NCCCO Rigger · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Inspection of rigging before use

  • List the tag, label, and identification data required on chain, wire rope, and synthetic web slings

  • Perform a documented pre-use inspection sequence on three sling types, front to back

  • State the removal-from-service criteria for cuts, broken wires, stretch, heat damage, and missing tags

  • Identify who is qualified to inspect rigging and when inspection must occur

Your checkpoint

A one-page pre-use inspection checklist covering chain, wire rope, and synthetic slings, scored 100% against the reference criteria

Week 2

Inspection of rigging before use & Hitch configurations, capacities, and basic knots

  • Inspect shackles, hooks, master links, swivels, and eyebolts for wear, throat opening, and distortion limits

  • Verify hook latch function and identify hook load-path defects

  • Explain how hardware ratings are marked and why unmarked hardware is rejected

  • Match each piece of hardware to a hitch type it can and cannot serve

Your checkpoint

Inspection log for 15 pieces of hardware with accept/reject calls and the reason for each rejection

Week 3

Hitch configurations, capacities, and basic knots

  • Differentiate vertical, choker, basket, and bridle hitches by load path and contact points

  • Apply the correct efficiency multiplier to compute capacity for each basic hitch

  • Calculate sling tension for a two-leg and four-leg bridle at a given included angle

  • Determine when edge protection, softeners, or a different hitch is required

Your checkpoint

A completed 20-problem hitch capacity and sling-tension worksheet with work shown, 85% or better

Week 4

Hitch configurations, capacities, and basic knots & Inspection of rigging before use

  • Tie and dress four field knots and state the strength loss for each

  • Recognize when a knot is prohibited in a rated sling assembly

  • Identify wear patterns that a hitch type creates on slings and hardware

  • Select the hitch configuration that minimizes sling-to-load contact damage

Your checkpoint

Live demonstration of four knots plus a written comparison of hitch types showing capacity, wear risk, and best-use case

Milestones

Week 4: Pass a closed-book 30-question quiz on Domains 1 and 2 at 80% or higher, with zero missed questions on removal-from-service criteria or hitch efficiency factors

Week 6: Complete a tabletop hazard walk-through of a described lift site and correctly name at least 8 of 10 planted hazards

Week 8: Score 85% or higher on a full-length 100-question timed practice exam spanning all four domains