NFPA CFPE study materials
NFPA CFPE study resources

NFPA CFPE practice questions

One question at a time. Build your NFPA CFPE understanding.

First 50 of 200 questions. Each one lists the choices, the correct answer, and an explanation. The checker at the top of this page saves progress in this browser when it is available.

Continue in the practice tool above to load more questions, 50 at a time.

Question 1Plan Review Fundamentals and Code Administration

Which entity has the authority to review and approve fire protection construction documents for compliance with the adopted fire code?

  1. The installing contractor
  2. The authority having jurisdiction Correct answer.
  3. The building owner
  4. The product manufacturer

Explanation

The authority having jurisdiction administers and enforces the adopted fire code, including reviewing construction documents and issuing permits. Designers and contractors prepare and submit plans, but they do not approve their own work.

Question 2Plan Review Fundamentals and Code Administration

Which NFPA document is the model fire code that consolidates fire prevention and protection requirements?

  1. NFPA 1 Correct answer.
  2. NFPA 72
  3. NFPA 13
  4. NFPA 101

Explanation

NFPA 1 is the Fire Code, which consolidates fire prevention and protection requirements. NFPA 101 addresses life safety, NFPA 13 addresses sprinkler systems, and NFPA 72 addresses alarm and signaling systems.

Question 3Plan Review Fundamentals and Code Administration

When a statute requires construction documents to be prepared by a licensed design professional, who must seal them before submittal?

  1. The general contractor
  2. The licensed design professional responsible for the design Correct answer.
  3. The property insurer
  4. The fire code official

Explanation

Where the law requires a licensed design professional, the documents must be prepared and sealed by that professional before code review. Contractors and officials do not seal design documents they did not prepare.

Question 4Plan Review Fundamentals and Code Administration

A permit for a fire sprinkler installation is typically required before which activity?

  1. Submitting a bid
  2. Ordering materials
  3. Beginning installation work Correct answer.
  4. Scheduling the final inspection

Explanation

A permit must be issued before regulated installation work begins. Work performed before permit issuance is subject to stop-work orders and may require removal or additional inspection.

Question 5Plan Review Fundamentals and Code Administration

Which item is normally part of a fire sprinkler plan submittal for code review?

  1. Building tenant lease
  2. Hydraulic calculations Correct answer.
  3. Contractor payroll records
  4. Material purchase orders

Explanation

Hydraulic calculations demonstrate that the proposed piping and water supply can deliver the required density and pressure. Purchase orders, payroll records, and leases are not technical design documents used for code compliance review.

Question 6Plan Review Fundamentals and Code Administration

A certificate of occupancy is issued after which condition is met?

  1. The contractor requests a bid
  2. Required final inspections and tests are completed and approved Correct answer.
  3. The permit application is received
  4. The design drawings are sealed

Explanation

A certificate of occupancy confirms that required inspections and tests have been completed and approved. Receiving an application, bidding, or sealing drawings does not establish that the building complies.

Question 7Plan Review Fundamentals and Code Administration

NFPA 101 is best described as which type of document?

  1. The model fire code for fire prevention
  2. The standard for sprinkler installation
  3. The Life Safety Code addressing means of egress and occupancy Correct answer.
  4. The standard for fire alarm signaling

Explanation

NFPA 101 is the Life Safety Code and addresses means of egress, occupancy features, and protection from fire and similar emergencies. NFPA 13 covers sprinklers, NFPA 72 covers alarm signaling, and NFPA 1 is the Fire Code.

Question 8Plan Review Fundamentals and Code Administration

A deferred submittal is best described as which of the following?

  1. Design details submitted for review after the main permit Correct answer.
  2. A plan review performed after occupancy
  3. A drawing revision issued during construction
  4. A request to waive plan review

Explanation

A deferred submittal allows specified design details to be reviewed after the main permit is issued, but before that portion of the work is installed. It does not waive review or authorize occupancy before compliance.

Question 9Plan Review Fundamentals and Code Administration

When two adopted code provisions conflict and neither specifically states which governs, what should the reviewer apply?

