- Limited approach boundary
- The distance from an exposed live part within which an unqualified person must not enter unless escorted, and a qualified person must use shock protection.
- Arc flash boundary
- The distance at which a person without arc-rated protection could receive a second-degree burn, defined as incident energy of 1.2 calories per square centimeter.
- Let-go threshold
- The current level at which a person can no longer release a conductor, typically around 10 to 20 milliamperes for AC at power frequency.
- CAT III rating
- A measurement category for test instruments used on distribution circuits and fixed installations, indicating transient withstand beyond that of CAT II.
- Four-wire Kelvin measurement
- A resistance measurement using separate current and potential leads, eliminating lead and contact resistance so that low winding resistances can be read accurately.
- Burden voltage
- The voltage drop across a multimeter's internal shunt when measuring current in series, which can disturb the circuit being tested.
- Polarization index
- Insulation resistance at ten minutes divided by insulation resistance at one minute; values above 2.0 are generally acceptable for Class B insulation and above.
- Dielectric absorption ratio
- Insulation resistance at sixty seconds divided by the value at thirty seconds; a result below 1.25 suggests moisture or contamination in the insulation.
- Guard terminal
- A meter connection that diverts surface leakage current around the measurement circuit, allowing true bulk insulation resistance to be read on contaminated surfaces.
- Temperature correction of IR
- Insulation resistance falls as temperature rises, roughly halving for each ten degrees Celsius, so readings must be corrected to a common base before comparison.
- Micro-ohmmeter contact test
- A four-wire low-resistance measurement across closed breaker contacts, compared with the manufacturer limit or the previous baseline rather than a universal value.
- Trip unit pickup test
- A test that slowly raises injected current until the overcurrent element operates, confirming the pickup point is within tolerance of the setting.
- Pole discrepancy
- The maximum difference in opening or closing time among the poles of a high-voltage breaker, commonly limited to about five milliseconds.
- SF6 dew point check
- A measurement of moisture in sulfur hexafluoride gas; excessive moisture lowers dielectric strength and can form corrosive byproducts during arcing.
- Open CT hazard
- An open secondary on an energized current transformer develops a very high voltage that can destroy insulation and injure personnel, so the secondary must never be opened under load.
- CT polarity marks
- Primary terminals P1 and P2 and secondary terminals S1 and S2 define instantaneous current direction, which differential and directional relays depend on.
- VT short-circuit hazard
- A shorted voltage transformer secondary draws high current and can destroy the winding, so the secondary must never be short-circuited.
- Relay secondary injection
- A test that applies currents and voltages to the relay secondary terminals; the primary equivalent is the injected value multiplied by the instrument transformer ratio.
- Turns ratio test
- A comparison of measured transformer ratio to nameplate ratio; a deviation beyond about half a percent indicates a shorted turn or tap problem.
- Winding resistance imbalance
- A phase-to-phase difference in transformer winding resistance, commonly limited to two percent, indicating a loose connection or broken strand.
- Copper temperature coefficient
- Copper resistance rises about 0.4 percent per degree Celsius, so winding resistance readings are corrected to a reference temperature such as 75 degrees Celsius.
- Transformer IR test setup
- Insulation resistance is measured with the core grounded, testing each winding to ground and between windings, using a DC voltage selected for the winding rating.
- Fall-of-potential method
- A ground resistance test placing a current probe and a potential probe; the potential probe is set at about 62 percent of the current probe distance.
- 62 percent rule
- For a three-point ground test, the potential probe is placed at 62 percent of the distance to the current probe, with readings checked by moving it ten percent.
- Equipment grounding conductor
- A conductor that provides a low-impedance fault current path so overcurrent protection operates; it carries no current under normal conditions.
- GFCI trip level
- A ground-fault circuit interrupter trips at about four to six milliamperes, protecting people rather than equipment, and does not replace equipment grounding.
- Time-domain reflectometry
- A cable fault locating method that sends a pulse and measures reflection time; distance equals propagation velocity times time divided by two.
- Murray loop test
- A bridge method for locating cable faults by balancing the faulted conductor against a known good conductor to determine the distance to the fault.
- Motor winding balance
- A comparison of resistance among motor phases; a difference beyond about five percent suggests a turn-to-turn fault or a poor connection.
- Motor IR test voltage
- The DC test voltage for motor insulation resistance is selected from the motor's rated voltage, not its horsepower, and the windings must be discharged first.
- Test record content
- A valid record lists date, ambient temperature and humidity, instrument model and calibration date, test voltage, measured value, and the acceptance limit applied.
- Calibration traceability
- Instrument calibration must trace to a national standard; an out-of-calibration instrument invalidates acceptance test results and requires retesting.