Inspection of Rigging Before Use

  • Inspect all rigging before each use and after any incident, shock load, or severe service; remove defective gear from service immediately.

  • Frequent inspection occurs before each shift or use; periodic inspection is performed at least annually and documented by a qualified person.

  • Wire rope sling removal criteria include 10 randomly distributed broken wires in one lay, 5 broken wires in one strand in one lay, kinking, bird-caging, crushing, or severe corrosion.

  • Chain sling removal criteria include cracks, nicks, gouges, weld spatter, stretch, or wear exceeding 10% of the original link diameter.

  • Synthetic web sling removal criteria include holes, cuts, tears, snags, severe abrasion, broken stitching, chemical discoloration, or a missing or illegible tag.

  • A sling with no legible identification tag showing capacity, length, and manufacturer is removed from service because its working load limit cannot be verified.

  • Hook removal criteria include a throat opening increased more than 15% or twist more than 10 degrees; a missing latch on a latch-equipped hook also removes it from service.

  • Shackle removal criteria include cracks, a bent or worn pin, damaged threads, or wear exceeding 10% of the pin or body dimension.

  • Never weld, heat, or modify rigging hardware; do not use homemade or unmarked components for overhead lifting.

Quick reference

Hitch Configurations, Capacities, and Basic Knots

  • Vertical hitch: one leg carries its full working load limit; multiple legs share load equally only when symmetrical and the center of gravity is centered.

  • Choker hitch capacity is typically 75% to 80% of the vertical rating, depending on sling type and manufacturer.

  • Basket hitch with two vertical legs: capacity is 2 x single-leg working load limit when balanced and both legs carry equal tension.

  • Sling tension per leg in a symmetric two-leg lift = load / (2 x sin theta), where theta is the angle each leg makes with horizontal.

  • At 60 degrees from horizontal each leg carries 0.577 x load; at 45 degrees each carries 0.707 x load; at 30 degrees each carries the full load.

  • An included angle of 90 degrees between legs equals 45 degrees from horizontal for each leg; larger included angles increase leg tension.

  • D/d ratio = diameter of curvature / sling diameter; small D/d reduces basket and choker capacity, and ratings commonly assume about 25:1.

  • Knotted slings are not permitted for overhead lifting; a knot can reduce rope strength by 50% or more.

  • Basic knots: bowline forms a fixed loop; clove hitch makes a quick attachable hitch; half hitch secures a line; timber hitch grips a log.

Quick reference

Recognition of Associated Hazards

  • Maintain OSHA minimum approach distance from energized power lines; the required distance increases with voltage, and de-energizing with lockout/tagout is the preferred control.

  • Keep the load center of gravity below the lifting point to prevent tipping, flipping, and shock loading.

  • Shock loading from jerking or sudden stops can exceed the static load several times; lifts must be smooth and controlled.

  • Sharp edges cut wire rope and synthetic slings; edge protectors or softeners are required, and slings must not be dragged over corners.

  • No personnel under a suspended load; barricade the drop zone and use tag lines to control rotation from a safe distance.

  • Side loading of hooks, shackles, and eyebolts reduces capacity and can cause bending or opening; load axially unless the component is rated otherwise.

  • Synthetic slings are damaged by heat, chemicals, and ultraviolet light; chain is attacked by acids; wire rope fails from corrosion and broken wires.

  • Ground condition affects stability: soft or sloping ground can let outriggers settle, so bearing capacity and mats must be evaluated.

  • Wind and weather increase load swing and effective load area; stop lifts when conditions exceed the lift plan or manufacturer limits.

Quick reference

Use of Rigging Equipment and Basic Hitches and Applications

  • Load hooks in the saddle, not the tip, and keep the latch closed; never tip-load a hook.

  • Fully seat shackle pins; orient the pin so the load cannot roll it loose, and never substitute a lower-strength bolt.

  • Shoulder eyebolts must be seated flush and loaded along the bolt axis; angular loading reduces capacity unless the eyebolt is rated for it.

  • Use a spreader beam to keep sling legs vertical on wide loads, avoiding compression on the load and sling-angle capacity loss.

  • Tag lines control swing and rotation from a safe distance and are never used to lift or to pull a load beyond the crane's rating.

  • Synthetic web slings suit polished or finished loads; chain suits abrasive, hot, or rough loads; wire rope suits heavy general service.

  • A two-leg bridle hitch capacity depends on the angle between legs and the center of gravity; unequal leg lengths cause load shift.

  • Equalizing slings or a spreader beam distribute load between lifting points; verify each point's capacity before lifting.

  • For a basket hitch around a load, both legs must be vertical and the load balanced; otherwise capacity is reduced by the sling angle.