PECB Six Sigma Green Belt study materials
PECB Six Sigma Green Belt study resources

PECB Six Sigma Green Belt: Improve and Control Phases: Solution Implementation and Sustainment

PECB Six Sigma Green Belt · Work through your exam, one topic at a time.

All guide sections

Improve and Control Phases: Solution Implementation and Sustainment

Domain 5 tests whether an improvement sticks. Questions cover solution selection, piloting, control plans, control-chart choice and the reaction rules that stop gains from decaying.

Improve

  • Generate broadly, then screen with impact/effort, FMEA risk reduction and cost.
  • Pilot before full rollout; use DOE - screening designs first - to find the X settings that move Y.
  • Mistake-proofing hierarchy: eliminate the error, then prevent it, then detect it.
  • Verify the gain statistically (repeat the hypothesis test) and financially, then update standard work and documentation.

Control

  • Control plan: characteristic, specification, measurement method, sample size and frequency, owner, and the out-of-control action plan (OCAP).
  • SPC limits come from the process (±3σ), never from specifications. Specification limits state what the customer wants; control limits state what the process actually does.
  • Chart choice: X̄-R for subgrouped continuous data (n ≈ 2–5), I-MR for individuals, p for proportion defective, c or u for defect counts.
  • Signal rules include a point beyond 3σ, 8–9 consecutive points on one side of the centre line, and 6 steadily trending points.
  • Sustain with standard work, visual management, layered audits, training and a named process owner.

Worked example

A filling line runs subgroups of 5 every 30 minutes. X̄ = 250 mL and R̄ = 4 mL, so with A2 = 0.577 the X̄ limits are 250 ± 0.577 × 4, i.e. 247.7 to 252.3 mL. The last six subgroup means rise steadily. That is a trend signal even though every point lies inside the limits: investigate the filler head, do not widen the limits, and do not adjust a stable process point by point.

Traps that cost marks

Specification limits drawn on a control chart; tampering with common-cause variation; a chart that does not match the data type; no OCAP or named owner; declaring victory without post-improvement capability; letting the control plan lapse at handover.