PDCA CPC study plan
PDCA CPC · Give each week a clear focus.
8 weeks · About 7 hours per week
Project Management and Pre-Construction Planning
Map the project delivery lifecycle from initiation through closeout and write a one-page sequence diagram in your own words
Draft a pre-construction checklist covering permitting, site logistics, utility coordination, and constructability review
Produce a work breakdown structure for a sample mid-rise project down to three levels of detail
Identify the stakeholder set for that sample project and assign each a communication need and decision authority
Your checkpoint
A 6-8 page pre-construction planning package for one sample project containing the lifecycle diagram, checklist, three-level WBS, and stakeholder register.
Project Management and Pre-Construction Planning & Estimating, Bidding, and Cost Management
Convert the week-1 WBS into a quantity takeoff summary organized by CSI division
Build a bottom-up estimate with labor, material, equipment, and indirect costs, and apply markup for overhead and profit
Reconcile your estimate against a rough order-of-magnitude check using a unit-cost benchmark and explain any variance above 10 percent
Draft a bid package scope narrative that defines inclusions, exclusions, and allowances clearly
Your checkpoint
A complete estimate workbook with takeoff, pricing, markup, benchmark comparison, and a one-page variance memo.
Contracts, Specifications, and Construction Documents & Estimating, Bidding, and Cost Management
Compare the standard delivery methods (design-bid-build, design-build, CM at risk) and list the risk transfer each creates for the owner and contractor
Annotate a sample AIA-style agreement clause by clause for payment terms, retainage, indemnity, and termination
Read a set of general conditions and flag the ten clauses most likely to generate a claim
Explain how the hierarchy of contract documents resolves a conflict between drawings and specifications
Your checkpoint
A contract risk register listing at least 12 clauses with the risk, the party bearing it, and a proposed mitigation for each.
Scheduling and Time Management & Project Management and Pre-Construction Planning
Build a CPM network for the sample project with at least 40 activities and correct logic ties
Calculate the critical path, total float, and free float by hand for a 15-activity subset, then verify against software output
Assign durations using productivity rates and crew sizing rather than guesswork, and document the basis for each
Produce a resource-loaded schedule and identify the three activities most exposed to labor peaks
Your checkpoint
A resource-loaded CPM schedule with a written basis-of-schedule narrative and a hand-check appendix for the 15-activity subset.
Site Supervision, Field Operations, and Quality Control & Scheduling and Time Management
Write an inspection and test plan that maps hold points to each major work element
Draft a daily report template and a three-week look-ahead process, then simulate two weeks of updates against your schedule
Analyze a schedule delay scenario, classify it as excusable, compensable, or concurrent, and draft the time-impact narrative
Define a punch-list and turnover workflow from substantial completion to final acceptance
Your checkpoint
A field operations manual section containing the inspection and test plan, daily report template, look-ahead procedure, and a one-page delay analysis of a supplied scenario.
Safety, Health, and Environmental Management & Site Supervision, Field Operations, and Quality Control
Build a site-specific safety plan covering hazard analysis, PPE, fall protection, and emergency response
Map the major OSHA construction standards to the work activities in your sample project and note the trigger thresholds
Design a quality control program with measurable acceptance criteria and a nonconformance tracking log
Outline an environmental controls plan for stormwater, dust, noise, and waste diversion
Your checkpoint
A combined site safety, quality, and environmental plan of 8-10 pages with an activity-to-standard crosswalk table.
Construction Law, Ethics, and Professional Practice & Contracts, Specifications, and Construction Documents
Summarize the legal doctrines most tested in construction practice: lien rights, prompt payment, differing site conditions, and substantial completion
Work through five ethics scenarios involving bid shopping, undisclosed conflicts of interest, and certification of pay applications, and state the correct action with reasoning
Identify the licensing and professional responsibility obligations that apply to your jurisdiction
Draft a records retention and documentation policy that would support a claim or defend against one
Your checkpoint
An ethics and legal reference sheet plus five written scenario responses, each with a rule, an application, and a conclusion.
Leadership, Communication, and Team Management & Project Management and Pre-Construction Planning & Scheduling and Time Management
Build a communication plan that assigns message type, audience, channel, and cadence for a project team
Practice two conflict-resolution conversations using a structured interest-based script and record what changed in the outcome
Run a full timed 100-question practice exam under test conditions and score it by domain
Build a remediation list from your weakest two domains and schedule review sessions before exam day
Your checkpoint
A scored practice exam with a domain-by-domain analysis and a dated remediation plan covering the final review period.
Milestones
Week 2: You can produce a defensible estimate from your own takeoff without referring to a template, and explain every markup line.
Week 4: You compute critical path and float by hand correctly on the 15-activity subset and your software output matches within zero activities.
Week 6: You score at least 70 percent on a self-written 40-question quiz spanning domains 1 through 6, with no domain below 60 percent.
Week 8: You score at least 75 percent overall on the timed practice exam with no single domain below 65 percent, and your remediation plan is dated and specific.