NV Fire Sprinkler key terms
NV Fire Sprinkler · Get comfortable with the vocabulary.
- Design Density
- Related: Remote Area, Hydraulic Calculation
The minimum water flow rate, in gallons per minute, that must be discharged over each square foot of protected floor area. It is selected from the occupancy hazard classification and drives sprinkler spacing and pipe sizing.
- Hydraulic Calculation
- Related: Design Density, Remote Area, Safety Factor
A step-by-step pressure-loss analysis that sums friction, elevation, and fitting losses from the most remote sprinkler back to the water supply to prove the system delivers the required density at the required pressure.
- Remote Area
- Related: Design Density, Hydraulic Calculation
The hydraulically most demanding cluster of sprinklers, defined by a minimum square footage, that must be calculated to flow at design density. Its size increases for dry systems, sloped ceilings, and certain combustibles.
- Safety Factor
- Related: Hydraulic Calculation, Water Supply Curve
An added margin of pressure or flow applied to a hydraulic calculation to cover unknowns such as pipe roughness, future changes, and water supply fluctuation. Local practice often requires a set percentage above demand.
- K-Factor
- Related: Design Density, Sprinkler Spacing
A discharge coefficient that describes how freely a sprinkler orifice passes water. Flow equals the K-factor multiplied by the square root of the pressure in psi, so a larger K-factor delivers more water at the same pressure.
- Hazard Classification
- Related: Design Density, Remote Area
The category assigned to an occupancy based on fuel load and expected heat release, such as light, ordinary group 1 or 2, or extra hazard. The classification sets design density, remote area size, and sprinkler spacing limits.
- Sprinkler Spacing
- Related: K-Factor, Deflector Distance, Branch Line
The maximum allowable distance between sprinklers and between the last sprinkler and a wall, governed by hazard classification, ceiling height, and sprinkler listing. It directly limits how much floor area each head protects.
- Deflector Distance
- Related: Sprinkler Spacing, Escutcheon
The vertical clearance required between a sprinkler deflector and the ceiling or roof deck so the spray pattern develops properly. It varies with sprinkler type, temperature rating, and whether construction is combustible.
- Branch Line
- Related: Cross Main, Sprinkler Spacing
The smaller pipe that carries water to individual sprinklers on a single line. Branch lines feed into cross mains, and their size and the number of heads they serve affect friction loss and balancing.
- Cross Main
- Related: Branch Line, Riser
The larger distribution pipe that supplies water to multiple branch lines and is fed by a feed main or riser. Cross main sizing is a key hydraulic variable and often determines whether the system balances.
- Riser
- Related: Riser Check Valve, Cross Main, Main Drain Test
The vertical supply pipe that connects the water source or underground main to the overhead sprinkler piping. It typically carries the main control valve, check valve, alarm devices, and drain connections.
- Riser Check Valve
- Related: Riser, Backflow Preventer
A one-way valve at the riser that prevents water from flowing backward out of the sprinkler system into the public supply. It also holds system pressure and is often combined with alarm and pressure switches.
- Backflow Preventer
- Related: Riser Check Valve, Hydraulic Calculation
A device that stops contaminated water from reversing into a potable supply. Reduced-pressure zone and double-check assemblies are common on sprinkler connections, and they add friction loss that must be included in calculations.
- Water Supply Curve
- Related: Safety Factor, Fire Flow Test
A graph of available pressure versus flow at a given point in the supply. The system demand point must fall below this curve, and the gap between them shows the margin available for the sprinkler system.
- Fire Flow Test
- Related: Water Supply Curve, Static Pressure, Residual Pressure
A field test using hydrants and pitot readings that measures static and residual pressure at known flows. The results are extrapolated to estimate the available water supply for design and to verify adequacy.
- Static Pressure
- Related: Residual Pressure, Fire Flow Test
The pressure in a water system when no water is flowing. It indicates elevation and supply head but says nothing about friction losses once water moves through the system.
- Residual Pressure
- Related: Static Pressure, Fire Flow Test
The pressure remaining at a test point while a measured flow is being drawn. Comparing it to static pressure reveals the friction loss characteristics of the supply main and the available flow.
- Churn Pressure
- Related: Rated Pump Flow, Pressure Reducing Valve
The maximum pressure a fire pump produces at zero flow. It is typically a percentage above rated pressure and must be considered when sizing piping, valves, and pressure-reducing devices downstream.
- Rated Pump Flow
- Related: Churn Pressure, Fire Pump Acceptance Test
The flow in gallons per minute at which a fire pump is listed to deliver its rated pressure. Pump curves are plotted from churn through overload flow to confirm the system demand falls within an acceptable range.
- Standpipe System
- Related: Hose Valve, Pressure Reducing Valve
A fixed piping arrangement with hose valves at various levels that lets firefighters connect hoses and reach upper floors or large areas. Classes are defined by hose size and intended user.
- Hose Valve
- Related: Standpipe System, Pressure Reducing Valve
A valved outlet on a standpipe where firefighters attach hose. Its size, thread type, and whether it includes a pressure-reducing feature must match local fire department requirements.