  1. The provision in the older code edition
  2. The provision preferred by the contractor
  3. The more restrictive provision Correct answer.
  4. The less restrictive provision

Explanation

In the absence of a specific precedence provision, the more restrictive requirement is generally applied to maintain the intended level of safety. The less restrictive provision may fail to satisfy the other adopted requirement.

Question 10Plan Review Fundamentals and Code Administration

An applicant proposes a design that does not meet a prescriptive code requirement but provides equivalent safety. What is the appropriate administrative path?

  1. Submit a deferred submittal
  2. Ignore the requirement
  3. Request approval of an alternate method or equivalency from the authority having jurisdiction Correct answer.
  4. Apply for a certificate of occupancy

Explanation

The code official may approve an alternate method or equivalency when the applicant demonstrates equivalent performance and safety. A deferred submittal addresses timing of design details, not substitution for a prescriptive requirement.

Question 11Plan Review Fundamentals and Code Administration

Needed fire flow for a building is primarily based on which set of factors?

  1. The insurance company's premium
  2. The number of parking spaces
  3. The contractor's schedule
  4. Occupancy, construction, exposure, and building size Correct answer.

Explanation

Needed fire flow reflects the fire demand of the building and considers factors such as occupancy hazard, construction type, exposure, and size. The available water supply must be compared with that demand during review.

Question 12Plan Review Fundamentals and Code Administration

When an existing building is altered, the new work generally must meet which requirement?

  1. Comply only if the owner volunteers to upgrade
  2. Meet only the code in effect at original construction
  3. Be exempt from plan review and permits
  4. Comply with current code for the new work Correct answer.

Explanation

Alterations generally must comply with current code requirements for the new work, and the alteration must not reduce existing life safety. Existing building provisions may permit limited alternatives, but they do not create a blanket exemption.

Question 13Plan Review Fundamentals and Code Administration

When must the authority having jurisdiction be given the opportunity to inspect fire-resistive construction or piping before it is covered?

  1. After the ceiling is installed
  2. Only if the contractor requests it
  3. At the final occupancy inspection
  4. Before concealment Correct answer.

Explanation

Concealed fire-resistive construction and piping must be inspected before covering so the official can verify compliance. Once concealed, the installation cannot be readily observed without destructive investigation.

Question 14Plan Review Fundamentals and Code Administration

After acceptance, who is responsible for maintaining fire protection systems in accordance with the adopted code?

  1. The product manufacturer
  2. The installing contractor indefinitely
  3. The authority having jurisdiction
  4. The owner or owner's designated representative Correct answer.

Explanation

The owner remains responsible for maintaining fire protection systems and arranging required inspection, testing, and maintenance. Contractors may perform the work, but responsibility does not transfer away from the owner.

Question 15Plan Review Fundamentals and Code Administration

Inspection, testing, and maintenance records for fire protection systems should be handled in which way?

  1. Kept only by the contractor
  2. Retained and made available to the authority having jurisdiction upon request Correct answer.
  3. Discarded after each test
  4. Sent to the manufacturer

Explanation

Records document that required inspection, testing, and maintenance have been performed and are retained for review by the authority having jurisdiction. Discarding them or keeping them only with the contractor prevents the owner from demonstrating compliance.

Question 16Plan Review Fundamentals and Code Administration

Before a new fire alarm system is placed in service, what must typically occur?

  1. A manufacturer audit
  2. An occupancy inspection only
  3. An acceptance test witnessed or approved by the authority having jurisdiction Correct answer.
  4. A plan review only

Explanation

An acceptance test demonstrates that the installed fire alarm system operates as designed and approved. The authority having jurisdiction typically witnesses or approves the test before the system is placed in service.

Question 17Plan Review Fundamentals and Code Administration

A contractor needs to change the location of a sprinkler riser from the approved plans. What should happen first?

  1. Obtain approval of a revised plan or field change from the authority having jurisdiction Correct answer.
  2. Ask the owner to approve it verbally
  3. Install it and note it on the as-built drawing
  4. Wait until the final inspection

Explanation

Changes from approved construction documents require review and approval before the work is installed. A verbal owner approval or later as-built note does not substitute for code administration approval.

Question 18Plan Review Fundamentals and Code Administration

A portion of a building is proposed for occupancy before the entire project is complete. What is the key plan review concern?

