NE General Contractor study materials
NE General Contractor study resources

NE General Contractor flashcards

NE General Contractor · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Nebraska contractor registration threshold
Nebraska requires contractor registration for projects over $5,000 in labor and materials. Unregistered contractors cannot enforce contracts and face penalties from the Department of Labor.
Nebraska mechanics' lien filing period
A contractor must file a mechanics' lien within 120 days after last furnishing labor or materials. Subcontractors must give the owner preliminary notice within 10 days of first furnishing.
Nebraska statute of repose
Neb. Rev. Stat. § 25-223 bars construction defect claims more than five years after substantial completion of an improvement to real property, regardless of discovery date.
Nebraska Prompt Payment Act
Public owners in Nebraska must pay a proper invoice within 30 days. Retainage on public projects must be released within 30 days of final acceptance of the work.
Total float formula
Total float equals late start minus early start, or late finish minus early finish. An activity with zero total float lies on the critical path and delays completion if slipped.
Change order vs. CCD
A construction change directive orders work before price is agreed; a change order is a signed agreement covering scope, price, and time. CCDs are later converted to change orders.
Bid bond percentage
A bid bond is typically 5 to 10 percent of the bid amount. It guarantees the contractor will enter the contract if awarded; failure forfeits the bond to the owner.
Substantial completion effect
Substantial completion starts warranty periods, triggers retainage release provisions, and allows owner occupancy. Only punch list items and minor work remain incomplete at that point.
Specification MasterFormat divisions
CSI MasterFormat organizes specifications into 50 divisions. Division 01 is General Requirements, Division 03 Concrete, Division 05 Metals, and Division 09 Finishes.
Concrete volume formula
Cubic yards equal length times width times depth in feet, divided by 27. Add 5 to 10 percent for spillage and uneven subgrade when ordering ready-mix.
Drawing scale conversion
At 1/4 inch equals 1 foot, one inch on the drawing represents 4 feet. At 1/8 inch equals 1 foot, one inch represents 8 feet.
Estimate contingency percentages
Design contingency runs 5 to 10 percent during design; construction contingency runs 3 to 5 percent during construction. Add escalation separately for long-duration projects.
OSHA fall protection height
OSHA 29 CFR 1926.501 requires fall protection at 6 feet in construction. Guardrails, safety nets, or personal fall arrest systems are acceptable means of protection.
Excavation protective system threshold
Protective systems are required for excavations 5 feet deep or more. Spoil piles and equipment must be kept at least 2 feet back from the excavation edge.
Ladder 4:1 rule
Ladders must be set at a 4:1 angle: 1 foot out for every 4 feet of height. They must extend 3 feet above the landing for roof access.
Scaffold rail dimensions
Scaffold top rails are 38 to 45 inches high, midrails about 21 inches, and toe boards 3.5 inches. Scaffolds must support four times the intended load.
Water-cement ratio effect
Lower water-cement ratios increase concrete strength and reduce permeability. Typical structural concrete uses 0.45 to 0.50; higher ratios weaken the mix.
Standard vs. Modified Proctor
ASTM D698 Standard Proctor uses lower compaction energy than ASTM D1557 Modified Proctor. Modified yields higher maximum dry density and is often the field specification.
Rebar size identification
Rebar is numbered in eighths of an inch: #4 is 1/2 inch, #5 is 5/8 inch, and #8 is 1 inch in diameter. Cover and development length follow ACI 318.
Concrete slump test
ASTM C143 slump test measures workability of fresh concrete. A standard slump cone is filled in three lifts, rodded 25 times each, then the drop is measured.
CMU nominal dimensions
A standard concrete masonry unit is nominally 8 by 8 by 16 inches; actual dimensions are 7-5/8 by 7-5/8 by 15-5/8. Mortar joints are 3/8 inch.
Mortar type selection
Type M is highest strength for below grade; Type S is moderate-high for exterior load-bearing; Type N is general purpose above grade; Type O is low strength for interior non-load-bearing.
Nominal vs. actual lumber
A nominal 2x4 measures 1.5 by 3.5 inches; a 2x6 measures 1.5 by 5.5; a 2x10 measures 1.5 by 9.25. Framing spacing is typically 16 or 24 inches on center.
Collar tie placement
Collar ties are installed in the upper third of the rafter span to resist separation. They are not a substitute for ceiling joists, which resist outward wall thrust.
Roof slope categories
Low-slope roofs are 2:12 or less; steep-slope roofs exceed 4:12. Underlayment and flashing requirements vary by slope and roofing product.
Ice dam membrane location
An ice dam membrane is installed at the eaves, extending at least 24 inches inside the exterior wall line, to prevent water backup in cold climates.
Vapor retarder placement
Vapor retarders go on the warm side of insulation in cold climates to prevent condensation inside the assembly. In hot-humid climates placement may reverse.
Insulation R-value per inch
Polyiso foam is about R-6 per inch, XPS about R-5, EPS about R-4, fiberglass batt about R-3.1, and spray polyurethane about R-6 to R-7.
HVAC tonnage definition
One ton of cooling equals 12,000 BTU per hour. A rough sizing guideline is 1 ton per 400 to 600 square feet depending on climate and envelope.
GFCI and AFCI requirements
GFCI protection is required in bathrooms, kitchens, outdoors, garages, and within 6 feet of sinks. AFCI protection is required in bedrooms and living areas per NEC.
Drain pipe slope
Drain pipe slopes 1/4 inch per foot for 2-inch and smaller pipe, and 1/8 inch per foot for 3-inch and larger. Vent stacks must extend above the roof.
Drywall finishing levels
Level 4 drywall finish is standard for painted surfaces; Level 5 adds a skim coat for critical lighting conditions. Levels 1 through 3 are for less visible areas.