- Initiating Device Circuit (IDC)
- Related: Conventional Zone, Manual Pull Station, Supervisory Signal
The wiring path that carries alarm or supervisory signals from automatic detectors and manual pull stations to the fire alarm control unit. It may serve a conventional zone or a group of addressable devices.
- Notification Appliance Circuit (NAC)
- Related: Voltage Drop Calculation, Temporal-3 Pattern
The circuit that supplies operating power from the control unit to audible and visible signaling appliances such as horns, speakers, and strobes, and that the panel monitors for wiring faults.
- Addressable Device
- Related: Signaling Line Circuit (SLC), Conventional Zone
A detector, module, or appliance on a signaling line circuit that carries its own unique address, so the control unit can report its exact location and status.
- Signaling Line Circuit (SLC)
- Related: Addressable Device, Class X Pathway
A supervised circuit that carries digital data between the control unit and addressable devices, letting many devices share a single wiring path while each is identified separately.
- Conventional Zone
- Related: Initiating Device Circuit (IDC), Addressable Device
A group of initiating devices wired on one circuit that the control unit reports as a single area, without identifying which individual device operated.
- Fire Alarm Control Unit (FACU)
- Related: Sequence of Operations, Notification Appliance Circuit (NAC)
The main panel that receives signals from initiating devices, applies its programmed logic, and activates notification appliances, relays, and off-premises transmitters.
- Waterflow Switch
- Related: Valve Supervisory Switch, Supervisory Signal
A device that senses sustained water movement in a sprinkler or standpipe pipe and sends an alarm signal, usually after a delay that ignores pressure surges.
- Valve Supervisory Switch
- Related: Supervisory Signal, Waterflow Switch
A device that monitors whether a control valve is fully open and sends a supervisory signal when the valve is closed or partly closed, indicating reduced protection.
- Duct Smoke Detector
- Related: Supervisory Signal, Fire Alarm Control Unit (FACU)
A detector installed on or in an air-handling duct that samples the airstream for smoke; on alarm it typically stops the fan and signals the control unit.
- Supervisory Signal
- Related: Trouble Signal, Valve Supervisory Switch
A signal showing that a system or protected condition is impaired but no fire exists, such as a closed valve, low sprinkler air pressure, or a detector switched off.
- Trouble Signal
- Related: Supervisory Signal, Ground Fault
A signal reporting a fault in the fire alarm system itself, such as an open circuit, a ground fault, loss of primary power, or a failed battery.
- Temporal-3 Pattern
- Related: Notification Appliance Circuit (NAC), Fire Alarm Control Unit (FACU)
The standard audible evacuation pattern used in the United States: three half-second pulses, a pause, three more pulses, repeated, to signal occupants to leave.
- Manual Pull Station
- Related: Initiating Device Circuit (IDC), Fire Alarm Control Unit (FACU)
A manually operated initiating device, mounted at a marked and accessible location, that lets a person send an alarm signal to the control unit.
- Rate-of-Rise Heat Detector
- Related: Initiating Device Circuit (IDC)
A heat detector that responds when the temperature climbs faster than a set rate, catching fast-growing fires before a fixed temperature threshold is reached.
- Supervising Station
- Related: Fire Alarm Control Unit (FACU), Trouble Signal
A facility, staffed or automated, that receives signals from protected premises, notifies the fire department, and documents the actions taken.
- Authority Having Jurisdiction (AHJ)
- Related: NFPA 72, Acceptance Test
The official or agency with legal authority to review plans, issue permits, conduct inspections, and enforce fire code requirements within a jurisdiction.
- NFPA 72
- Related: NFPA 70 Article 760, Inspection, Testing, and Maintenance (ITM)
The National Fire Alarm and Signaling Code, which sets requirements for designing, installing, testing, inspecting, and maintaining fire detection and signaling systems.
- NFPA 70 Article 760
- Related: NFPA 72, Primary Power Supply
The National Electrical Code article governing fire alarm system wiring methods, including power-limited circuit classification, conductor requirements, and installation rules.
