Lead SCADA Security Manager flashcards
Lead SCADA Security Manager · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Purdue Level 3.5
- The industrial DMZ between site operations and enterprise networks. Traffic terminates at proxies or brokers here, preventing direct routing between Level 3 and Level 4.
- Zone and conduit model
- IEC 62443 grouping method. Assets with common security requirements form a zone; conduits define allowed protocols, direction, and inspection points between zones.
- Target Security Level
- The SL-T value derived from risk assessment in IEC 62443-3-2. It states the protection a zone must achieve against a defined threat, distinct from vendor-claimed capability.
- GOOSE message constraint
- IEC 61850 Layer 2 multicast used for protection trips with millisecond latency budgets. Encryption is generally infeasible, so isolation and frame filtering are the controls.
- Passive OT monitoring
- Collecting traffic via SPAN ports or taps without sending packets. Preferred in Levels 0-2 because active scanning can crash fragile controllers or disturb real-time loops.
- TRITON attack target
- Malware that targeted safety instrumented systems, aiming to disable protection functions. It illustrates that SIS must be segmented from the basic process control system.
- Data diode
- A unidirectional gateway that permits telemetry to flow out of a control zone with no return path, replacing bidirectional firewall rules where only outbound data is needed.
- NIST CSF 2.0 Govern
- The function added in CSF 2.0 covering risk strategy, roles, policy, and supply chain. It sits alongside Identify, Protect, Detect, Respond, and Recover.
- C2M2 maturity indicators
- The Cybersecurity Capability Maturity Model for energy, with ten domains and maturity levels MIL0 to MIL3. Used to benchmark program capability, not to certify compliance.
- OT manual fallback plan
- Documented procedures and trained operators able to run the plant without SCADA for a stated duration. A core incident response requirement unique to operational technology.
- OT change management gate
- Every controller or HMI change passes a maintenance window, rollback plan, and post-change verification. Unmanaged changes are among the most common audit findings.
- Vendor remote access control
- Time-bound, logged, MFA-protected sessions through a jump host. Standing VPN access from a vendor into Level 2 is a control failure.
- OT detection metric
- Mean time to detect OT anomalies, percentage of OT assets inside monitored zones, and critical PLC firmware patch latency are more informative than raw alert counts.
- Tabletop exercise scope
- A discussion exercise including operations, engineering, IT security, and physical security. It is incomplete unless it reaches a safe-state decision for the process.
- Defense in depth for SCADA
- Layered controls: perimeter firewall, DMZ with replicated data, zone firewalls, host hardening, application allowlisting, and physical access control at the controller.
- DMZ historian pattern
- A replica historian in the industrial DMZ receives data from the control zone and serves enterprise users. No enterprise client queries the Level 2 historian directly.
- OT vulnerability prioritization
- Rank by exploitability and process exposure rather than CVSS alone. A critical score on an unreachable engineering tool ranks below a moderate score on an internet-facing HMI.
- Privileged access management
- Vaulting and brokering credentials for controllers, switches, and engineering workstations. Unique accounts plus MFA at jump hosts remove shared-account exposure.
- TLS termination proxy
- A protocol-aware intermediary that adds encryption for legacy devices lacking TLS support, avoiding weaker tunnels or firmware changes on fragile controllers.
- OT log sources
- Windows event logs, firewall and IDS alerts, PLC change events, and engineering workstation USB activity. These feed the SIEM and support forensic reconstruction.
- Offline configuration backup
- Versioned, offline copies of PLC, HMI, and switch configurations that are restore-tested. Ransomware recovery in OT depends on this more than on detection tooling.
- NERC CIP scope
- Mandatory reliability standards for bulk electric systems in North America, covering asset categorization, security controls, personnel, perimeters, and incident reporting.
- ISO/IEC 27001 evidence
- Certification requires risk assessment, a Statement of Applicability, and management review. It is a point-in-time audit, not continuous assurance of control operation.
- Policy hierarchy
- Board-approved policy, standards specifying mandatory controls, procedures with step-level instructions, and records evidencing execution. Each layer is auditable against the one above.
- Risk register entry
- Records owner, asset, threat, vulnerability, likelihood, impact, treatment choice, residual rating, and review date. Missing fields make the entry unauditable.
- Time-bound risk exception
- A formally approved acceptance of risk above the risk owner's authority, with a compensating control and expiry date. Open-ended acceptance is an audit exception.
- IEC 62443-4-1
- The secure development lifecycle requirement for product suppliers. Procurement can require attestation to it as a supply chain governance control.
- Recovery time objective
- The maximum tolerable downtime for a process before unacceptable impact. In SCADA it is set from physical process consequence, not from IT service tiers.
- Recovery point objective
- The maximum tolerable data loss measured in time. SCADA RPO is often near zero for process state because live state is re-read from field devices.
- Business impact analysis order
- Identify critical processes, map dependencies, set RTO and RPO, derive recovery strategies, then build and test plans. Skipping dependency mapping produces untested assumptions.
- Control center redundancy
- Geographically separate control centers with tested failover, redundant historians, and ring network topologies. Resilience depends on the failover being exercised, not just designed.
- OT ransomware recovery
- Isolate the zone, restore from offline backups, verify firmware integrity, rotate credentials, and validate controller logic before reconnecting to the network.
- Regulatory reporting clock
- Notification timelines such as NERC CIP-008 start at incident recognition, not resolution. Pre-agreed paths to regulators and leadership must exist before the event.