PDCA CPC · Keep the key ideas within reach.

Quick reference

Project Management and Pre-Construction Planning

  • Work breakdown structure (WBS) decomposes scope into deliverable-oriented levels; the 100% rule requires child elements to sum exactly to the parent's scope.

  • Critical path method (CPM) identifies the longest duration path through the network; total float = LS − ES = LF − EF, and zero-float activities lie on the critical path.

  • Pre-construction services typically include constructability review, value engineering, preliminary scheduling, and cost modeling before design is complete.

  • Responsibility matrix (RACI) assigns each task one Accountable party, plus Responsible, Consulted, and Informed roles; multiple accountable owners per task is a defect.

  • Design-bid-build sequence: programming → schematic design → design development → construction documents → bidding → award → construction.

  • Project delivery selection drivers: cost certainty vs. speed, owner risk tolerance, design completeness at award, and single-point vs. shared responsibility.

  • Milestone schedules carry no duration and mark contractual or decision gates; master schedules integrate design, procurement, permitting, and construction.

  • Change control board reviews scope changes against baseline; approved changes rebaseline cost and schedule and flow into contract modification.

Quick reference

Contracts, Specifications, and Construction Documents

  • Contract documents hierarchy is set by the agreement's order of precedence clause; typically agreement → general conditions → supplementary conditions → specifications → drawings.

  • AIA A201 General Conditions defines the architect's role in site visits as observing for general conformance, not supervising or warranting the contractor's work.

  • Specification divisions follow MasterFormat: Division 01 General Requirements governs submittals, substitutions, quality control, and temporary facilities.

  • Submittals are the contractor's representation that materials conform to the contract documents; review stamps (approved, approved as noted, rejected, revise and resubmit) do not relieve the contractor of compliance.

  • Shop drawings are contractor-prepared detailing of fabrication and installation; they supplement, and never override, the contract documents.

  • A performance specification states required results (e.g., thermal, structural) and leaves means and methods to the contractor; a prescriptive specification dictates products and methods.

  • Addenda modify bidding documents before bid opening; after award, changes are made by change order, construction change directive, or minor change in the work.

  • Differing site conditions clauses distinguish latent physical conditions (subsurface, unknown) from unknown physical conditions of an unusual nature.

Quick reference

Estimating, Bidding, and Cost Management

  • Quantity takeoff converts dimensions to units (LF, SF, CY, EA); concrete volume = length × width × depth ÷ 27 for cubic yards.

  • Bid price = direct costs (labor, material, equipment, subcontracts) + indirect costs (overhead, bonds, insurance, permits) + markup (profit, contingency).

  • Unit price contracts pay measured quantities at fixed unit rates; total price varies with actual quantities, so unbalanced bidding shifts risk to the owner.

  • Bid bond typically 5–10% of bid; performance and payment bonds each commonly 100% of contract price.

  • Contingency is an owner- or estimator-held allowance for known unknowns; it is not markup and is drawn down as risks resolve.

  • Life-cycle cost analysis discounts future operating, maintenance, and replacement costs to present value for comparison of alternatives.

  • Balanced bid check: front-end loading raises early items, back-end loading raises late items; both are detectable by comparing unit prices to the estimate.

  • Earned value: CPI = EV ÷ AC and SPI = EV ÷ PV; CPI below 1.0 means cost overrun, SPI below 1.0 means behind schedule.

Quick reference

Scheduling and Time Management

  • Activity-on-node network: ES = max(EF of predecessors); EF = ES + duration; backward pass gives LF and LS; float = LS − ES.

  • Free float is the delay an activity can absorb without delaying any successor; total float is delay without delaying project completion.

  • A near-critical path has low total float; resource leveling may consume float and shift the critical path, so re-run the network after leveling.

  • Crashing shortens duration by adding resources to critical activities; cost slope = (crash cost − normal cost) ÷ (normal time − crash time), crash lowest slope first.

  • Fast-tracking overlaps sequential activities to compress schedule and increases coordination and rework risk.

  • Time impact analysis measures delay by inserting the delay event into a fragnet at the point of occurrence and comparing completion dates.

  • Concurrent delay exists when two parties independently cause overlapping delay; under many contracts neither party recovers time-related damages for the concurrent period.