- Pressure Reducing Valve
- Related: Hose Valve, Churn Pressure
A device that lowers downstream pressure to a safe level for hoses or sprinklers. In standpipe systems it protects firefighters from excessive nozzle pressure at lower floors of tall buildings.
- Main Drain Test
- Related: Riser, Weekly Gauge Reading
A flow test through the riser drain that compares static and residual pressure to detect obstructions or closed valves in the supply. Results are recorded and compared with baseline readings over time.
- Weekly Gauge Reading
- Related: Main Drain Test, Inspector's Test Valve
A routine check of the system and supply pressure gauges on wet pipe systems to confirm normal conditions and detect leaks or valve problems. Abnormal readings trigger investigation and repair.
- Inspector's Test Valve
- Related: Waterflow Alarm, Main Drain Test
A test connection at the end of the most remote branch line that simulates a single sprinkler operating. Opening it verifies that water flows, alarms activate, and the delay time is within limits.
- Waterflow Alarm
- Related: Inspector's Test Valve, Valve Supervision
A device or switch that signals when water moves through the system piping. Testing confirms it activates within the required time after flow begins and transmits to the monitoring company.
- Valve Supervision
- Related: Waterflow Alarm, Main Drain Test
Electrical monitoring of control valves so that any unauthorized closure sends a trouble signal. Supervised valves must be sealed or locked, and tamper switches must be tested periodically.
- Fire Pump Acceptance Test
- Related: Churn Pressure, Rated Pump Flow
A documented field test at churn, rated flow, and overload flow that confirms the installed pump meets its curve. Results are compared with factory data and recorded for the authority having jurisdiction.
- Nevada State Fire Marshal
- Related: Authority Having Jurisdiction, Permit and Plan Review
The state official responsible for adopting and enforcing the statewide fire code and licensing certain fire protection activities. Local jurisdictions may adopt amendments that are stricter than the state code.
- Authority Having Jurisdiction
- Related: Nevada State Fire Marshal, Permit and Plan Review
The organization or individual empowered to interpret and enforce code requirements, approve plans, and accept completed work. It may be a state, county, or city fire agency depending on the project location.
- Permit and Plan Review
- Related: Authority Having Jurisdiction, As-Built Drawings
The process of submitting drawings, calculations, and product data to the enforcing agency and receiving approval before installation. Work performed without required permits can be ordered removed and may affect licensing.
- Contractor Licensing
- Related: Nevada State Fire Marshal, Lien
State or local authorization required to bid and perform fire sprinkler work. Licensing rules typically cover qualification, insurance, bonding, and the scope of work a licensee may legally perform.
- Lien
- Related: Contractor Licensing, Change Order
A legal claim against property for unpaid work or materials. Contractors must follow statutory notice and deadline requirements to preserve lien rights, and missing them can bar recovery.
- Change Order
- Related: Lien, As-Built Drawings
A written modification to the contract scope, price, or schedule signed by the parties. Without a signed change order, added work is often difficult to collect and may cause disputes.
- As-Built Drawings
- Related: Permit and Plan Review, Change Order
Final drawings updated to show actual installed conditions, including rerouted piping and added devices. They support future inspections, maintenance, and modifications and are often required at project closeout.
- Job Hazard Analysis
- Related: Lockout Tagout, Fall Protection
A pre-task planning method that identifies each step of a job, the hazards involved, and the controls to be used. It documents worker training and supports safe execution of high-risk tasks.
- Lockout Tagout
- Related: Job Hazard Analysis, Fire Pump Acceptance Test
A procedure for isolating energy sources before servicing equipment so that machinery cannot be re-energized unexpectedly. It requires locks, tags, verification, and clear communication among affected workers.
- Fall Protection
- Related: Job Hazard Analysis, Scaffold and Aerial Lift Safety
Systems and practices that prevent workers from falling from heights, including guardrails, personal fall arrest, and safe ladder use. Training and inspection of equipment are required before use.
- Scaffold and Aerial Lift Safety
- Related: Fall Protection, Job Hazard Analysis
Requirements for erecting, inspecting, and using elevated work platforms, including stable footing, guardrails, and trained operators. Unsafe use is a leading cause of serious injury in sprinkler installation.
- Clean Agent System
- Related: Special Hazard Occupancy, Pre-Action System
A suppression system using electrically nonconductive gaseous agents that extinguish fire without leaving residue. It is common in rooms with sensitive electronics where water damage would be costly.
- Pre-Action System
- Related: Clean Agent System, Remote Area
A dry pipe arrangement in which water is held back by a valve released by detection devices before sprinkler operation. It reduces accidental water discharge in areas where leaks are unacceptable.
- Special Hazard Occupancy
- Related: Clean Agent System, Hazard Classification
An area with unusual fuel, height, or process conditions that standard sprinkler design may not adequately protect. It often requires engineered alternatives such as foam, water mist, or special listing.
- Escutcheon
- Related: Deflector Distance, Sprinkler Spacing
The decorative plate that covers the gap between a sprinkler and the ceiling or wall surface. Recessed and concealed types affect deflector position and must match the sprinkler listing.