  1. Whether the occupied portion is complete for egress, fire protection, and separation Correct answer.
  2. The color of exit signs
  3. The contractor's payment schedule
  4. The number of parking spaces

Explanation

Partial occupancy requires the occupied area to have complete means of egress, fire protection, and separation from areas still under construction. Payment schedules, sign color, and parking counts do not address the life safety basis for phased occupancy.

Question 19Plan Review Fundamentals and Code Administration

For a performance-based fire safety design, the review should confirm which of the following?

  1. The building is unsprinklered
  2. No engineering calculations are submitted
  3. Only prescriptive code language is used
  4. Design fire scenarios and acceptance criteria are documented and met Correct answer.

Explanation

A performance-based design must document the design fire scenarios, assumptions, methods, and acceptance criteria and show that the proposed design meets them. Reviewing only prescriptive text or ignoring calculations does not establish equivalent performance.

Question 20Plan Review Fundamentals and Code Administration

Plan review for a high-piled storage area should specifically verify which item?

  1. The office furniture layout
  2. The parking lot lighting
  3. The landscaping plan
  4. Commodity classification and storage height used for sprinkler design Correct answer.

Explanation

Sprinkler protection for high-piled storage depends on commodity classification, storage height, aisle width, and related storage arrangements. These design inputs must be verified because they determine the required protection scheme.

Question 21Plan Review Fundamentals and Code Administration

The fire code official may grant a modification to a code requirement when which condition is present?

  1. The contractor is behind schedule
  2. The modification is supported by equivalent protection and does not compromise safety Correct answer.
  3. The owner wants to reduce construction cost
  4. The designer prefers a different product brand

Explanation

Modification authority is limited to cases where the proposed alternative provides equivalent or superior protection and meets the code's intent. Cost savings, schedule pressure, or product preference alone are not valid bases for a modification.

Question 22Plan Review Fundamentals and Code Administration

At project closeout, as-built fire protection drawings are important because they do which of the following?

  1. Document the installed system for future maintenance and code enforcement Correct answer.
  2. Eliminate the owner's maintenance duties
  3. Replace the need for inspections
  4. Transfer liability to the authority having jurisdiction

Explanation

As-built drawings record the system as actually installed and support future maintenance, modifications, and code enforcement. They do not replace inspections, transfer liability, or relieve the owner of maintenance responsibility.

Question 23Plan Review Fundamentals and Code Administration

During plan review, checking that a building's height and area are within code limits for the proposed construction type requires comparing what?

  1. The number of electrical outlets
  2. The proposed height and area with the construction-type limits Correct answer.
  3. The water bill
  4. The contractor's bid

Explanation

Height and area limits are tied to construction type and whether the building is protected by an automatic sprinkler system. The reviewer compares the proposed building envelope with the applicable limits in the adopted code.

Question 24Plan Review Fundamentals and Code Administration

Before conducting a required acceptance test, the installer should generally do which of the following?

  1. Wait for the certificate of occupancy
  2. Proceed without notifying anyone
  3. Notify the authority having jurisdiction so the test can be witnessed Correct answer.
  4. Remove all test records

Explanation

The authority having jurisdiction is typically notified so the acceptance test can be witnessed or otherwise approved. Proceeding without notification may require the test to be repeated, and test records must be retained.

Question 25Plan Review Fundamentals and Code Administration

Which record is most important for the authority having jurisdiction to keep to show that a project was reviewed and approved?

  1. Daily weather logs
  2. Supplier catalogs
  3. Approved plans, permits, and inspection records Correct answer.
  4. Contractor personnel files

Explanation

Approved plans, permits, and inspection records form the administrative record that the project was reviewed and approved under the adopted code. Supplier catalogs, weather logs, and personnel files do not establish code compliance.

Question 26Plan Review Fundamentals and Code Administration

What is the principal purpose of fire protection plan review by the authority having jurisdiction?

  1. To assign the contractor's bid price for the fire protection work
  2. To confirm that the proposed design complies with adopted codes and standards before construction begins Correct answer.
  3. To determine the market value of the proposed construction
  4. To establish the property insurance premium for the completed building

Explanation

Plan review is a code-administration step that checks construction documents for compliance before work starts, so deficiencies can be corrected at the drawing stage. It is not a valuation, insurance-rating, or bidding function.

