- Rational method formula
- Q = CiA estimates peak storm runoff, where Q is discharge, C the runoff coefficient reflecting surface cover, i rainfall intensity, and A drainage area. It is valid only for small catchments.
- Percentage slope
- Percent slope equals rise divided by run, multiplied by 100. A 1:12 ramp is therefore 8.33%, while walkway cross slopes are usually held at 1-2% to shed water.
- BP 344 ramp standard
- Philippine accessibility rule: ramps have a maximum slope of 1:12, clear width of 1.20 m, landings every 6.00 m of run, and handrails on both sides at 0.90 m and 0.70 m.
- Contour interval
- The vertical distance in meters between two adjacent contour lines on a topographic map. Closely spaced lines indicate steep ground; widely spaced lines indicate gentle or flat terrain.
- Cut and fill balance
- A grading strategy that makes excavated soil volume equal fill volume on the same site, avoiding costly hauling and preventing import or export of soil off site.
- Philippine solar orientation
- The Philippines lies at roughly 5-20 degrees north latitude, so the sun is nearly overhead. Long building axes oriented east-west reduce low-angle east and west solar heat gain.
- Building setback
- The minimum horizontal distance required between a structure and the property line, established by the National Building Code and refined by the applicable local zoning ordinance.
- Viewshed analysis
- A map of all terrain visible from a chosen viewpoint, or of all points from which a landmark can be seen. It is used to protect vistas and position structures.
- Flexible pavement
- Pavement built from compacted subgrade, granular subbase, base course, and an asphalt or similar wearing surface. Loads spread gradually downward through the layers.
- Weep holes
- Small openings through a retaining wall, backed with gravel and filter fabric, that release trapped groundwater and relieve hydrostatic pressure behind the wall.
- Class A concrete mix
- Common Philippine proportion of 1:2:4 cement, sand, and gravel by volume, producing roughly 3,000 psi or 20.7 MPa, used for footings, walks, and slabs.
- Subgrade compaction
- The soil beneath pavement is compacted to at least 95% of its maximum dry density determined by the Standard Proctor test, preventing later settlement and pavement failure.
- Concrete curing period
- New concrete is kept continuously moist for about seven days so cement hydration can continue, improving strength and durability while reducing surface cracking.
- Drip emitter output
- A device delivering water slowly, typically 1-4 liters per hour, directly to the root zone. Efficiency is high because evaporation, wind drift, and runoff are minimal.
- Pole spacing rule
- A site lighting rule of thumb: luminaire spacing should be roughly three to four times the mounting height to produce reasonably even illumination on the ground.
- Expansion joint
- A planned gap between concrete slabs, paving units, or structures that allows thermal and moisture movement, preventing random cracking at uncontrolled locations.
- Narra
- Pterocarpus indicus, the Philippine national tree. A large hardwood used for shade and avenue planting, noted for its spreading crown and fragrant yellow flowers.
- Root flare
- The point where the trunk widens into the root system. It must sit at or slightly above finished grade; burying it suffocates roots and invites decay.
- Balling and burlapping
- A nursery method in which a soil root ball is dug around a tree and wrapped in burlap and twine to keep roots intact and moist during transport and transplanting.
- One-third mowing rule
- A turf management rule stating that at any single mowing, no more than one-third of the total grass blade height should be removed, to avoid stressing the plant.
- Hydrozoning
- Grouping plants with similar water requirements into separate irrigation zones, so each zone is scheduled according to its own need instead of the site average.
- Edge effect
- Greater species richness and density found where two habitat types meet, because the transition zone or ecotone offers resources from both adjoining communities.
- Rhizophora
- A mangrove genus with stilt or prop roots, typically planted on the seaward fringe. Species such as Rhizophora apiculata stabilize shorelines and buffer storm waves.
- Water hyacinth
- Eichhornia crassipes, a free-floating South American aquatic plant that is invasive in Philippine rivers and lakes, forming dense mats that block light, oxygen, and navigation.
- RA 9053
- Republic Act No. 9053, the Philippine Landscape Architecture Act of 2000, which regulates the practice and licensure of landscape architecture and defines the scope of professional services.
- Board of Landscape Architecture
- A three-member professional board under the Professional Regulation Commission that prepares and rates the licensure examination and recommends issuance of licenses to successful candidates.
- Ildefonso P. Santos Jr.
- Pioneer Filipino landscape architect named National Artist in 2006 under the Architecture category, recognized for park, plaza, and institutional ground designs in the Philippines.
- Design with Nature
- Ian McHarg's 1969 book that introduced overlay mapping, stacking site factor layers to identify land most suitable for development and land best left preserved.
- Garden City concept
- Ebenezer Howard's 1898 proposal for self-contained towns of limited population surrounded by productive agricultural greenbelts, combining town convenience with country air.
- Emerald Necklace
- A system of connected parks and parkways in Boston designed by Frederick Law Olmsted, linking the Boston Common to Franklin Park through continuous green corridors.
- PALA
- The Philippine Association of Landscape Architects, the accredited professional organization for the practice and the Philippine member association of IFLA.
- CPD units
- Continuing Professional Development credits required under RA 10912 as a condition for renewing a PRC professional identification card, which is renewed every three years.