PDCA CPC flashcards
PDCA CPC · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Total float formula
- Total float equals late start minus early start, or late finish minus early finish. Zero total float indicates a critical activity whose delay postpones project completion.
- Cost slope
- The additional cost per unit of time saved when crashing an activity, calculated as crash cost minus normal cost divided by normal time minus crash time.
- Free float
- The amount of time an activity can be delayed without delaying the early start of any successor activity. It is always less than or equal to total float.
- Time impact analysis
- A delay analysis method that inserts a fragnet representing a delay event into the schedule at its occurrence and compares the resulting completion date to the prior forecast.
- Earned value CPI
- Cost performance index equals earned value divided by actual cost. A value below one means the project has spent more than the work performed is worth.
- Unbalanced bidding
- A pricing strategy that raises unit prices on early or quantity-increased items and lowers others, increasing total payment under unit-price contracts and shifting risk to the owner.
- Performance bond
- A surety instrument, commonly equal to one hundred percent of contract price, guaranteeing the contractor will complete the work per the contract or the surety will fund completion.
- Contingency versus markup
- Contingency is an allowance for known unknowns drawn down as risks resolve. Markup is added profit and overhead. They are separate and should not be combined.
- Order of precedence
- A contract clause ranking documents to resolve conflicts, typically agreement, general conditions, supplementary conditions, specifications, then drawings, with specific over general.
- Performance specification
- A specification stating required end results such as capacity or thermal performance, leaving means, methods, and product selection to the contractor who warrants the result.
- Construction change directive
- A written owner-architect order directing a change before price and time are agreed. It is used when the contractor and owner cannot reach agreement on a change order.
- Differing site conditions
- Contract clause covering latent physical conditions materially different from those indicated, or unknown unusual conditions. It typically entitles the contractor to equitable adjustment.
- Shop drawing review effect
- The reviewer's stamp indicates conformance check only. It does not relieve the contractor of responsibility for compliance with contract documents or for dimensions and quantities.
- Substantial completion
- The stage when work is sufficiently complete for its intended use. It typically starts warranty periods, shifts risk of loss to the owner, and triggers retention release.
- Hold point
- A designated inspection stage in an inspection and test plan where work cannot proceed until the inspector or owner signs off following verification.
- Proctor test
- A laboratory test determining maximum dry density and optimum moisture content of soil. Field compaction is measured as a percentage of that maximum density.
- Punch list
- A record of incomplete or defective items identified at substantial completion that the contractor must correct before final completion and final payment.
- Competent person
- An individual trained to identify existing and predictable hazards and authorized to take prompt corrective measures, required for scaffolding, excavations, and fall protection.
- Recordable incident rate
- Calculated as recordable cases times two hundred thousand divided by total hours worked. The constant normalizes one hundred employees working forty hours for fifty weeks.
- Hierarchy of controls
- Risk mitigation ordered from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment.
- Excavation protective system
- Required for excavations five feet or deeper unless a competent person determines stable rock. A means of egress is required at four feet.
- Mechanic's lien
- A statutory claim against real property securing payment for labor, materials, or services that improved it. Notice and filing deadlines are strict and jurisdiction-specific.
- Statute of repose
- A statute barring claims after a fixed period from substantial completion or design, regardless of when the defect is discovered, unlike a statute of limitations.
- Promissory estoppel
- A doctrine that can enforce a subcontractor's bid where the contractor reasonably relied on it and the subcontractor should have expected that reliance.
- Standard of care
- The degree of skill and care ordinarily exercised by similarly situated professionals under similar circumstances. It is not a warranty of perfect results.
- Communication channels formula
- The number of communication channels equals n times n minus one, divided by two, where n is the number of participants in the project.
- Tuckman team stages
- The sequence forming, storming, norming, performing, and adjourning. Conflict typically peaks during storming and resolves as roles and norms clarify.
- Thomas-Kilmann conflict modes
- Five conflict approaches: competing, collaborating, compromising, avoiding, and accommodating. Collaborating pursues mutual gain and suits important issues with time available.
- Work breakdown structure
- A deliverable-oriented hierarchical decomposition of project scope. The one hundred percent rule requires child elements to sum exactly to the parent.
- RACI matrix
- A responsibility assignment tool labeling each task with Responsible, Accountable, Consulted, and Informed roles. Each task should have exactly one accountable party.
- Value engineering
- A structured review of design elements to improve value by reducing cost without reducing function, or improving function for the same cost.
- Constructability review
- A pre-construction review assessing whether the design can be built efficiently, safely, and economically, conducted before construction documents are finalized.