Question 27Plan Review Fundamentals and Code Administration

A plan reviewer finds that a required sprinkler hydraulic calculation packet is missing from a permit application. What is the most appropriate action?

  1. Return the application as incomplete and specify the missing item Correct answer.
  2. Conduct a field flow test in place of the calculations
  3. Issue the permit and request the calculations after installation
  4. Approve the plans based on the sprinkler contractor's verbal assurance

Explanation

A submittal that lacks information needed to evaluate code compliance is incomplete and should be returned with a written deficiency list. Approval cannot rest on verbal assurances, and a field flow test does not replace hydraulic calculations.

Question 28Plan Review Fundamentals and Code Administration

Which edition of the adopted fire code generally governs the review of a new permit application?

  1. The edition adopted and in effect on the date the complete permit application is received Correct answer.
  2. The edition selected by the design professional
  3. The edition in effect when the building was originally constructed
  4. The most recent edition published, regardless of local adoption

Explanation

Jurisdictions enforce the edition adopted at the time of application unless a vested-rights or transition rule says otherwise. Designers cannot choose the edition, and a newer published edition is not enforceable unless adopted.

Question 29Plan Review Fundamentals and Code Administration

Plan review differs from field inspection primarily because plan review does which of the following?

  1. Verifies only the contractor's license status
  2. Is performed after the certificate of occupancy is issued
  3. Applies only to sprinkler systems
  4. Evaluates the design on paper, while inspection verifies the installed work Correct answer.

Explanation

Plan review checks the proposed design in construction documents before construction, whereas inspection confirms that the actual installation matches the approved documents and code. Both functions are necessary parts of code administration.

Question 30Plan Review Fundamentals and Code Administration

During review of a sprinkler plan, which item is most directly used to confirm that the available water supply meets system demand?

  1. A comparison of the waterflow test curve with the hydraulic calculation demand Correct answer.
  2. The building's occupancy classification only
  3. The contractor's installation schedule
  4. The manufacturer's warranty for the sprinkler heads

Explanation

Hydraulic analysis compares the available supply, derived from a waterflow test and adjusted to design conditions, with the required demand plus any required safety margin. Occupancy affects demand but does not by itself establish the available supply.

Question 31Plan Review Fundamentals and Code Administration

For egress review, the occupant load of a room is generally determined from which information?

  1. The number of parking spaces assigned to the building
  2. The building's construction type
  3. The floor area and the occupant load factor for the use Correct answer.
  4. The number of sprinkler heads installed in the room

Explanation

Occupant load is generally calculated by dividing the floor area by the occupant load factor for the use, with adjustments for fixed seating or other specific conditions in the code. Sprinkler head count, parking, and construction type are not the basis for that calculation.

Question 32Plan Review Fundamentals and Code Administration

A tenant proposes to change a mercantile space to a restaurant. What is the key plan review concern?

  1. Only the sign permit for the new business name
  2. Whether the new use meets the requirements for the new occupancy, including egress and fire protection Correct answer.
  3. Only the property tax classification
  4. Only the number of employees expected

Explanation

A change of use or occupancy triggers review against the code requirements for the new occupancy and may require upgrades to egress, fire protection, or other features. Business-name signs and tax classification do not determine fire code compliance.

Question 33Plan Review Fundamentals and Code Administration

What is the main benefit of a pre-application meeting between the design team and the AHJ?

  1. It clarifies submittal requirements and identifies code issues before formal review Correct answer.
  2. It eliminates the need for construction documents
  3. It transfers code compliance responsibility to the AHJ
  4. It guarantees permit approval without further review

Explanation

Pre-application meetings improve submittal quality by clarifying what must be submitted and by raising code issues early. They do not guarantee approval, eliminate documents, or shift compliance responsibility away from the applicant.

Question 34Plan Review Fundamentals and Code Administration

When a jurisdiction uses a third-party plan review consultant, who retains final authority for code compliance?

