NE Fire Sprinkler · Give each week a clear focus.
8 weeks · About 6 hours per week
Water-Based Fire Protection
List the components of a wet-pipe, dry-pipe, preaction, and deluge system and state the activation sequence for each from memory
Identify the applicable NFPA 13 occupancy hazard classifications (light, ordinary group 1 and 2, extra hazard group 1 and 2) and assign three building examples to each
Define the key hydraulic terms (flow, pressure, density, discharge coefficient, K-factor, friction loss) and write the formula relating discharge to pressure and K-factor
Map the exam's single content domain into a personal topic checklist covering design, installation, hydraulics, inspection, and ITM
Your checkpoint
A one-page system-type comparison table (activation logic, piping, when used) plus a 20-item self-quiz scored and logged with missed topics flagged
Water-Based Fire Protection
Calculate required flow from design density times design area for at least five practice scenarios
Trace a simple tree and gridded layout and explain how remote-area selection and hydraulic balance differ between them
Compute friction loss through schedule 40 steel pipe using the Hazen-Williams form and verify units on each step
Explain how K-factor, minimum operating pressure, and sprinkler spacing interact to set the minimum end-head pressure
Your checkpoint
A worked hydraulic calculation packet for five scenarios showing density, area, flow, per-head pressure, and total demand with units on every line
Water-Based Fire Protection
Size a water supply by converting a static and residual flow test into an available-pressure-versus-flow curve
Determine the margin between supply and demand at the base of the riser and at the most remote head
Select sprinkler temperature ratings and response types (quick, standard, special) for given occupancy and ceiling conditions
Identify obstruction rules that require additional sprinklers or shielding, and describe the spacing rule for each case
Your checkpoint
A water supply analysis sheet plotting supply curve against demand point, stating the safety margin and pass/fail conclusion
Water-Based Fire Protection
Explain the purpose and required components of a fire department connection, main drain, and flow test valve
Describe the acceptance test sequence for a new system: hydrostatic, flow, main drain, alarm, and trip tests for dry and preaction systems
State the inspection, testing, and maintenance frequencies for gauges, alarm devices, valves, and waterflow switches
Differentiate between impairment procedures, hot work controls, and the conditions that require a fire watch
Your checkpoint
A completed acceptance-test checklist and a separate ITM frequency table covering at least 12 devices with the correct interval for each
Milestones
Week 2: Score at least 80 percent on a closed-book 25-question set on system types and hydraulic fundamentals; rework every missed item
Week 4: Produce the full water supply analysis and acceptance-test checklist with no unresolved unit or formula errors, and explain each step aloud in under 10 minutes