Public Bid Withdrawal After a Missed HVAC Addendum

NE General Contractor · Put your knowledge to work in context.

All case studies

Public Bid Withdrawal After a Missed HVAC Addendum

Prairie Ridge Builders is bidding a $6.2 million public school addition in Kearney. Bids are due Tuesday at 2:00 p.m. On Sunday at 8:00 a.m., the architect issues Addendum 3 changing the rooftop HVAC units from 40-ton to 50-ton and adding a 12-inch curb. Prairie Ridge's estimator is on vacation; the bid is submitted without acknowledging Addendum 3. The bid is $180,000 below the second bidder. The owner's bid form requires acknowledgment of all addenda and a 5% bid bond. Prairie Ridge's bid includes an alternate for a gym floor at $95,000 and a unit price of $1,200 per door. On Wednesday, the owner asks Prairie Ridge to honor its bid; the estimator discovers the missed addendum would add $145,000. The bid bond is $310,000.

1. Can Prairie Ridge withdraw its bid without forfeiting the bid bond? Show the financial and legal reasoning.

Read the worked answer

The first step is immediate written notice to the owner before award or acceptance. A bid mistake can support withdrawal only if it is a material, clerical error that the owner knew or should have known, and if the bidder acts promptly; a judgment error in pricing is harder. Here the missed addendum is documented and changes scope, so it is a strong clerical/omission argument. Financially, honoring the bid means absorbing about $145,000. Withdrawing risks the 5% bond, $310,000, but the owner's actual damages may be the difference between the low bid and the next bid, about $180,000, not the full bond. The owner may also reject the bid as nonresponsive for failing to acknowledge Addendum 3. Prairie Ridge should not submit a revised bid after opening unless the owner requests it. It should compare: negotiate a mutual mistake rescission, honor with a documented cost claim if the owner wants to proceed, or accept bond forfeiture only after legal review. The best immediate move is a written reservation of rights and a request for relief, not silence.

2. What should the estimator do about the alternate and unit prices, and how should the company prevent recurrence?

Read the worked answer

The alternate and unit prices are part of the bid and can be used by the owner to adjust scope; they should not be used to mask the addendum error. If the owner accepts the base bid, Prairie Ridge must perform the addendum scope unless it obtains a written change order. The estimator should rebuild the estimate from the addendum, confirm the HVAC curb and structural implications, and issue a written notice of the discrepancy. For prevention, the company should use an addendum log, require acknowledgment on the bid form, assign a backup estimator during vacation, and set a bid-closing checklist with a second reviewer. The bid bond amount should be verified against the owner's form. The unit price of $1,200 per door should be checked against actual cost; if it is unbalanced, it can create risk if quantities change. The lesson is that bid day controls and addendum tracking are not clerical details; they are risk allocation.