  1. The building owner
  2. The authority having jurisdiction Correct answer.
  3. The design professional of record
  4. The third-party consultant exclusively

Explanation

Delegating review work does not transfer the AHJ's legal authority or responsibility for code enforcement. The AHJ remains responsible for accepting and administering the review.

Question 35Plan Review Fundamentals and Code Administration

Which calculation is commonly reviewed to confirm that a fire alarm system will remain operational on secondary power?

  1. The duct smoke detector airflow velocity
  2. The fire pump churn pressure
  3. The sprinkler pipe schedule
  4. The battery capacity and standby/alarm load calculation Correct answer.

Explanation

Battery calculations demonstrate that secondary power can support the fire alarm system for the required standby and alarm periods. Pipe schedules, fire pump churn, and duct airflow do not establish fire alarm secondary power capacity.

Question 36Plan Review Fundamentals and Code Administration

A plan reviewer receives a fire protection submittal sealed electronically by a licensed engineer. What should the reviewer confirm?

  1. That the electronic seal is valid and applied by the responsible licensed professional Correct answer.
  2. That the file was printed on paper before review
  3. That the engineer's office is in the same county
  4. That the submittal uses the AHJ's preferred drawing color

Explanation

Electronic seals are acceptable where permitted, but the reviewer should confirm that the seal is valid and that the responsible licensed professional applied it. Printing, office location, and drawing color are not code-compliance criteria.

Question 37Plan Review Fundamentals and Code Administration

Which record best documents the AHJ's decision that a completed project was reviewed and approved?

  1. The waterflow test report alone
  2. The inspector's personal notes
  3. The approved plan set with review comments and the permit file Correct answer.
  4. The contractor's material purchase orders

Explanation

The approved plans, review comments, and permit file together form the official record of the review and approval decision. Purchase orders, a single test report, or informal notes do not provide that complete record.

Question 38Plan Review Fundamentals and Code Administration

For a performance-based design using fire modeling, what should the plan review include?

  1. Acceptance of the model output without checking inputs
  2. Only a comparison against the prescriptive tables
  3. A review of design fire scenarios, input assumptions, and sensitivity/uncertainty Correct answer.
  4. Only a check that the software is commercially available

Explanation

Performance-based review requires evaluating the design fire scenarios, input assumptions, modeling limitations, and sensitivity or uncertainty of results. Commercial availability of software or a simple prescriptive comparison does not validate the analysis.

Question 39Plan Review Fundamentals and Code Administration

Which statement best describes the effect of plan approval by the AHJ?

  1. It transfers design responsibility from the designer to the AHJ
  2. It guarantees that no field corrections will be required
  3. It authorizes construction of the reviewed scope but does not relieve the permit holder of compliance or later enforcement Correct answer.
  4. It eliminates the need for a certificate of occupancy

Explanation

Plan approval authorizes work within the reviewed scope, but the owner, designer, and contractor remain responsible for compliance. The AHJ can still require correction of code violations discovered later.

Question 40Plan Review Fundamentals and Code Administration

During review, a revised drawing replaces a previously approved sheet. What is the most reliable practice for code administration?

  1. Keep the revision under the same approval number without noting changes
  2. Rely on the contractor to remember which sheet is current
  3. Discard all prior sheets so only the latest drawing exists
  4. Use a revision control process that records the revision, date, and which sheets are superseded Correct answer.

Explanation

Revision control preserves a traceable record of what was approved and what changed, including dates and superseded sheets. Discarding records or relying on memory can lead to construction from outdated documents.

Question 41Building Construction and Fire Resistance

Which standard is used to determine the fire-resistance rating of an assembly such as a wall or floor/ceiling assembly?

  1. ASTM E108
  2. ASTM E136
  3. ASTM E84
  4. ASTM E119 Correct answer.

Explanation

ASTM E119 exposes a full assembly to a standard time-temperature curve and establishes the period before failure. UL 263 is the equivalent assembly fire test. ASTM E84 measures surface burning characteristics, not assembly fire resistance.

Question 42Building Construction and Fire Resistance

Under NFPA 101, interior finish with a flame spread index of 20 is classified as which class?