  • S-curve plots cumulative percent complete against time; progress below the planned curve indicates schedule slippage.

Quick reference

Site Supervision, Field Operations, and Quality Control

  • Three phases of quality control: preparatory (review submittals, hold pre-activity meeting), initial (first work item inspected), and follow-up (ongoing inspection).

  • Inspection and test plan (ITP) lists hold points (work cannot proceed without sign-off) and witness points (notification required, work may proceed).

  • Punch list records incomplete or defective work identified at substantial completion; final completion follows correction and closeout documents.

  • Substantial completion starts warranty periods and typically shifts risk of loss and insurance responsibility to the owner.

  • Field density testing for compacted fill commonly uses nuclear gauge or sand cone; required compaction is expressed as percent of maximum dry density from a Proctor test.

  • Concrete slump test (ASTM C143) measures consistency; cylinders are cured and tested for compressive strength at 7 and 28 days.

  • Daily reports document weather, manpower, equipment, deliveries, visitors, and delays; they are contemporaneous records used in delay and change claims.

  • Mock-ups establish workmanship benchmark and must be approved before general installation; approved mock-ups become the standard of acceptance.

Quick reference

Safety, Health, and Environmental Management

  • Hierarchy of controls: elimination, substitution, engineering controls, administrative controls, personal protective equipment (least effective).

  • OSHA focus four fatality causes: falls, struck-by, caught-in/between, and electrocution; fall protection is generally required at 6 feet in construction.

  • Competent person is trained to identify hazards and authorized to take prompt corrective action; required for scaffolding, excavations, and fall protection.

  • Excavations 5 feet or deeper require a protective system unless the competent person determines stable rock; access/egress required at 4 feet.

  • Hazard communication (HazCom) requires safety data sheets (SDS) on site and labeled containers for hazardous chemicals.

  • Incident rate = (number of recordable cases × 200,000) ÷ total hours worked; 200,000 represents 100 employees at 40 hours for 50 weeks.

  • Job hazard analysis (JHA) breaks a task into steps, identifies hazards per step, and specifies controls before work begins.

  • Stormwater pollution prevention plan (SWPPP) controls erosion, sediment, and discharges under NPDES permit requirements.

Quick reference

Construction Law, Ethics, and Professional Practice

  • A contract requires offer, acceptance, consideration, capacity, and legality; a subcontract is formed when the subcontractor's bid is accepted by the contractor's award.

  • Promissory estoppel can bind a subcontractor to a bid where the contractor reasonably relied on it and the subcontractor should have expected reliance.

  • Mechanic's lien secures payment for labor, material, or services improving real property; notice and filing deadlines are statutory and strict.

  • Statute of limitations bars an action after a fixed period; statute of repose bars claims after a fixed period from substantial completion regardless of discovery.

  • Economic loss doctrine generally bars negligence claims for purely economic losses where the parties have a contract; design professionals may still face negligence claims in some jurisdictions.

  • Standard of care for design professionals is the skill and care ordinarily exercised by similarly situated professionals, not perfection or warranty of result.

  • Conflicts of interest must be disclosed and managed; accepting gifts or payments from vendors or contractors can violate ethics rules and procurement law.

  • Total cost method of proving damages is disfavored absent proof that the owner caused all cost overruns; measured mile analysis compares impacted to unimpacted periods.

Quick reference

Leadership, Communication, and Team Management

  • Tuckman stages: forming, storming, norming, performing, adjourning; conflict peaks in storming and is resolved through clear roles and norms.

  • Situational leadership matches style to follower maturity: directing, coaching, supporting, delegating.

  • Communication model: sender encodes, message travels through a channel, receiver decodes, and feedback confirms; noise distorts the message.

  • Number of communication channels = n(n − 1) ÷ 2, where n is the number of participants; adding one member adds n channels.

  • Thomas-Kilmann conflict modes: competing, collaborating, compromising, avoiding, accommodating; collaborating seeks win-win and is preferred for important issues.

  • Partnering aligns owner, designer, and contractor goals through a charter, joint issue resolution, and periodic evaluation rather than contractual change.

  • Lessons learned capture is most effective at phase gates and project closeout, feeding organizational process assets.

  • Maslow and Herzberg: hygiene factors (pay, conditions) prevent dissatisfaction but motivators (recognition, growth) drive engagement.