- Detector Spacing
- Related: Duct Smoke Detector, Sequence of Operations
The maximum permitted distance between detectors, or between a detector and a wall or obstruction, set by code for the ceiling type and the detector listing.
- Sequence of Operations
- Related: Fire Alarm Control Unit (FACU), Acceptance Test, Alarm Verification
A written description of how the system reacts to each input: which devices respond, what outputs activate, and in what order. It is used to program and test the panel.
- Record of Completion
- Related: As-Built Drawings, Acceptance Test
A document signed by the installer and owner at system turnover that lists the installed equipment and its configuration and confirms installation matched the approved plans.
- As-Built Drawings
- Related: Record of Completion, Inspection, Testing, and Maintenance (ITM)
Drawings updated to show how the system was actually installed, including device locations, circuit routing, and field changes, kept for future service and inspections.
- Cross-Zoning
- Related: Alarm Verification, Sequence of Operations
A design in which two or more detectors or zones must be in alarm before the system treats the condition as a real alarm or releases a suppression system.
- Alarm Verification
- Related: Cross-Zoning, Sequence of Operations
A feature that resets a detector briefly after its first alarm and requires a second alarm within a set time before the signal is processed, reducing nuisance alarms.
- Class A Circuit
- Related: Class B Circuit, End-of-Line Resistor
A circuit whose wiring leaves the control unit and returns on a separate path, so it keeps operating with a single open or ground fault and uses no end-of-line resistor.
- Class B Circuit
- Related: Class A Circuit, End-of-Line Resistor
A circuit that does not return to the control unit, so a single open fault disables everything beyond it; an end-of-line resistor is used to supervise the wiring.
- Class X Pathway
- Related: Signaling Line Circuit (SLC), Pathway Survivability
A circuit arranged so a single open or short does not stop operation; faulted sections are isolated so the rest of the signaling line circuit keeps working.
- End-of-Line Resistor
- Related: Class B Circuit, Trouble Signal
A resistor installed at the far end of a Class B circuit that lets the panel monitor the conductors for opens and shorts.
- Primary Power Supply
- Related: Secondary Power Supply, NFPA 70 Article 760
The normal branch circuit supplying AC power to the fire alarm system; it must be dedicated to the system, clearly labeled, and not controlled by a switch.
- Secondary Power Supply
- Related: Primary Power Supply, Battery Calculation
The standby source, usually rechargeable batteries or a generator, that keeps the system operating for a code-specified time when normal AC power is lost.
- Battery Calculation
- Related: Secondary Power Supply, Voltage Drop Calculation
A design calculation adding standby and alarm currents to verify the battery can carry the system through the required standby period plus a full alarm period.
- Voltage Drop Calculation
- Related: Notification Appliance Circuit (NAC), Battery Calculation
A check performed during design to confirm enough voltage reaches the last appliance on each notification circuit so all devices operate within their listed range.
- Pathway Survivability
- Related: Class X Pathway, Class A Circuit
A classification describing how well circuit wiring resists fire damage, ranging from no added protection to a two-hour rated enclosure, required for voice and other critical circuits.
- Ground Fault
- Related: Trouble Signal, Class B Circuit
An unintended connection between a circuit conductor and ground that can keep a circuit from working properly; the panel must detect and annunciate it.
- Acceptance Test
- Related: Record of Completion, Sequence of Operations, Inspection, Testing, and Maintenance (ITM)
The functional test performed after installation, before the system is placed in service, showing every device and function works as designed; results are documented for the AHJ.
- Inspection, Testing, and Maintenance (ITM)
- Related: Acceptance Test, Sensitivity Test
The continuing program of periodic inspection, functional testing, and servicing required to keep a fire alarm system reliable after it has been accepted.
- Sensitivity Test
- Related: Inspection, Testing, and Maintenance (ITM), Acceptance Test
A test, often using a calibrated instrument, confirming that each smoke detector responds within the sensitivity range listed on its nameplate and in the design documents.