  1. Class B
  2. Class C
  3. Class D
  4. Class A Correct answer.

Explanation

NFPA 101 assigns interior finish classes by flame spread index: Class A is 0 to 25, Class B is 26 to 75, and Class C is 76 to 200. A flame spread index of 20 therefore falls in Class A. NFPA 101 does not use a Class D designation.

Question 43Building Construction and Fire Resistance

Which test determines whether a material qualifies as noncombustible?

  1. ASTM E136 Correct answer.
  2. ASTM E108
  3. ASTM E84
  4. ASTM E119

Explanation

ASTM E136 is the standard test that evaluates a material's behavior in a furnace to determine noncombustibility. Materials that pass are permitted where noncombustible construction is required. ASTM E119 rates assemblies, not material combustibility.

Question 44Building Construction and Fire Resistance

What is the highest fire-protection rating available for a listed fire door assembly?

  1. 3 hours Correct answer.
  2. 1½ hours
  3. 1 hour
  4. 2 hours

Explanation

Listed fire door assemblies are available with ratings up to 3 hours, which is the maximum recognized fire-protection rating. Lower ratings such as 1½ hours, 1 hour, and 20 minutes are common but are not the maximum. A door cannot be listed for a rating greater than 3 hours.

Question 45Building Construction and Fire Resistance

Which construction type is characterized by heavy timber structural members that derive fire resistance from their large cross section?

  1. Type V
  2. Type I
  3. Type IV Correct answer.
  4. Type II

Explanation

Type IV construction uses heavy timber members whose large dimensions provide inherent fire resistance through charring. Type I and Type II construction require noncombustible structural members. Type V construction typically uses light combustible framing.

Question 46Building Construction and Fire Resistance

A fire wall used to create separate fire areas must extend vertically from the foundation to which point?

  1. The underside of the roof deck Correct answer.
  2. The ceiling of the highest occupied floor
  3. The next horizontal fire barrier
  4. The top of a parapet only

Explanation

A fire wall must be continuous from the foundation to the underside of the roof deck and through concealed spaces to maintain the separation. Stopping at a ceiling or at an intermediate barrier would leave a path for fire spread. The wall must also be structurally stable.

Question 47Building Construction and Fire Resistance

Draftstopping installed in an attic is intended primarily to do which of the following?

  1. Seal pipe penetrations through fire walls
  2. Prevent vertical fire spread in concealed spaces
  3. Protect structural steel from fire
  4. Subdivide large concealed horizontal spaces Correct answer.

Explanation

Draftstopping subdivides large concealed horizontal spaces, such as attics and ceiling voids, to limit the movement of air, smoke, and fire. Fireblocking is the related measure used to cut off vertical concealed spaces. Through-penetration firestops seal pipe penetrations.

Question 48Building Construction and Fire Resistance

What is the minimum fire-resistance rating of a smoke barrier?

  1. 1½ hours
  2. 1 hour Correct answer.
  3. 2 hours
  4. ½ hour

Explanation

A smoke barrier is required to have a fire-resistance rating of at least 1 hour and must be continuous and smoke-tight. Its primary purpose is to restrict the movement of smoke, not to serve as a full fire wall. Higher ratings may be required where the barrier also serves another function.

Question 49Building Construction and Fire Resistance

In a high-rise building, an interior stairway serving as an exit enclosure generally must be enclosed with fire barriers having a rating of at least which value?

  1. 3 hours
  2. 1 hour
  3. 2 hours Correct answer.
  4. 1½ hours

Explanation

NFPA 101 requires exit enclosures in high-rise buildings to be separated by fire barriers with at least a 2-hour rating. In non-high-rise buildings, a 1-hour rating is generally permitted. The higher rating protects the stairway from fire on any floor during egress.

Question 50Building Construction and Fire Resistance

An air duct penetrates a 2-hour fire barrier. What is required at the penetration?

  1. A smoke detector
  2. A draftstop
  3. A listed fire damper Correct answer.
  4. A thermal barrier

Explanation

A fire damper is required where an air duct penetrates a fire barrier so that the opening does not reduce the barrier's fire-resistance rating. A smoke damper is added where the barrier is also a smoke barrier. Draftstops and thermal barriers serve different purposes.