, and the weakest-link capacity for each
Rigging Selection and Configuration & Inspection of Rigging Equipment
Differentiate the removal-from-service criteria for wire rope slings, synthetic slings, chain slings, and metal mesh slings
Perform a documented pre-use inspection on sample slings and hardware, recording each defect and pass/fail decision
Explain tag and identification requirements for slings and below-the-hook devices, and spot missing or illegible tags
Review inspection records and determine which items require periodic versus pre-use inspection intervals
Your checkpoint
A completed inspection log covering twenty sling and hardware items with defect notes and pass/fail dispositions
Inspection of Rigging Equipment
Classify fifteen rigging defects by type, cause, and severity, and state the correct disposition for each
Inspect shackles, hooks, and eyebolts for deformation, wear, and thread damage, and apply the correct rejection thresholds
Describe storage, care, and recordkeeping requirements that keep rigging equipment in service
Distinguish inspection responsibilities between the competent person and the rigger in the field
Your checkpoint
A scored practice quiz on Domain 3 with every missed item rewritten as a corrected rule statement
Execution of Complex Lifts
Plan a two-crane (tandem) lift, allocating load share between cranes and stating the maximum permitted wind and load drift limits
Sequence the steps of a load-upending or load-turning operation and identify the point where the load transfers
Write the pre-lift meeting agenda for a critical lift and assign responsibilities to each crew member
Identify control measures for blind lifts, load drift, and tag line use in restricted areas
Your checkpoint
A written execution plan for a multi-crane critical lift including load share percentages, step sequence, and abort criteria
Execution of Complex Lifts & Communication, Signaling, and Load Control
Direct three simulated lifts using standard hand signals, then verify each against the written signal chart
Deliver voice commands over radio using clear, standardized phrasing for stop, hold, swing, and boom motions
Assign and position signal persons and tag line operators for a lift with limited sight lines
Identify and correct ten communication failures in written lift scenarios
Your checkpoint
A demonstration checklist of twenty standard hand and radio signals performed and confirmed correct
Communication, Signaling, and Load Control & Site and Lift Planning & Execution of Complex Lifts
Sit a full-length timed practice exam covering all five domains and score each domain separately
Re-study the two lowest-scoring domains and rewrite every missed concept as a rule statement
Rehearse the load-control sequence (tag lines, swing control, landing, and load securing) from memory
Review lift planning fundamentals one final time, focusing on capacity, ground conditions, and hazard control
Your checkpoint
A full-length mock exam score report with a written remediation list and confirmation that the final score meets or exceeds the target
Milestones
Week 2: Eight load chart and net capacity calculations completed with correct governing limits identified on at least seven of eight
Week 4: Score 80% or higher on a 40-question timed quiz covering Domains 1 and 2, plus an inspection log with every item correctly dispositioned
Week 6: Multi-crane critical lift plan reviewed against a written checklist with all required elements present (load share, sequence, abort criteria, wind limits)
Week 7: All twenty hand and radio signals performed correctly with no more than one retry
Week 8: Full-length mock exam score of 85% or higher overall with no single domain below 75%