NCCER Crew Leadership cheat sheet
NCCER Crew Leadership · Keep the key ideas within reach.
Crew Leadership and Field Supervision
Span of control: a first-line crew leader typically supervises 5–12 craft workers; beyond that, split the crew or add a lead worker.
Authority types: line authority flows down the chain of command; staff authority advises; the crew leader holds line authority over assigned craft.
Delegation rule: assign the task, grant the needed authority, set the deadline, and confirm the worker has the skill and tools before release.
Progressive discipline sequence: verbal coaching, written warning, suspension, termination; document each step with date, behavior, and corrective action.
Maslow order for motivation: physiological, safety, social, esteem, self-actualization; safety needs dominate on a jobsite and must be met first.
Situational leadership: directing (low skill, low will), coaching (low skill, high will), supporting (high skill, low will), delegating (high skill, high will).
Constructive feedback formula: describe the observed behavior, state its impact, agree on the specific change, and set a follow-up date.
Grievance handling: hear the complaint, verify facts against the contract or policy, respond within the time limit in the agreement, and record the outcome.
Jobsite Safety and Risk Mitigation
Hierarchy of controls, most to least effective: elimination, substitution, engineering controls, administrative controls, PPE.
Incident rate formula: (number of recordable cases × 200,000) ÷ total hours worked; 200,000 equals 100 workers × 40 hours × 50 weeks.
Fall protection trigger for general construction: 6 ft; scaffolds 10 ft; ladders 24 ft; steel erection 15 ft (per OSHA 1926 subparts).
Competent person: capable of identifying existing and predictable hazards and authorized to take prompt corrective action to eliminate them.
Excavation rules: spoil and equipment at least 2 ft from the edge; a competent person inspects daily and after rain; trench access within 25 ft of lateral travel.
Hazard communication: every container labeled, safety data sheet on site for each hazardous chemical, and worker training before exposure.
Lockout/tagout: isolate the energy source, apply the lock and tag, verify zero energy, and only the person who applied the lock removes it.
Permit-required confined space: test atmosphere before entry and continuously, attendant outside at all times, rescue plan in place before entry.
Near-miss reporting is leading-indicator data; track and investigate near misses before they become recordable injuries.
Jobsite Operations and Planning
Look-ahead schedule: a 3-week rolling plan; week 1 is committed, weeks 2–3 are planned; update weekly to expose constraints early.
Constraint removal: identify material, labor, equipment, and information constraints during the look-ahead and assign an owner and due date for each.
Critical path: the longest duration path through the network; any delay on it delays project completion; float equals late start minus early start.
Percent complete by cost: earned value ÷ budget at completion; earned value = percent complete × budget.
Crew balance: match crew size to the limiting resource (equipment, space, or material delivery); adding workers past that point adds no output.
Material staging rule: stage only what the next work period consumes; excess on site increases handling, damage, and housekeeping cost.
Daily report content: date, weather, crew and hours, work performed by location, equipment on site, deliveries, visitors, delays, and safety events.
Change order flow: written request, cost and schedule impact priced, owner approval, then work proceeds; no verbal direction authorizes extra work.
Quality control: first-work inspection, then periodic checks; hold points require sign-off before the next trade covers the work.
Communication, Documentation, and Client Satisfaction
Communication model: sender encodes, message travels a channel, receiver decodes, feedback confirms; noise in any stage causes distortion.
Documentation rule: if it is not written down, it did not happen; record verbal directions in a confirming memo the same day.
RFI content: drawing or spec reference, the question stated precisely, proposed solution, and schedule impact; log and track the response date.
Meeting minutes: date, attendees, decisions made, action items with owner and due date; distribute within 24–48 hours.
Client satisfaction drivers: on-time completion, cleanliness, minimal disruption to ongoing operations, responsiveness to concerns, and punch-list closure.
Punch list: walk with the owner, list deficiencies by location, assign a responsible trade and date, and re-inspect before sign-off.
Conflict resolution: separate the people from the problem, focus on interests not positions, generate options, and agree on objective criteria.
Three-part message for direction: what is to be done, by whom and when, and how completion will be verified.