NETA ETT Level 1 · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Low-Voltage and High-Voltage Circuit Breaker Testing & Protective Relays and Instrument Transformers

  • Map each circuit breaker test type (contact resistance, timing, travel, minimum pickup, trip unit verification) to the specific fault or degradation mode it is meant to detect, and state the acceptance criterion you would apply for each.

  • Build a one-page comparison of low-voltage versus high-voltage breaker test setups, listing required isolation steps, test instrument connections, and safety boundaries for each.

  • Explain the operating principle of current and voltage instrument transformers, including polarity marks, ratio, burden, and what happens to a CT secondary when it is open-circuited under load.

  • Trace a simple overcurrent protection scheme from CT secondary through relay input to breaker trip coil, naming each element and the failure mode that would prevent a trip.

  • Write out the relay test sequence for a time-overcurrent element: pickup verification, time-curve points at two multiples of pickup, and target/flag check.

Your checkpoint

A two-page breaker-and-relay test matrix listing at least 10 tests, the instrument used, the pass criterion, and the hazard control for each.

Week 2

Low-Voltage and High-Voltage Circuit Breaker Testing & Protective Relays and Instrument Transformers

  • Calculate pickup and time-dial settings for a time-overcurrent relay given a CT ratio, load current, and desired coordination margin, and show the arithmetic.

  • Describe how to verify CT ratio and polarity by primary injection or by secondary voltage injection, and state which method you would choose in an energized versus de-energized switchyard.

  • List the checks performed on a trip circuit (trip coil resistance, trip-circuit supervision, DC supply verification) and explain how each catches a latent failure.

  • Practice interpreting a timing test result where the breaker opens slower than nameplate, and list at least four candidate causes ranked by likelihood.

Your checkpoint

A worked relay-setting and CT-ratio calculation set with three complete problems and answers.

Week 3

Transformers: Ratio, Winding Resistance, and Insulation Testing & Insulation Resistance and Polarization Index Testing

  • Explain turns-ratio testing on a two-winding transformer, including expected ratio versus nameplate tolerance and how tap position changes the expected value.

  • Describe the winding resistance test method (test current selection, stabilization, temperature correction) and explain why low-voltage high-current measurement is preferred on large windings.

  • Distinguish insulation resistance from polarization index, state the test voltages used for different winding voltage classes, and explain what a falling PI indicates about moisture or contamination.

  • Identify the safety controls for transformer testing: discharge and ground after IR tests, guarding of high-voltage leads, and lockout of the tap changer.

  • Interpret a set of IR readings taken at 1 minute, 10 minutes, and after temperature correction, and decide whether the unit is acceptable for service.

Your checkpoint

A completed transformer test report template with ratio, winding resistance, IR, and PI sections, each with a worked example value and pass/fail judgment.

Week 4

Electrical Safety and Hazard Awareness & Test Equipment Selection, Use, and Care

  • Apply the hierarchy of hazard controls to a live-testing scenario and justify why PPE is the last line of defense rather than the primary control.

  • Define approach boundaries, arc-flash boundary, and incident energy in your own words, and explain how a label's values drive the choice of PPE category.

  • Select the correct instrument category rating (CAT III versus CAT IV) for measurements at service entrance, panelboard, and branch circuit, and justify each choice.

  • Describe the pre-use inspection of a multimeter, insulation tester, and clamp meter, including lead condition, fuse check, and proving the instrument on a known source before and after use.

  • Explain how a non-contact voltage tester can mislead and what confirming measurement you would take before touching a conductor.

Your checkpoint

A personal pre-job safety checklist covering hazard assessment, boundary determination, instrument category check, and live-dead-live verification.

Week 5

Grounding, Bonding, and Ground-Fault Protection & Cables, Switches, and Motor Circuit Testing

  • Explain the difference between grounding, bonding, and equipment grounding conductors, and describe the fault-current path that opens the overcurrent device in a grounded versus ungrounded system.

  • Describe the fall-of-potential method for earth resistivity and ground electrode resistance testing, including probe spacing and why the measurement is invalid if the potential probe is too close to the electrode.

  • Outline the tests performed on a motor circuit: insulation resistance to ground, winding resistance balance, rotation check, and no-load current comparison, and state what each result rules out.

  • Describe continuity and contact-resistance testing of switches and disconnects, and explain how a contact resistance reading that drifts under load indicates a developing failure.

  • Explain how a ground-fault protection scheme detects current that returns outside the intended path, and name the two common sensing arrangements.

Your checkpoint

A grounding and motor-circuit test procedure covering at least three tests, with instrument, connection diagram described in words, and acceptance criteria.

Week 6

Insulation Resistance and Polarization Index Testing & Transformers: Ratio, Winding Resistance, and Insulation Testing & Cables, Switches, and Motor Circuit Testing

  • Perform insulation resistance tests on a cable, a motor winding, and a transformer winding, and explain how test voltage and duration are chosen differently for each.

  • Describe the step-voltage test and the ramp test, and state what a decreasing resistance with increasing voltage suggests about insulation condition.

  • Explain how temperature, humidity, and surface leakage distort IR readings, and describe the guard-terminal technique for suppressing surface current.

  • Compare winding resistance measurements across all three phases of a transformer and decide whether a phase imbalance is acceptable based on percent deviation.

  • Document a cable insulation test result and write the pass/fail conclusion with reference to a recognized standard, without overstating what the standard requires.

Your checkpoint

Three completed insulation test records (cable, motor, transformer) with readings, temperature correction shown, and a written conclusion for each.

Week 7

Electrical Safety and Hazard Awareness & Test Equipment Selection, Use, and Care & Test Records, Reporting, and Standards Interpretation

  • Write a test report section that states the standard applied, the test method, the measured values, the acceptance criterion, and the conclusion, keeping fact separate from interpretation.

  • Identify the elements a defensible test record must contain: date, ambient conditions, instrument model and calibration status, circuit identification, and technician identity.

  • Explain how to handle a result that falls marginally outside criteria, including retest, investigation, and escalation rather than silent acceptance.

  • Describe how to read a standards clause and apply it to a specific test, distinguishing a mandatory requirement from an informational note.

  • Review a sample test record for deficiencies and list at least five corrections.

Your checkpoint

A full sample test report for one breaker or transformer, reviewed against a self-made quality checklist of at least 10 items.

Week 8

Low-Voltage and High-Voltage Circuit Breaker Testing & Protective Relays and Instrument Transformers & Insulation Resistance and Polarization Index Testing & Transformers: Ratio, Winding Resistance, and Insulation Testing

  • Complete a timed mixed-domain practice set weighted to the exam blueprint, and score each domain separately to find weak areas.

  • Re-derive from memory the key formulas: PI, temperature correction for winding resistance, CT ratio and burden, and relay pickup from tap and CT ratio.

  • Re-teach the two weakest domains in writing, explaining each concept as if to a new technician, and check the explanation against your references.

  • Review every missed practice question and record the underlying concept gap rather than the question wording.

Your checkpoint

A scored practice exam summary with per-domain percentages and a one-page list of the five concepts you will review again before test day.

Milestones

Week 2: Can solve a relay pickup and time-dial problem and explain CT polarity without notes.

Week 4: Can assign an instrument category rating and state the correct approach boundary for a given work location.

Week 6: Can run and interpret IR, PI, ratio, and winding resistance tests and state pass/fail with justification.

Week 8: Scores at least 80 percent overall on the mixed practice set with no domain below 70 percent.